Local Enterprise Support and High Street and Growth Incubator
AgreedCommittee2 papers
AI summarySolihull Cabinet Member accepted two West Midlands devolved funding streams: £164,000 a year for three years of Local Enterprise Support, and £944,444 over three years for the High Street and Growth Incubator, both focused on local SMEs and Solihull town centre.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedLocal Enterprise Support and High Street and Growth Incubator
Money£164,000/year + £944,444 totalThree year Integrated Settlement, April 2026 to March 2029
What happens nextStart delivery April 2026Year one of HS&GI focused on engagement and planning
Who it affectsSolihull SMEs and town centreStart-ups, established businesses, care leavers, town centre visitors
What was decided
Accepted two devolved funding streams to SMBC under the Economic and Regeneration pillar of the West Midlands Integrated Settlement. Report P6
Agreed the proposed delivery programme for Local Enterprise Support, linking to the wider West Midlands business support landscape. Report P6
Agreed the High Street and Growth Incubator focus on Solihull town centre, and initial proposals covering stakeholder engagement, meanwhile uses, and public realm work. Report P7, P8
Why
UK Shared Prosperity Funding ends in March 2026, and the three year Integrated Settlement provides replacement economic and regeneration funding through the WMCA. Report P13, P14
Solihull is ranked 7th nationally for businesses with strong growth potential, and has below average start-up rates but strong survival rates, suggesting a need for targeted local support. Report P23, P25
Solihull town centre draws a wide catchment, accounts for 17% of local retail units, and has a Town Centre Masterplan providing a strategic fit for HS&GI activity. Report P37, P38, P40
What happens next
Commission a provider to deliver a blend of start-up and established SME support, working with the existing Community Hub in North Solihull run by Colebridge Trust. Report P44, P45
Use year one of HS&GI for stakeholder engagement, project feasibility and planning, with capital works weighted to years two and three. Report P33, P50
Coordinate across SMBC teams including Corporate Land, Public Realm, Highways and Regulatory Services, with reports back to the WMCA on delivery. Report P64, P75
The money
£164,000 Local Enterprise Support allocation for financial year 26/27, proposed to continue at the same level for the following two years Report P68
£944,444.44 High Street and Growth Incubator funding for the three year programme Report P69
£666,666.67 HS&GI capital allocation across the three years Report P69
£277,777.78 HS&GI revenue allocation across the three years Report P69
£111,111.11 Year 1 HS&GI capital Report P71
£92,592.59 HS&GI revenue for each of years 1, 2 and 3 Report P71
£222,222.22 Year 2 HS&GI capital Report P71
£333,333.33 Year 3 HS&GI capital Report P71
Options considered
Chosen: Commission a single provider to deliver start-up and established SME support tailored to local priorities, linked to the regional framework. Evidence shows start-up and everyday economy support is best delivered locally, with the provider acting as a front door to specialist regional programmes Report P28, P44, P46
Implications
Financial: Local Enterprise Support is set at £164,000 per year and HS&GI at £944,444.44 over three years, with match funding expected from other WMCA streams and the public or private sector. Report P68, P69, P72
Legal: Funding comes with its own grant agreements and terms administered through the WMCA. Report P73
Equalities: The programme targets underrepresented groups, care leavers, those furthest from the labour market, and entrepreneurs in North Solihull, and town centre projects may improve pedestrian accessibility. Report P65, P76, P77
Climate: Local Enterprise Support will link businesses into regional sustainability programmes and High Street activity will take account of the local environment. Report P59
Risk: Delivery, underperformance and financial forecasting will be reviewed regularly and reported to the WMCA under grant agreements. Report P75
Staffing: Internal engagement is underway across Corporate Land, Public Realm, UK Central development, Highways and Regulatory Services to join up delivery. Report P64
Who and where
Start-up entrepreneurs and established SMEs in Solihull, including the everyday economy such as retail, hospitality and wholesale Report P12, P24, P26, P27
Solihull town centre businesses, visitors and the wider catchment served by the centre Report P37, P38
Care experienced young people and residents of North Solihull Report P45, P65, P76
Community Hub users in North Solihull currently supported by Colebridge Trust Report P45
Timeline
March 2026: UK Shared Prosperity Funding comes to an end Report P13
1 April 2026: New West Midlands Economic Development Vehicle launches within the West Midlands Growth Company, and Integrated Settlement period begins Report P15, P67
26/27: First year of delivery, with HS&GI focused on engagement and project development and planning Report P33, P50, P68
27/28: Second year, with capital works on HS&GI weighted to begin Report P71
28/29: Third and final year of the Integrated Settlement, with the largest share of HS&GI capital Report P71
March 2029: End of the three year Integrated Settlement Report P67
Plain English for the jargon
HS&GI: High Street and Growth Incubator, a national £10m fund devolved to three Strategic Authorities including the WMCA for high street regeneration
WMCA: West Midlands Combined Authority, which administers the Integrated Settlement
EDV: Economic Development Vehicle, a new body within the West Midlands Growth Company launching on 1 April 2026
WMGC: West Midlands Growth Company
SME: Small to medium sized enterprise
Integrated Settlement: The three year West Midlands funding settlement from April 2026 to March 2029 covering Economy and Regeneration, transport, housing and other areas
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5
Resolved
The Cabinet Member: 1. Accepted the two devolved funding streams to SMBC – the regional Local Enterprise Support and HS&GI programme, part of the Economic and regeneration pillar of the Integrated Settlement. 2. Agreed the proposed delivery programme for Local Enterprise Support, linking to the new wider West Midlands business support landscape. 3. Agreed the geographical location for the focus of the HS&GI funding as Solihull town centre, in accordance with the place prioritisation framework as set by the West To agree the proposals for Local Enterprise Support in Solihull, a key programme in the new West Midlands business support framework, aiming to establish refreshed local interventions to target hyper local business growth priorities, alongside a new regional high growth service. To approve the 26 March 2026 Midlands Combined Authority; and 4. Agreed the initial proposals for the HC&GI programme, including stakeholder engagement and delivery plan development, supporting activities such as improved public realm and accessibility, meanwhile uses to drive footfall and integration with the wider plans identified in the Solihull Town Centre Masterplan.
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
Report to CPH Economy, Business & Skills Decision Session
Executive summary
This report outlines two devolved funding streams to Solihull MBC, part of the Economy and Regeneration pillar of the three year Integrated Settlement for the West Midlands (April 2026 – March 2029).
Cabinet are asked to agree the proposals for Local Enterprise Support in Solihull, a key programme in the new West Midlands business support framework, aiming to establish refreshed local interventions to target hyper local business growth priorities, alongside a new regional high growth service.
Alongside this, Cabinet are asked to approve the approach to the new West Midlands High Street and Growth Incubator (HS&GI) funding, supporting town centre vacancy rates and regeneration activities.
2. Decision(s) Recommended
The Cabinet member is asked to:
Accept the two devolved funding streams to SMBC - the regional Local Enterprise Support and HS&GI programme, part of the Economic and Regeneration pillar of the Integrated Settlement. Agree the proposed delivery programme for Local Enterprise Support, linking to the new wider West Midlands business support landscape (Appendix A).
Agree the geographical location for the focus of the HS&GI funding as Solihull town centre, in accordance with the place prioritisation framework as set by the West Midlands Combined Authority.
Agree the initial proposals for the HS&GI programme, including stakeholder engagement and delivery plan development, supporting activities such as improved public realm and accessibility, meanwhile uses to drive footfall and integration with the wider plans identified in the Solihull Town Centre Masterplan.
3. Matters for Consideration
As key priorities within the Council’s Economic Strategy, a number of programmes have been progressed to support start-up entrepreneurs and established small to medium enterprises (SMEs), predominantly using the funding from the ‘double devolved’ UK Shared Prosperity Funding for Solihull.
The nature of the devolved funding, whilst having set regional outputs and outcomes, has allowed prioritisation for projects and programmes that directly support the Strategy and our business base, with flexibility to adapt to changes in demand and take up.
Through our commissioning approach, we have maintained a balance of provision of tailored support for our SME community, including running a successful start-up programme, supporting to date over 75 entrepreneurs this financial year.
UK Shared Prosperity Funding is coming to an end in March 2026, but additional funding through the West Midland’s three-year Integrated Settlement will be available for economic and regeneration programmes, administered through the West Midlands Combined Authority (WMCA).
The Economy pillar of the Integrated Settlement combines a variety of funding streams, including Local Growth Fund (supporting Local Enterprise Support) and HS&GI funding from the Ministry of Housing, Communities and Local Government and Department of Business and Trade. Also included is funding for the Social Economy, Creative Industries, Innovation, Investment Zones and Cluster Development.
Alongside this transition, the WMCA has initiated a review of its economic development model and services, aligned with the new West Midlands Growth Plan objectives, with a new Economic Development Vehicle (EDV) based within the West Midlands Growth Company (WMGC) launching on 1 April 2026.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow CPH Economy, Business & Skills Decision Session at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.