Resolved
The Cabinet Member RESOLVED to approve the refreshed attached at Appendix A to the report.
CPH Resources Decision Session approved this item on Monday 4 March 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
The Cabinet Member RESOLVED to approve the refreshed attached at Appendix A to the report.
Meeting date: 4 March 2024
Report to: Cabinet Member for Resources
Report title: Risk Management Policy
Report from: Director of Resources
Report author/lead Mark Wills - Health, Safety and Risk Manager contact officer: [email protected] 0121 704 6829
Wards affected: ☒ All Wards | ☐ Bickenhill | ☐ Blythe | ☐ Castle Bromwich | ☐ Chelmsley Wood | ☐ Dorridge/Hockley Heath | ☐ Elmdon | ☐ Kingshurst/Fordbridge | ☐ Knowle | ☐ Lyndon | ☐ Meriden | ☐ Olton | ☐ Shirley East | ☐ Shirley South | ☐ Shirley West | ☐ Silhill | ☐ Smith’s Wood | ☐ St Alphege
Public/private Public report:
1. Executive Summary The purpose of this report is to seek the Cabinet Member for Resources approval for the Council’s updated Risk Management Policy. The Audit Committee endorsed the Policy at their meeting on 12th February 2024.
2. Decision(s) Recommended The Cabinet Member for Resources is asked to approve the refreshed Policy attached at Appendix A.
3. Matters for Consideration The Council recognises that there are risks in everything it does and has a duty to manage these risks in a balanced, structured, and cost-effective way. Approval and publication of this Risk Management Policy demonstrates this intention. The policy: • explains the Council’s underlying approach to risk management; • documents the roles and responsibilities of Members, officers and other key parties for the ongoing management of risk; • explains key aspects of the Council’s risk management approach; and • forms part of the Council’s overall internal control and governance arrangements.
The policy is reviewed every 3 years to ensure that the Council’s risk management arrangements continue to be proportionate and appropriate to the Council’s needs. The last review to the policy was in 2020 where no material changes were made to the policy.
The risk management policy has been updated to reflect the maturity of the Council’s risk management practice and the importance of good risk management in the current climate of uncertainty nationally as well as globally. Some of the changes made to the policy are:
i.) The risk management process has been simplified from the previous 7 step model to a 4-step model - align, assess, respond and monitor.
ii.) Partnership working risks are now recognised, with the roles and responsibilities definitions being expanded to reflect this change.
iii.) The risk likelihood and impact matrix has been updated from the current 3x3 matrix to a 5x5 matrix to provide a more granular view and assessment of risk.
iv.) Risk impact scales have been updated to include impact measures on the environment and employees. The scales have been reworded to enable risk impact to be captured accurately for a range of risks including operational, project and programmes as well as strategic risks.
v.) The Council articulates the type and amount of risk they wish to take in their risk appetite. The updated policy introduces appetite-based risk management to improve decision making on resources allocated to mitigate risks to a proportionate level.
The policy updates are in line with guidance provided by ISO31000 (international standard for the design, implementation and maintenance of risk management) and the Orange book, (UK Government).
4. What options have been considered and what is the evidence telling us about them?
The following options have been considered while updating the risk management policy:
i.) Do nothing – This will maintain the Council’s current risk management practice but will continue to provide challenges around demonstrating risk movement within the constraints of a 3x3 matrix. It also limits the differentiation between risks, which can constrain or over emphasise the view on risk mitigations, particularly if the Council need to prioritise future actions in the context of more limited financial resources.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
AppendixAppendix | 637 KB | Download |
PDF |
Risk Management PolicyReport | 136 KB | DownloadRead as text |
Follow CPH Resources Decision Session at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Sep 2026 | ApologiesApologies for absence were received from A. Felton (Director of Resources) due to other Council business. | Decided | Open |
| 14 Sep 2026 | Declarations of Pecuniary or Conflicting Interest from MembersNo Declarations of Interest were received. | Decided | Open |
| 14 Sep 2026 | Questions and DeputationsNo questions or deputations were received. | Decided | Open |
| 14 Sep 2026 | Applications for Discretionary Rate ReliefHaving considered the report, the Cabinet Portfolio Holder for Resources: | Decided | Open |
| 14 Sep 2026 | Debt Monitoring Report - Quarter 1 2026/27Having considered the report, the Cabinet Portfolio Holder for Resources: | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.