CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Solihull Metropolitan Borough Council

Access Arrangements Update

Noted Scrutiny 2 papers

AI summarySolihull scrutiny board notes progress of Solihull Community Housing's no access pilot, with a six month extended scheme underway since 8 June 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedBoard noted SCH's steps on no access pilot
MoneyNo cost figures in the report
What happens nextSix month pilot continuesReporting to QMB and CLOs progressing cases
Who it affectsNot stated

What was decided

The Board noted the steps taken by SCH to manage no access issues, including the extended pilot, the progress made to date and the next steps for monitoring effectiveness. Report 2.1

Why

SCH has had ongoing difficulties gaining access to customer homes for repairs, building safety compliance checks and capital investment surveys, leaving homes out of compliance for years. Report P6

An initial 10 week pilot on EICRs cut overdue inspections from 170 to 87 and is judged to have improved access, collaboration, case visibility and resident engagement. Report P9, P14, P15

The success supported expansion into a six month pilot covering gas, electrical, water hygiene, fire safety, damp and mould, repairs, biomass and stock condition work. Report P16, P21

What happens next

The two dedicated Customer Liaison Officers will continue initial engagement and case work, including access arranged, in progress and resolved cases. Report P29, P38, P39

SCH will further develop the master sheet, tracker, risk scoring matrix and reporting, and engage IT and Open Housing on system capability. Report P19, P34, P42

The No Access Policy will be reviewed in consultation with the Council and residents and taken to a future Cabinet Portfolio Holder session; regular pilot reports will go to QMB. Report P17, P58, P42

Options considered

  • Chosen: Initial 10 week EICR focused pilot, with centralised engagement and revised Dodd Group appointment model. Reduced overdue inspections from 170 to 87 and improved access, collaboration and case visibility Report P9, P10, P14, P15, 4.1
  • Chosen: Extended six month pilot under a No Access Operating Framework covering multiple workstreams. Builds on initial pilot success to coordinate risk based management of no access cases Report P16, P15, 5.1

Implications

  • Staffing: Two additional Grade D Customer Liaison Officer posts have been established to carry out the no access management function. Report P61
  • Legal: Failure to complete statutory compliance checks within required timescales could expose SCH and the Council to legal and regulatory action. Report P62
  • Risk: There is a low risk appetite for statutory compliance activity not being completed in time; failure to gain access could increase risks to resident safety. Report P64
  • Equalities: The risk matrix includes resident vulnerability and age related considerations to support prioritisation and case management. Report P65
  • Climate: Access work will include Energy Performance Certificate assessments where needed, supporting Net Zero ambitions. Report P54, P55

Who and where

  • SCH tenants in properties where access has been difficult, including those with overdue compliance checks, repairs, damp and mould cases and biomass issues Report P6, P21
  • Eight HHSRS Category 1 households as at 13 July 2026, escalated as top priority Report P27
  • Dodd Group, working on electrical, fire safety, damp, mould and other works for SCH Report P7, P10, P33

Timeline

  • First two months of 2026: Initial 10 week pilot on EICRs carried out Report P6, P9
  • 10 week pilot end: Overdue EICR inspections reduced from 170 to 87 Report P9
  • 8 June 2026: Extended six month Access Management pilot formally began Report P32
  • 13 July 2026: Eight HHSRS Category 1 no access households recorded Report P27
  • 2026-07-29: Scrutiny Board noted the update

Plain English for the jargon

  • SCH: Solihull Community Housing, the council's housing body
  • EICR: Electrical Installation Condition Report, a safety certificate for electrical systems
  • CLO: Customer Liaison Officer, a dedicated SCH role coordinating no access cases
  • HHSRS: Housing Health and Safety Rating System; Category 1 is the highest hazard level
  • No Access Operating Framework: A coordinated, risk based approach to managing properties where SCH cannot gain entry
  • QMB: Quarterly Management Board, receiving regular reports on pilot progress
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

i. To note the steps taken by SCH to manage no access issues, including the extended pilot, the progress made to date and the next steps for monitoring effectiveness. The Economic Development, Managed Growth and Skills Scrutiny Board meeting closed at 8:28 p.m.
Word for word from the decision Solihull published for this meeting. Source: democracy.solihull.gov.uk

Follow this further

Built from Solihull's papers

What the report saysPro

Report to Economic Development, Managed Growth and Skills Scrutiny Board

Executive summary

1.1This report has been prepared in response to a request from the Economic Development, Managed Growth & Skills Scrutiny Board for an update on SCH’s revised approach to managing no access to properties across compliance, repairs and improvement workstreams. It summarises the purpose of the revised approach, the outcomes from the initial pilot, the current operational position and the next steps for monitoring effectiveness.

2. Decision(s) Recommended

2.1The Board is asked to note the steps taken by SCH to manage no access issues, including the extended pilot, the progress made to date and the next steps for monitoring effectiveness.

3. Matters for Consideration

3.1Introduction

3.1.1 SCH has experienced difficulties in gaining access to customer homes for the purpose of completing reported repairs, building safety compliance checks and surveys to inform capital investment programmes. During the first two months of 2026, a pilot was undertaken to take a different approach to managing no access cases relating to Electrical Installation Condition Reports (EICRs), in order to reduce the number of homes without a valid certificate of compliance.

3.1.2 Additional resource to coordinate and carry out engagement was centralised through the Engagement Team, with significant support from the Compliance and Neighbourhood Teams. The ways in which SCH engaged with residents were expanded, and the way in which Dodd Group arranged and completed safety checks, certification and identified works was also changed to increase communication with customers and provide greater flexibility and responsiveness.

3.1.3 The changes referred to in 3.1.2 centred around increased written communication, starting with a letter that set out the legal requirement to complete the safety checks, the importance of keeping the household and visitors safe, and the date and time when the works had been programmed, while inviting customers to rearrange the appointment if it was not convenient. If access for the appointment was not successful, a second letter was sent, detailing the importance of the works and the potential for tenancy enforcement action. If the third visit was not successful, a further letter was issued with increased emphasis on customer safety and SCH’s intention to proceed with legal options.

3.1.4 During the 10 week pilot, 126 electrical surveys were carried out where initial access had proved problematic. At the start of the pilot, 170 inspections were overdue, with some properties being out of compliance for many years despite significant efforts to engage and agree access or works with customers. At the end of the pilot, 87 properties remained. The team also identified additional hard-to-access properties during the pilot.

3.1.5 There were changes to the operating model for Dodd Group appointments including weekend and evening appointments, timed appointments and a single point of contact for scheduling.

3.1.6 There remained a cohort of homes where access could not be agreed. These are being progressed through tenancy enforcement, which could result in legal action.

3.1.7 It is important to note that whilst the initial project focused upon the 170 homes identified at the time, the number is continually changing as more properties exceed anniversary dates and others on the out of compliance list are completed.

3.2Initial Pilot Outcomes

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Access Arrangements UpdateReport 251 KB DownloadRead as text
PDF
Appendix 1Appendix 1 219 KB Download

At this meeting

Whole meeting

Who was there

2 of 21 attended
SK
Satnam KaurOfficer, expected
HC
Harleen ChimaOfficer, expected
LA
Liz AlstonOfficer, expected
JH
Jackie HillOfficer, expected
MM
Councillor Max McLoughlinCommittee Member, expected
KT
Councillor Kathryn ThomasCommittee Member, expected
ST
Councillor Sally TomlinsonCommittee Member, expected
PW
Perry WardleOfficer, expected
TB
Councillor Terry BakerCommittee Member, expected
HB
Councillor Hitesh BikumallaCommittee Member, expected
EG
Councillor Eleonora GoughCommittee Member, apologies, sent representative
DH
Councillor David HoeyCommittee Member, expected

All 21 on the meeting page

More from Solihull Economic Development, Managed Growth and Skills Scrutiny Board

All decisions
MeetingDecisionOutcome
29 Jul 2026 MinutesIt was agreed for the draft Minutes arising from the Economic Development, Managed Growth & Skills Scrutiny Board mee... Agreed Open
16 Jul 2026 Appointment of the Vice-Chairman to the Economic Development, Managed Growth and Skills Scrutiny Board for the 2026/27 Municipal YearTo appoint Councillor J Lamden as Vice-Chairman to the Economic Development, Managed Growth & Skills Scrutiny Board f... Decided Open
16 Jul 2026 Minutes(i) To agree the arising from the Economic Development, Managed Growth and Skills Scrutiny Board meeting held on 9 Ma... Agreed Open
16 Jul 2026 Economic Development, Managed Growth and Skills Scrutiny Board Draft Work Programme 2026/27i. To address the Council Motion arising from the Council Meeting held on 7 th July 2026 and referred to the Economic... Noted Open
9 Mar 2026 Minutesi. To agree the arising from the Economic Development and Managed Growth Scrutiny Board meeting held on 19 th January... Agreed Open