CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Solihull Metropolitan Borough Council
Audit Committee, Monday 20 July 2026 at 2.00pm

Council’s Performance Management Framework - Annual Update

Noted Finance 1 paper

AI summarySolihull Audit Committee noted the annual performance management framework update and asked for more detailed planning and performance framework content in future iterations.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedAsked for detailed planning and performance framework coverage in future reports
MoneyNo new costsFinancial impacts contained within approved base budgets
What happens nextAnnual reporting continuesTop 40 data to be collected for Q1 2026/27
Who it affectsCouncil and residentsFrames how performance is tracked across all Council Plan priorities

What was decided

The Audit Committee reviewed and noted the annual performance management framework update report. Report P3

The Committee asked officers to include a more detailed presentation of the planning and performance framework in future iterations of the report.

Why

It is the second annual update, providing the Committee with ongoing assurance that effective performance management arrangements are in place. Report P10

A corporate Top 40 performance scorecard was introduced in 2024/25, responding to an external auditor recommendation for a streamlined, consistent reporting format covering all KPIs, progress, direction of travel, links to corporate objectives and risk registers. Report P12, P13

What happens next

Officers will keep the Top 40 scorecard in place, aligning it with the national Local Outcomes Framework where possible, with data collection starting in the first quarter of 2026/27. Report P27

A Wider Corporate Leadership Team discussion on performance took place on 14 July 2026, with further monitoring of the Local Outcomes Framework continuing through 2026. Report P27

The Council's next Corporate Peer Challenge, scheduled for 22 to 25 September 2026, will cover performance and productivity as one of its five themes, with recommendations feeding into future framework development. Report P28, P29, P30

Implications

  • Financial: No additional costs arise; framework supports financial sustainability by enabling early identification of performance and demand risks and informing resource allocation. Report P49, P50
  • Legal: Statutory performance requirements, including those for children and adult services and statutory complaints, are incorporated into the arrangements. Report P51
  • Risk: Risk management is tied in with the performance management framework, with the Top 40 highlighting trends and out-of-appetite risks and linking mitigating actions to risk registers. Report P53, P54, P55, P56
  • Equalities: Work continues to drill outcome indicators down by protected characteristics such as gender and ethnicity to understand who is affected by performance issues. Report P57, P58
  • Other: The new national Local Outcomes Framework, published in February 2026, sets 16 outcomes and around 133 metrics and is being used as a direction-of-travel reference, with the LG Inform platform acting as a practical proxy until the national digital platform goes live. Report P22, P23, P24, P25, P26

Who and where

  • Solihull Metropolitan Borough Council and its directorates Report P11, P20
  • Elected members, including Cabinet and Scrutiny Boards Report P8, P21, P46
  • Residents, including children, adults with care needs and groups with protected characteristics Report P40, P41, P57
  • Partners including the Integrated Care Board, via the Health and Wellbeing Board Report P62

Timeline

  • 13 November 2023: Previous Audit Committee report on performance management arrangements Report P5
  • October 2024: Cabinet agreed introduction of the Top 40 corporate performance scorecard Report P12
  • July 2025: Then Deputy Prime Minister announced the Local Outcomes Framework Report P22
  • February 2026: Local Outcomes Framework published Report P26
  • 14 July 2026: Wider Corporate Leadership Team discussion on performance Report P27
  • 22 to 25 September 2026: Corporate Peer Challenge scheduled, covering performance and productivity Report P28
  • Q1 2026/27: Top 40 performance data collection begins, with retention of the scorecard under review Report P27

Plain English for the jargon

  • Top 40: A corporate performance scorecard of around 40 key indicators, reported quarterly to the Wider Corporate Leadership Team and briefed to Cabinet Members, agreed by Cabinet in October 2024.
  • Local Outcomes Framework (LOF): A national outcome-based accountability framework announced in July 2025 and published in February 2026, setting 16 outcomes and around 133 metrics for local authorities.
  • Corporate Peer Challenge (CPC): An independent challenge and assurance process facilitated by the Local Government Association, not an inspection.
  • RAG: Red, Amber, Green rating used to indicate performance status against targets.
  • Wider Corporate Leadership Team (WCLT): Senior officer group within the Council that reviews the Top 40 scorecard quarterly.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

RESOLVED Audit Committee reviewed and noted the report and asked for a more detailed presentation of the planning and performance framework to be included in the future iterations of the report to Audit Committee.
Word for word from the decision Solihull published for this meeting. Source: democracy.solihull.gov.uk

Follow this further

Built from Solihull's papers

What the report saysPro

Report to Audit Committee

Executive summary

The purpose of this report is to provide Audit Committee with an annual update on the Council’s Performance Management Framework, providing assurance.

2. Decision(s) Recommended

For Audit Committee to review and note the content of this report.

3. Matters for Consideration

On 13th November 2023, the Audit Committee considered a report providing an overview of the Council’s Performance Management arrangements. This report:

• Described the Council’s performance management arrangements.

• Explained how these provide a “line of sight” to help each part of the organisation and employees understand their contribution to achieving Council priorities.

• Set out current arrangements for reporting performance to elected members.

• Noted the external auditor’s recommendation that the Council consider a consistent format for performance reporting.

As part of the Audit Committee’s work programme, it has been agreed to give an annual update on the Council’s performance management framework and arrangements to provide the Audit Committee with ongoing assurance that the Council has effective performance management arrangements in place. This is the second annual update to be received by the Committee.

The Council Performance Management arrangements continue to operate as set out in the report to the Audit Committee in November 2023. Links to recent performance reporting to elected members can be found in section 10 of the report.

The most notable development in Performance Management arrangements in 2024/25 was the introduction of a corporate ‘Top 40’ corporate performance report, agreed by Cabinet in October 2024. Its purpose is to give the management team and elected members a high-level view of performance trends quarter on quarter and highlight potential areas of concern for further investigation and action.

The creation of the Top 40 responded to an external auditor recommendation that “…the Council should create a streamlined format for performance reporting. This should include all KPIs, progress to date, progress direction of travel, link to corporate objectives and risk registers.”

Metrics in the scorecard are reported in a consistent format which includes:

• Current performance value

• Direction of travel, to indicate if performance has improved or deteriorated since last reported period

• Performance commentary (by exception)

• Target (where appropriate)

• RAG (where appropriate)

Directors identified key performance measures from each Directorate for inclusion in the scorecard. In almost all cases these were picked from existing measures, meaning a minimal additional reporting burden associated with the new scorecard. There is the flexibility to add / remove metrics over time based on performance or importance.

The scorecard is reported quarterly to the Wider Corporate Leadership Team for review and management action. Cabinet Members are briefed quarterly on the indicators within their Portfolio and Cabinet agreed that the scorecard would be scrutinised annually by the Resources and Delivering Value Scrutiny Board.

In July 2025, the then Deputy Prime Minister announced the creation of the Local Outcomes Framework — a new approach to outcome-based accountability designed to empower councils as place leaders.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Council’s Performance Management Framework: Annual UpdateReport 252 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
TH
Tammy HollisOfficer, expected
TB
Mr Tony Beirne Independent Co-opted memberChairman, present
MB
Mr Michael Burnett Independent Co-opted MemberCommittee Member, present
DP
Mr David Page Independent Co-opted MemberCommittee Member, present
MW
Mark WillsOfficer, present
MM
Councillor Max McLoughlinVice-Chairman, present
SG
Councillor Samantha GethenCommittee Member, present
PW
Councillor Paul WhitehouseCommittee Member, present

More from Solihull Audit Committee

All decisions
MeetingDecisionOutcome
20 Jul 2026 Annual Report on Internal AuditRESOLVED Audit Committee: Noted the work of Internal Audit for 2025/26, detailed within the report, including the Hea... Noted Open
20 Jul 2026 Draft Annual Governance Statement for 2025-26RESOLVED Audit Committee endorsed the Council’s Annual Governance Statement. Decided Open
20 Jul 2026 Work ProgrammeRESOLVED Audit Committee approved the updated Work Programme, and noted the suggestions made in discussion. Approved Open
17 Mar 2026 2025/26 Accounting PoliciesRESOLVED Audit Committee noted and considered the proposed Accounting Policies, accounting estimates and significant ... Noted Open
17 Mar 2026 Internal Audit Monitoring ReportRESOLVED Audit Committee noted the work of Internal Audit and provided feedback, as above, on areas where Audit ... v... Noted Open