Resolved
To agree the Resources and Delivering Value Scrutiny Board arising from the meeting held on 2 nd February 2023 as a true record.
Resources & Delivering Value Scrutiny Board agreed this item on Monday 17 April 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
To agree the Resources and Delivering Value Scrutiny Board arising from the meeting held on 2 nd February 2023 as a true record.
RESOURCES & DELIVERING VALUE SCRUTINY BOARD
6TH MARCH 2023 MINUTES
Present Councillors: M Parker (Chairman), R Holt, J Tildesley, D Gibbin, N Moses, A Adeyemo, A Hodgson, A Mackenzie
Officers Paul Johnson: Acting Chief Executive Alan Brown: Assistant Director, Highways & Environment Perry Wardle: Assistant Director, Growth & Development Martin Clayton: Head of Investment & Commercial Partnerships Lisa Whitton: Project Manager, Economy & Infrastructure Alan Smith: Head of Growth Programmes Alex Heath: Group Manager, Programme Development Paul Rogers: Democratic Services
Guests Mike Cooke: Vital Energi Limited Andrew Hirst: Womble Bond Dickinson
1. APOLOGIES FOR ABSENCE
Apologies were received from Councillor Y Clements, for whom Councillor A Mackenzie was substituting.
2. DECLARATIONS OF PECUNIARY OR CONFLICTS OF INTEREST
No declarations were received.
3. QUESTIONS AND DEPUTATIONS
No questions or deputations were received.
4. MINUTES
The Resources and Delivering Value Scrutiny Board:
RESOLVED:
To agree the Resources and Delivering Value Scrutiny Board Minutes arising from the meeting held on 2nd February 2023 as a true record.
5. SOLIHULL TOWN CENTRE LOW CARBON ENERGY NETWORK
The Scrutiny Board received a presentation from the Project Manager, Economy & Infrastructure, which highlighted key matters within the Scrutiny Board report and provided further context. Members were invited to ask questions after the Project Manager, Economy & Infrastructure had presented each theme within the presentation. Members raised a number of questions through the course of the presentation, which are summarised as follows:
1 RESOURCES & DELIVERING VALUE SCRUTINY BOARD
6TH MARCH 2023
Strategic Case
Councillor Gibbin queried what incentive was there for future phase customers to connect if there is a potential additional for connection cost of up to £0.50M. Members were advised that a connection could become mandated through the future creation of Heat Network Zones however, the greatest incentive was that there was no need to de-carbonise their own buildings at significant capital expense, the energy centre can also more quickly decarbonise further as technology develops. In respect to Touchwood Centre, the majority of the business tenants already had their own electric energy systems in place and therefore would not necessarily be compatible with connection to the Heat Network.
Economic Case
Councillor Adeyemo questioned the lifespan of the Heat Network plant and equipment/power units, specifically in relation to the 40-year investment period for the Heat Network project. Mike Cooke (Vital Energi) clarified that each component had a different design life but are all maintained by Vital Energi through their Operation and Maintenance contract. An example provided was that the lifespan of the Heat Network pipes is more than 50 years, with heat pumps more than 20 years.
The Head of Investment & Commercial Partnerships further advised that fiscal provision for the lifecycle of the Heat Network components had been accounted for in terms of replacement and renewal of key components.
Councillor Adeyemo noted that the term of the ESCo was for 15 years only and questioned whether the Council would be expected to request Vital Energi to supply and replace Heat Network equipment at the end of its life cycle over 15 years. Scrutiny Board were advised that the initial ESCo contract period was 15 years with provision to extend for a further 10 years. The key test was that whether the company can afford to run for 40 years since that is the period that is required to repay the debt. The company has the long term capacity to replace the Heat Network components.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MinutesMinutes | 330 KB | DownloadRead as text |
Follow Resources & Delivering Value Scrutiny Board at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Minutesi. To agree the arising from the Resources and Delivering Value Scrutiny Board meeting held on 14 July 2026 were a tr... | Agreed | Open |
| 8 Sep 2026 | Resources and Delivering Value Scrutiny Board Work Programme 2026/27i. To identify a meeting date on which to consider the Council Motion of 7 th July 2026 concerning Leaseholder arrang... | Approved | Open |
| 14 Jul 2026 | Appointment of Chairman to the Resources and Delivering Value Scrutiny Board for the 2026/27 Municipal Yeari. To appoint Councillor K Thomas as Resources and Delivering Value Scrutiny Board Chairman for the 2026/27municipal ... | Decided | Open |
| 14 Jul 2026 | Appointment of Vice-Chairman to the Resources and Delivering Value Scrutiny Board for the 2026/27 Municipal YearTo appoint Councillor J Campbell as Resources and Delivering Value Scrutiny Board Vice-Chairman for the 2026/27munici... | Decided | Open |
| 14 Jul 2026 | Minutesi. To agree the draft arising from the Resources and Delivering Value Scrutiny Board meeting held on 16 March 2026 . | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.