Councillor Heather Shearer proposed the recommendations, which were seconded by Councillor Liz Leyshon. Having been duly proposed and seconded, the Council Resolved to:- 1. Note the updated DSG forecast deficit to 2029/30 of £294.600m based upon current policy and practice and the risk that this presented to the Council’s financial sustainability. 2. Approve: a. The incorporation of the DSG revised budget including proposed investment and savings, the forecast Deficit and the Deficit Management Plan into the MTFP for the period 2025/26 to 2029/30 as set out in Table 3 and Appendix 3. b. The additional General Fund base budget investment required from 2026/27 to deliver the proposed DMP workstreams set out in Appendix 4 of up to £0.679m as set out in Table 5. c. That the additional expenditure of £0.679m at 2b above was financed initially from the Corporate Contingency Budget in 2026/27 with funding over the MTFP period to be addressed as part of balancing the 2026/27 budget in February/March 2026. 3. Note that quarterly progress on delivery and financial tracking of the DSG Deficit Management Plan would be presented to Executive as part of future corporate revenue and capital monitoring reports.
Word for word from the decision Somerset published for this meeting.Source: democracy.somerset.gov.uk
This report provides Full Council with an updated assessment of the Council’s Dedicated Schools Grant (DSG) financial position and sets out a range of proposals for Council consideration and approval following endorsement at Executive on 6th August 2025, that aim to improve outcomes for pupils whilst strengthening the management and control of the DSG cumulative deficit.
The current Deficit Management Plan was produced in February 2024 which led to a number of structural changes within the service directorate. The current DMP has had limited impact upon the Council’s ability to manage and control its financial deficit to date, due to the length of time required to effect structural and systemic change. External consultants Peopletoo were commissioned in December 2024 to work with the Council to produce a revised DMP plan drawing upon sector wide expertise and impactful change in other local authorities. The review confirmed the trajectory taken by the service and recommended some additional areas of focus.
The proposals are consolidated into a Deficit Management Plan (DMP) which has been produced with input from external consultants – Peopletoo who have also made a number of recommendations for strengthening the Council’s SEND policy and practice. The recommendations are summarised in Appendix 1. The Council is required to produce a DMP by the Department for Education (DfE).
The DMP is the overarching plan and is large and complex in areas. It comprises of a range of actions, as follows: • some that fall within current policy and approved resources and can be progressed by officers at pace. • some that fall within current policy but require additional investment of resources to enable delivery. Approval of resources and delegation is sought for implementation by the Service Director Education and will be subject to the development and sign off of robust and detailed business cases and implementation plans in consultation with the Section 151 Officer and Service Director HR and OD where relevant. • Some actions that will require policy change, consultation and potentially additional resources, that will be further developed and reported to Executive for further consideration and approval in the coming months.
The DSG deficit has been increasing since 2018/19 primarily due to the growth in demand for, and complexity and cost of Special Educational Needs and Disabilities (SEND) provision, that the local authority has a statutory obligation to fund. This has been experienced by local authorities nationally and the growth in expenditure has exceeded the DSG allocations from the DfE for a number of years.
The cumulative deficit stood at £61.992m on 31 March 2025 and is projected to increase to £294.600m by 2029/30 assuming current policies and practices continue over the period of the 2025/26 MTFP to 2029/30. This presents a significant strategic financial risk to the Council’s financial sustainability and puts the Council at risk of the Section 151 Officer being required by law to issue a Section 114 Notice given that the Council’s revenue reserves are insufficient to meet the projected shortfall of resources.
The impact of measures proposed in the DMP and presented for consideration and approval are estimated to deliver cost reductions of £2.516m in 2025/26 and annual cost reductions of £79.297m by 2029/30 if delivered in line with stated assumptions within the Plan.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.