Additional funding for Highway and Environmental Maintenance Activity
ApprovedExecutive1 paper
AI summarySomerset Council Executive approves £2m for additional highway maintenance in 2026/27, combining £1m carried forward with £1m already allocated. A Steering Group will deliver gully emptying, sign renewal, vegetation and litter work, with an ambition of up to £5m over three years.
Written from the decision and the officer reportPDF Pro
OutcomeApproved£2m budget for new high-visibility maintenance programme
Money£2m for 2026/27Plus ambition of up to £5m over three years
What happens nextSteering Group mobilises programmeFlexible delivery starting in 2026/27
Who it affectsSomerset roads, footways and cyclewaysIncluding gully emptying, signs, markings and vegetation
What was decided
The Executive approved a £2m budget for 2026/27, made up of £1m carried forward from 2025/26 and £1m already allocated, to establish a Steering Group and deliver additional, high-visibility highway maintenance. Report P4, P39
Members noted the wider ambition to invest up to £5m over three years, with funding beyond 2026/27 to be considered in future budget-setting. Report P4, P11, P39
The Steering Group will use a flexible programme, redirecting resources quickly to priority locations using reporting, local intelligence and asset data. Report P4, P17
Why
Current highway maintenance focuses on safety-critical work, so visible issues such as faded markings, broken signs, overgrown vegetation and infrequent gully emptying have remained unresolved. Report P1, P9, P10
There is significant public dissatisfaction with current service levels within existing financial resources. Report P10, P26
The programme is intended to deliver visible improvements, respond to public concerns, and rebuild confidence in local infrastructure. Report P6, P11
What happens next
A Steering Group will be set up to plan the work, with delivery by highway contractor Kier and the in-house Open Spaces Team, including four new fixed-term Grounds Operatives. Report P13, P16, P44
A one-year intensive gully clearance will target around 65,000 additional gullies in areas at risk of 1 in 100-year flooding, alongside a sign and road-marking renewal on A and B roads. Report P16
The programme will run for up to three years from 2026/27 to 2028/29, with high-impact work prioritised in year 1, and a full review of equalities impacts by 12 October 2026. Report P15, P82
The money
£1m Carry forward from 2025/26 revenue budget, unspent and reallocated Report P4, P39
£1m Already allocated in the 2026/27 revenue budget for Council priorities Report P4, P39
£2m Combined 2026/27 budget for the new Steering Group programme Report P4, P12, P39
up to £5m Total ambition over three years, subject to future budget decisions and financial sustainability Report P4, P11, P39
Options considered
Chosen: Allocate £2m for 2026/27, combining carry-forward and existing provision. Considered financially achievable now that a balanced 2026/27 budget has been set Report P21
Rejected: Rely solely on the existing safety-led highway maintenance programme. Leaves visible issues unresolved and has led to public dissatisfaction Report P1, P9, P10
Implications
Financial: £2m committed in 2026/27 from existing revenue budget; further spending up to £5m over three years depends on future budget-setting and financial sustainability. Report P4, P11, P39
Equalities: Extra vegetation clearance is expected to improve access for older people and people with disabilities, but safety barriers on some routes may temporarily reduce accessibility, with alternatives to be provided by 14 May 2026. Report P47, P48, P69, P70, P71, P79
Staffing: Four fixed-term Grounds Operatives will be recruited; Steering Group members are existing staff. No additional staffing required for Steering Group work. Report P44, P45
Risk: Deliverability and capacity risk scored 9 (current and target), with reliance on recruitment of operatives; health and safety risk scored 12 inherent, 4 current and target, due to constraints on litter collection near traffic. Report P27, P33, P34
Climate: Keeping active travel routes clearer of vegetation is expected to encourage walking and cycling. Report P51, P54
Legal: Existing highway contracts can accommodate the additional work; legal services classed this as a financial decision only. Report P40, P42
Who and where
Somerset road users, pedestrians and cyclists, who should see improved signs, markings, drainage and vegetation management Report P11, P16, P19
Older people and people with disabilities, who should benefit from clearer walking and cycling routes Report P47, P69, P70
Residents reporting issues through the Council's 'Report It' platform Report P16
Highway contractor Kier and the in-house Open Spaces Team, who will deliver the work Report P13
City, town and parish councils, who will be liaised with to avoid duplication Report P14
Timeline
2026/27: Year 1 of the programme, with high-impact work prioritised and four Grounds Operatives recruited Report P15, P44
14/05/2026: Mitigation action due: suitable alternative routes provided where safety barriers reduce accessibility Report P79
12/10/26: Scheduled review of the Equalities Impact Assessment Report P82
2027/28: Further investment beyond 2026/27 to be considered as part of MTFP budget-setting Report P4, P39
2028/29: Indicative end of the three-year programme Report P15
Plain English for the jargon
MTFP: Medium-Term Financial Plan, the Council's multi-year budget planning process
EIA: Equality Impact Assessment, a review of how a proposal affects protected groups
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item139
Resolved
Having been duly proposed and seconded, the Executive Resolved to:- 1) Approve £1m carry forward from the 2025/26 revenue budget. Combine it with the £1m allocated for 2026/27 to create a £2m budget to establish and mobilise a new programme of work overseen by a Steering Group to deliver additional, high-visibility highway maintenance activity. 2) Note that the wider ambition was to invest up to £5m over three years; and that funding beyond 2026/27 would be considered as part of future budget-setting processes. 3) Agree that the Steering Group would operate with a flexible programme approach, enabling resources to be directed quickly to priority locations/issues as determined by the Steering Group and informed by reporting, local intelligence and asset data.
Word for word from the decision Somerset published for this meeting.Source: democracy.somerset.gov.uk
Somerset Council’s current highway maintenance programmes necessarily prioritise safety-critical works, which has meant that lower-priority but highly visible issues such as faded road markings, broken/deteriorated signs, and overgrown vegetation affecting footways/cycleways can remain unresolved for prolonged periods. Communities have also expressed a desire for more frequent emptying of roadside gullies in areas most prone to flooding.
This report proposes the creation of a dedicated, time-limited programme of high- visibility additional highway maintenance that goes beyond the standard safety-led regime, with a Steering Group determining and flexing the precise programme of works to respond to emerging issues and public reporting.
Recommendations
That Executive:
1. Approve £1m carry forward from the 2025/26 revenue budget. Combine it with the £1m allocated for 2026/27 to create a £2m budget to establish and mobilise a new programme of work overseen by a Steering Group to deliver additional, high-visibility highway maintenance activity. 2. Note that the wider ambition is to invest up to £5m over three years; and that funding beyond 2026/27 will be considered as part of future budget-setting processes. 3. Agree that the Steering Group will operate with a flexible programme approach, enabling resources to be directed quickly to priority locations/issues as determined by the Steering Group and informed by reporting, local intelligence and asset data. Reasons for Proposals
The proposed Steering Group and investment are intended to:
• Deliver visible improvements to Somerset’s roads, pavements and cycleways that are not always addressed through the core safety-led programme. • Respond to longstanding public concerns and rebuild confidence in local infrastructure through a high-profile programme. • Improve the ability of residents to highlight issues for our teams to consider through enhancements to the Council’s public reporting system, complementing a more flexible delivery model.
Report Author: Mike O’Dowd-Jones Service Director for Infrastructure and Transport Contact Details: 01823 356238. [email protected] Main report and supporting information
Background and purpose of report
1. Somerset Council’s current highway maintenance programmes necessarily prioritise safety-critical works, which has meant that lower-priority but highly visible issues such as faded road markings, broken/deteriorated signs, and overgrown vegetation affecting footways/cycleways, can remain unresolved for prolonged periods.
2. Current gully emptying operates on a risk-based cycle (annual for high-risk, biennial for medium-risk, and quadrennial for low-risk areas). While efficient, this has led to public dissatisfaction regarding perceived infrequency of drain clearance.
3. The Council has announced an intention to spend up to £5m (subject to demonstrating financial stability) over the next 3 years to undertake additional maintenance. The aim is to deliver a range of visible improvements like clearing more drains and gullies, fixing and cleaning road signs, repainting faded road markings, collecting litter, and clearing overgrown vegetation, particularly near to walking and cycling routes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Scrutiny Recommendations to ExecutiveThe Executive Resolved to:- 1) Consider the comments and recommendations made by the four Scrutiny Committees during ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.