Update for the Corporate Approach to Delivering an Asset Masterplan (CADAM) Programme

Agreed Scrutiny 1 paper

Resources & Delivering Value Scrutiny Board agreed this item on Monday 9 January 2023. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

i) To agree that progress with the CADAM was satisfactory.
Word for word from the decision Solihull published for this meeting. Source: democracy.solihull.gov.uk

Follow this further

Built from Solihull's papers

What the report saysPro

Report to Resources & Delivering Value Scrutiny Board

Executive summary

1.1To provide an update on the progress of the Corporate Approach to Delivering an Asset Masterplan (CADAM) Programme.

2. Decision(s) Recommended

2.1Review the progress so far with the programme; and

2.2Determine whether the progress with the programme is satisfactory. Report Title: Update for the Corporate Approach to Delivering an Asset Masterplan (CADAM) Programme

3. Matters for Consideration

3.1As a key Council transformational programme item, CADAM forms part of the Resources and Delivering Value Scrutiny Board work programme. The programme is planned to take place over three financial years and the last progress report was presented on 7th October 2021.

3.2Property is currently managed by a number of stakeholders and through a variety of different agreements or mechanisms including Corporate Property Services, Corporate Land, service departments and third parties (through lease agreements). Whilst this approach has worked well in the past, it is recognised that there are benefits to a corporate approach. The aim of this programme is to implement a Corporate Landlord approach to managing property with robust processes, procedures and evidenced decision making being established.

3.3The programme was impacted significantly by the Covid pandemic and suspended for a period whilst emergency response work was undertaken. Estates work undertaken in the recovery period focused on business retention, maximising the recovery of rent arrears and the development of initiatives to support economic growth in the Borough.

3.4A continued impact, that is affecting most businesses across the UK, is the approach to the future use of office space that remains in a state of flux as employers balance the many factors involved that include work/life balance, commuting costs, congestion, cost of living and the energy crisis. Elements of our asset masterplan inevitably have to find clarity in this area that will only develop over time.

3.5Since the last report further work has been completed to refine the programme deliverables taking into account the learning acquired so far. The programme now has two main objectives as shown below:

(a) To centralise assets previously within the responsibility of service departments; and

(b) To put in place a strategic approach which enhances strategic management, maintenance and decision making for our assets.

4. Update on Programme Progress

4.1The programme is planned to be delivered in a phased approach and Phase 1 consisted of corporate office buildings. Phase 2 assets comprise of Libraries and buildings held within the Adult Social Care directorate and work is currently ongoing to centralise these assets. The key actions to complete this process is the production of a Corporate Services Standard Offer (Standard Offer) which details the provision of services to ensure that the assets are compliant, secure and maintained to a good order.

4.2To date the centralisation of community libraries has been completed and assets used by Adult Social Care are the next to be centralised. In addition, work has started to centralise cemeteries, crematoria, and car parks with a programmed implementation date of March 2023.

4.3Work has also progressed on the Strategic Deployment arm of the programme which supports a longer-term view of the council’s asset needs.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update for the Corporate Approach to Delivering an Asset Masterplan (CADAM) ProgrammeReport 173 KB DownloadRead as text

At this meeting

Whole meeting
4MinutesAgreed 5MTFS Update – Budget Strategy 2023/24 – 2025/26On the agenda 6Follow up report – Building SafetyOn the agenda
7Update for the Corporate Approach to Delivering an Asset Masterplan (CADAM) ProgrammeThis decision

Who was there

17 of 19 attended
MP
Councillor Mark ParkerChairman, present
RH
Councillor Richard HoltVice-Chairman, apologies, sent representative
CD
Councillors DiaryOfficer, expected
AA
Councillor Ade AdeyemoCommittee Member, present
MA
Councillor Maggie AllenCommittee Member, present
YC
Councillor Yvonne ClementsCommittee Member, present
DG
Councillor Daniel GibbinCommittee Member, present
AH
Councillor Andy HodgsonCommittee Member, present
NM
Councillor Nathan MosesCommittee Member, present
JT
Councillor Joe TildesleyCommittee Member, apologies
BS
Councillor Bob Sleigh OBECommittee Member, present
LW
Linda WilsonOfficer, present, as expected, virtual

All 19 on the meeting page

On this subject at Solihull

Search all
  1. Update for the Corporate Approach to Delivering an Asset Masterplan (CADAM) ProgrammeThis decision
  2. Update on Corporate Approach to Delivering An Asset MasterplanAgreed

More from Solihull Resources & Delivering Value Scrutiny Board

All decisions
MeetingDecisionOutcome
8 Sep 2026 Minutesi. To agree the arising from the Resources and Delivering Value Scrutiny Board meeting held on 14 July 2026 were a tr... Agreed Open
8 Sep 2026 Resources and Delivering Value Scrutiny Board Work Programme 2026/27i. To identify a meeting date on which to consider the Council Motion of 7 th July 2026 concerning Leaseholder arrang... Approved Open
14 Jul 2026 Appointment of Chairman to the Resources and Delivering Value Scrutiny Board for the 2026/27 Municipal Yeari. To appoint Councillor K Thomas as Resources and Delivering Value Scrutiny Board Chairman for the 2026/27municipal ... Decided Open
14 Jul 2026 Appointment of Vice-Chairman to the Resources and Delivering Value Scrutiny Board for the 2026/27 Municipal YearTo appoint Councillor J Campbell as Resources and Delivering Value Scrutiny Board Vice-Chairman for the 2026/27munici... Decided Open
14 Jul 2026 Minutesi. To agree the draft arising from the Resources and Delivering Value Scrutiny Board meeting held on 16 March 2026 . Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies