Written from the decision and the officer reportPDF Pro
OutcomeApprovedSpend, contractor appointment and delegations all approved
Money£16,400,000CRSTS grant funding for scheme construction
What happens nextMain works May/June 2026Up to 18 months duration
Who it affectsA45 / Damson Parkway usersJLR, Birmingham Airport, NEC, Arden Cross
What was decided
Approved £16,400,000 of City Region Sustainable Transport Settlement grant funding to construct the A45 / Damson Parkway Junction Improvement scheme, delivering the outputs in paragraph 3.7 and shown in Appendix A. Report P5
Approved appointment of Balfour Beatty as contractor and delegated authority to the Director of Economy and Infrastructure, in consultation with the Cabinet Portfolio Holder, to sign the Delivery Agreement. Report P6
Delegated authority to the Director of Economy and Infrastructure to make minor design changes, provided key objectives are unaffected, with the Cabinet Member and spokespeople to be informed of any changes. Report P7
Why
The A45 / Damson Parkway junction is one of Solihull's most congested, particularly during peak periods and Jaguar Land Rover shift changes, with poor facilities for pedestrians and cyclists, and growing demand from planned UK Central Hub development. Report P8, P9, P10
Traffic modelling and economic appraisal under the Department for Transport's TAG framework shows the scheme delivers high value for money, with a Benefit to Cost Ratio of 2.89. Report P18
Public consultation in early 2021 found 79% of 200 respondents supported the scheme, with backing from JLR, Birmingham Airport, Prologis and the adjacent Holiday Inn. Report P53, P11
What happens next
Initial preparation works such as site compound setup to commence late March / early April, with main works starting May/June 2026 and lasting up to 18 months. Report P25
Officers will continue liaising with Jaguar Land Rover, Birmingham Airport, the Holiday Inn, the owner/occupier of The Lodge, and National Highways on coordinated delivery, and will publish highway works and traffic management as required. Report P26, P27, P28
Officers continue to engage with Birmingham Airport to secure a potential local contribution; any match funding would reduce the CRSTS spend proportionately, but scheme delivery is not dependent on it. Report P59
The money
£16,400,000 CRSTS grant funding approved to construct the A45 / Damson Parkway Junction Improvement scheme Report P5, P12, P31
£16.4m WMCA approved budget envelope within which the scheme can be delivered Report P31
£2,234,471 Earlier development phase spend, funded by WMCA Investment Programme, WMCA Transforming Cities, and CRSTS revenue capacity funding Report P64
Options considered
Chosen: Construct the preferred junction improvement scheme as designed. Provides optimal capacity enhancement predominantly within the existing highway boundary and balances highway, public transport, pedestrian and cyclist needs; delivers high value for money with a BCR of 2.89. Report P18, P36, P40
Rejected: Do nothing. Existing congestion would worsen with traffic growth and UK Central Hub development, compromising the Council's UK Central growth programme. Report P37
Rejected: Larger, more costly improvement options considered at an earlier stage. Scale of investment and impact considered disproportionate relative to the need for intervention. Report P38
Implications
Financial: The Council is the accountable body for the project; funding is provided on a cost reimbursement basis via WMCA's standard CRSTS Grant Funding Agreement, and officers continue to seek a potential local contribution from Birmingham Airport. Report P58, P59, P66
Financial: A separate risk contingency pot is allocated within the project budget; any cost escalation beyond it would need to be managed through existing budgets or alternative Council funding mechanisms with appropriate governance. Report P61, P63
Legal: The Council will need to enter into a Delivery Agreement with Balfour Beatty; authority to sign is delegated to the Director of Economy and Infrastructure in consultation with the Cabinet Portfolio Holder. Report P65
Risk: No net 'Red' high risks identified; a detailed Risk Register is in place and managed through the UK Central Project Management Framework, with Change Management procedures for any necessary corrective actions. Report P33, P34, P68, P69
Equalities: New toucan crossings provide a step-free route across the A45, benefiting people with disabilities, those with temporary mobility needs, children, older people, and socio-economically disadvantaged groups reliant on public transport or active travel. Report P70, P71, P73
Climate: The scheme contributes to climate ambitions by improving active travel facilities, providing a new dedicated bus lane to support public transport, and reducing congestion, all helping the move towards net zero. Report P50, P51
Who and where
Road users, pedestrians, cyclists and bus passengers using the A45 / Damson Parkway junction Report P8, P15, P17
Jaguar Land Rover, Birmingham Airport, NEC, Arden Cross and the UK2 development site as key regional employers and freight access points Report P9, P15, P27
Key stakeholders directly engaged: the owner/occupier of The Lodge residence, the adjacent Holiday Inn, and National Highways Report P27, P28
Residents of Solihull, vulnerable groups, and communities in deprived areas along the Coventry Road corridor, including those benefiting from future Sprint services linking east, central and west Birmingham Report P73
Timeline
21 December 2020: Cabinet Member for Growth & Delivery approved scheme to proceed to consultation Report P36, P79
Early 2021: Public consultation carried out on preferred design proposals; 79% of 200 respondents supported the scheme Report P11, P53
March 2023: Council's Cabinet adopted Solihull Connected 2023 transport strategy, in which this scheme is a key priority Report P55
5 July 2025: Cabinet Member resolution granting authority to accept the funding Report P31, P80
22 September 2025: West Midlands Combined Authority approved the Full Business Case Report P1, P12
19 March 2026: Cabinet Member for Environment & Infrastructure approved spend, contractor appointment and delegations
Late March / early April 2026: Initial preparation works (such as site compound setup) anticipated to commence, subject to prompt signing of the Delivery Agreement Report P25
May/June 2026: Main works anticipated to start, lasting for a duration of up to 18 months Report P25
Plain English for the jargon
CRSTS: City Region Sustainable Transport Settlement, the grant funding stream from which the £16,400,000 is drawn, administered via the West Midlands Combined Authority
BCR: Benefit to Cost Ratio; the scheme's BCR of 2.89 indicates high value for money under the Department for Transport's TAG framework
Sprint: Planned bus rapid transit service, including the proposed A45 Sprint, intended to run through the junction
Toucan crossing: A pedestrian and cycle crossing designed to modern standards, replacing the existing substandard pedestrian footbridge
SCAPE Framework: A procurement framework through which Balfour Beatty is to be appointed as Principal Contractor
UKC PMF: UK Central Project Management Framework, used by Solihull Council to manage this scheme, including risk and change management
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4
Resolved
The Cabinet Member for Environment & Infrastructure RESOLVED to: Approve spend of £16,400,000 of City Region Sustainable Transport Settlement (CRSTS) grant funding to construct the A45 / Damson Parkway Junction Improvement scheme, delivering the key outputs set out in paragraph 3.7 and as shown by the scheme plan at Appendix A. Approve the appointment of Balfour Beatty as the contractor responsible for scheme construction and approve the delegation of authority to the Director of Economy and Infrastructure, in consultation with the Cabinet Portfolio Holder – Environment and Infrastructure, to sign the associated Delivery Agreement. Delegate authority to the Director of Economy and Infrastructure to make minor design changes to the scheme, as considered necessary, provided that delivery of the key objectives remain unaffected (the Cabinet Member and spokespeople to be informed of any changes).
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
Report to CPH Environment and Infrastructure Decision Session
Executive summary
To update the Cabinet Member on the progress of the A45 / Damson Parkway Junction Improvement scheme, following Full Business Case approval from the West Midlands Combined Authority on the 22 September 2025.
To seek approval from the Cabinet Member to progress the construction of the scheme and support the recommendations as set out below.
2. Decision(s) Recommended
The Cabinet Member is asked to:
Approve spend of £16,400,000 of City Region Sustainable Transport Settlement (CRSTS) grant funding to construct the A45 / Damson Parkway Junction Improvement scheme, delivering the key outputs set out in paragraph 3.7 and as shown by the scheme plan at Appendix A.
Approve the appointment of Balfour Beatty as the contractor responsible for scheme construction and approve the delegation of authority to the Director of Economy and Infrastructure, in consultation with the Cabinet Portfolio Holder – Environment and Infrastructure, to sign the associated Delivery Agreement.
Delegate authority to the Director of Economy and Infrastructure to make minor design changes to the scheme, as considered necessary, provided that delivery of the key objectives remain unaffected. 3. Matters for Consideration
The A45 Coventry Road / Damson Parkway / Terminal Road junction is one of the most congested junctions in Solihull. The junction currently experiences congestion in the morning and evening peak periods, together with congestion during Jaguar Land Rover’s (JLR) shift changes. Bus services, including the proposed A45 Sprint service, also get constrained by this congestion, affecting journey time reliability. Planned growth within the UK Central Hub area is likely to further exacerbate the existing congestion issues.
The ongoing efficient operation of the junction is vital to JLR and Birmingham Airport as it forms the main access for freight vehicles to and from these key regional employers and their business operations. The junction is also a key node on the A45, which links Birmingham City Centre with the Airport, National Exhibition Centre and, in the future, HS2.
The junction currently has poor facilities for pedestrians and cyclists with a substandard pedestrian footbridge spanning the A45 adjacent to the junction and substandard uncontrolled crossings at the junction itself, creating a barrier for people walking and cycling to get to locations across the A45.
Following approval in December 2020 by the then Cabinet Member for Growth & Delivery, public consultation was carried out in early 2021 on preferred design proposals for a scheme that would improve facilities at the A45 / Damson Parkway junction for users of all modes. The outcome of the consultation was positive, with 79% of respondents indicating support for the scheme; support was also provided by a number of key stakeholders, including Jaguar Land Rover, Birmingham Airport and the Holiday Inn.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow CPH Environment and Infrastructure Decision Session at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.