Children’s Services Capital Programme 2025-28 Mid year update
ApprovedCommittee1 paper
AI summarySolihull Cabinet Member for Children and Education approved mid-year update to the Children's Services Capital Programme 2025-28, totalling £27.380m, including merging budgets to expand Reynalds Cross Special School by up to 30 pupils and approving public consultation from February 2026.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedCapital programme update and consultation approved
Money£27.380mTotal 3 year investment, 2025-28
What happens nextConsultation from February 2026On expanding Reynalds Cross Special School
Who it affectsSolihull children and SEND provisionSchools, parents and pupils borough-wide
What was decided
Amalgamated the two former Reynalds Cross expansion budgets into a single project line within the 2025/26 Children's Services Capital Programme, and noted the 3 year rolling programme at Appendix A. Report P5, P10, P29
Approved a period of consultation on the proposal to expand Reynalds Cross Special School, with officers to begin consulting parents, schools and the wider community from February 2026. Report P6, P11, P30
Why
To update the fully funded 2025-28 programme to reflect the mid-year position, with overall investment standing at £27.380m across the three year period. Report P1, P2, P8, P66
The school and its senior leadership raised concerns that the current Reynalds Cross environment is increasingly difficult for more complex pupils, prompting a revised solution that addresses principal concerns and adds capacity for up to 30 additional pupils. Report P27, P28
Department for Education guidance on making significant changes (prescribed alterations) to maintained schools requires a statutory consultation process for an expansion greater than 10% or 20 pupils. Report P30
What happens next
Officers to begin a formal period of consultation with parents, schools and the wider community on the Reynalds Cross expansion from February 2026. Report P11
Officers to continue pursuing the Department for Education for opportunities within the School Rebuilding Programme while ensuring the Reynalds Cross works do not compromise a future full rebuild. Report P31
Officers to plan deployment of the High Needs Capital Provision Allocation, awarded in three instalments starting in Summer 2026, to create new specialist places in other ways. Report P33
The money
£27.380m Revised total investment across the 3 year Children's Services Capital Programme 2025-28 Report P8, P66
£6.701m Revised 2025/26 budget within the Children's Services Capital Programme Report P66
Options considered
Chosen: Merge the two former Reynalds Cross budgets into one project line and approve consultation on expansion by up to 30 pupils. Addresses the school's concerns about increasingly complex pupils while still expanding capacity within the previously approved budget Report P5, P10, P11, P27, P28, P29, P30
Implications
Financial: The programme remains fully funded, with the revised total standing at £27.380m for 2025-28 and £6.701m for 2025/26, drawn from the funding streams set out in Appendix A. Report P2, P8, P66
Legal: The local authority has a legal duty to secure sufficient childcare places in its area in line with its published sufficiency plan. Report P68
Equalities: All existing and future school building provision will take full account of the Public Sector Equalities Duty and access needs for staff, children and visitors with disabilities. Report P72
Climate: A fabric first approach to energy efficiency is adopted where possible, focusing on roofing and windows, and officers are exploring specifications for operational net zero on all new developments. Report P16, P59, P60
Risk: Corporate Risk Registers are maintained for the programme and there are no red risks to report; the position is currently improving through collaborative working with schools. Report P70, P71
Other: The Department for Education confirmed on 12 December 2025 that it will not directly fund the new 150 place special school previously awarded under the Free School Programme, while also awarding a top-up to the High Needs Capital Provision Allocation. Report P32, P33
Who and where
Children and young people in Solihull, particularly those with special educational needs and disabilities Report P2, P53
Parents, schools and the wider community to be consulted on the Reynalds Cross expansion Report P11
Pupils and staff at Reynalds Cross Special School, including up to 30 additional places Report P27, P28
Pupils and staff at Hazel Oak Special School, where suitability works are ongoing Report P34
Key Stage 5 pupils at Forest Oak Special School, now relocated to Tudor Grange Academy Kingshurst campus Report P34
Timeline
October 2024: Draft local plan withdrawn, creating uncertainty in planning of school places Report P23
12 November 2024: Mainstream school sufficiency plan presented to the Cabinet Portfolio Holder Report P14
19 December 2024: 2025/26 maintenance programme approved by Cabinet Member Report P38
12 December 2025: Department for Education confirmed it will not directly fund the new 150 place special school and awarded a top-up High Needs Capital Provision Allocation Report P32, P33
February 2026: Consultation on the proposal to expand Reynalds Cross Special School to commence Report P11
Spring 2026: Education Sufficiency Strategy expected to be approved; design and start of works at Burman Infant School planned Report P13, P38
Summer 2026: First instalment of the High Needs Capital Provision Allocation to be received Report P33
Plain English for the jargon
CSCP: Children's Services Capital Programme
SEND: Special Educational Needs and Disabilities
EHCP: Education, Health and Care Plan
DSG: Dedicated Schools Grant
HNB: High Needs Block
DfE: Department for Education
PSED: Public Sector Equalities Duty
Prescribed alterations: Significant changes to maintained schools set out in Department for Education guidance
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6
Resolved
(i) That the change to the Children’s Services Capital Programme 2025/26 to include the amalgamation of the two former budgets for the Reynalds Cross expansion detailed at paragraph 5.10 be approved and note the overall 3 year rolling financial programme that is more particularly detailed at Appendix A; and (ii) That a period of consultation on the proposal to expand Reynalds Cross Special school as detailed in paragraph 5.11 be approved.
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
Report to CPH Children and Education Decision Session
Executive summary
This report presents a mid- year update to the Children’s Services Capital Programme for 2025-28.
The fully funded Children’s Services Capital Programme for 2025-28 which is attached at Appendix A represents an investment in the Solihull schools’ and early years estate and has been updated to reflect the mid-year position.
2. Decision(s) Recommended
The Cabinet Member for Children and Education is asked to approve:
The change to the Children’s Services Capital Programme 2025/26 to include the amalgamation of the two former budgets for the Reynalds Cross expansion detailed at paragraph 5.10 and to note the overall 3 year rolling financial programme that is more particularly detailed at Appendix A.
To seek approval for a period of consultation on the proposal to expand Reynalds Cross Special school as detailed in paragraph 5.11.
3. Matters for consideration
This report seeks to update the programme to reflect the mid- year position for 2025-26 which is attached at Appendix A. Presently the update, which remains fully funded as illustrated through the funding streams within Appendix A, represents a revised total investment of £27.380m in the school estate for the three year period.
The following items require approval:
The change to the Children’s Services Capital Programme 2025/26 to include the amalgamation of the two former budgets for the Reynalds Cross expansion detailed at paragraph 5.10 and to note the overall 3 year rolling financial programme that is more particularly detailed at Appendix A.
Permission for officers to carry out a period of consultation with parents, schools and the wider community on the proposal to expand Reynalds Cross School from February 2026.
Background
The Children’s Services Capital Programme (CSCP) includes projects which address the sufficiency, suitability and condition of the schools’ estate.
The draft Education Sufficiency Strategy has been subject to a period of stakeholder engagement and feedback during the Autumn 2025 and is expected to be approved in early Spring 2026. The strategy sets out the strategic vision for the delivery of school places and is supported by three annual sufficiency updates covering mainstream, early years and SEND which contain the evidence base for any organisational or physical changes in places.
The mainstream school sufficiency plan was presented to the Cabinet Portfolio Holder at their Children and Education Decision Session on 12th November 2024 and will be updated later this year. The draft early years and SEND annual sufficiency plans have been drafted and been subject to a period of stakeholder engagement pending approval later this year.
Appraising the suitability of the school estate continues to be about ensuring our school premises are fit for purpose to support the effective delivery of teaching and learning and the drive to raise education standards. Asset management planning with individual schools continues to enable suitability issues to be identified and where possible addressed, often in works that are complementary to other projects focused upon places and condition. This can also be through the Landlord Approval process where schools have proposed using their own funding, given the priority they attach to such schemes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow CPH Children and Education Decision Session at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.