Strategic and High Scoring Tactical and Operational Risks Q4 Update
DecidedExecutive6 papers
AI summarySomerset Council Executive endorses Q4 strategic risk profile and notes 26 high-scoring tactical and operational risks, with one new risk added and one risk score rising from 12 to 20.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedConsidered high scoring tactical and operational risks
MoneyNo direct financial implicationsCorporate risk reserves held for mitigations
What happens nextScrutiny Corporate & Resources 10 June 2026Audit Committee 25 June 2026
Who it affectsAll council directorates and servicesRisk management oversight
What was decided
The Executive endorsed the current strategic risk profile set out in Appendix B, with 12 of 13 strategic risks unchanged from Q3 and risk ORG007 reduced from 12 to 8. Report P1, P19
Members considered 26 high-scoring tactical and operational risks detailed by directorate in Appendices C to G, including one new risk (STRICT017) and one risk (STRCIG002) that rose from 12 to 20. Report P2, P30
Members agreed to identify any areas for potential scrutiny focus and to refer matters of concern to the relevant Scrutiny Committee.
Why
The Executive is responsible for overseeing the council's approach to managing risk, including considering risk oversight, policies and regularly assessing corporate risk. Report P9
Member oversight helps ensure risks to Somerset Council are effectively managed, reviewed and that any areas of concern are identified and addressed. Report P10
In line with the Risk Framework, high scoring tactical and operational risks scoring 16 or more are included in quarterly risk reporting to improve transparency and oversight. Report P14
What happens next
Scrutiny Corporate & Resources Committee will consider the quarterly risk report on 10 June 2026, and the Audit Committee on 25 June 2026. Report P38
A full review of strategic risk ORG005 (Carbon Neutrality and Climate Change) will be undertaken during Q1 2026/27 following the April 2026 Executive consideration of the new Climate and Ecological Vision and carbon baseline. Report P44
The sequencing of reporting risk and performance to Executive, Corporate and Strategy Scrutiny and Audit Committee is under review. Report P46
Options considered
Chosen: Endorse current strategic risk profile and consider high scoring risks. Standard quarterly oversight of risk management as set out in the Risk Framework Report P7, P14
Implications
Risk: Risk ORG007 (governance and decision making) reduced from 12 to 8 following implementation of a new Corporate Organisational Assurance Dashboard on Ideagen. Report P1, P19
Risk: Risk STRCIG002 (organisational capacity for information requests) re-evaluated upward from 12 to 20. Report P2, P30
Financial: No direct financial implications from the recommendations; corporate risk reserves are held to mitigate risks exceeding planned mitigations or to fund additional mitigations. Report P50
Climate: A full review of strategic risk ORG005 (Carbon Neutrality and Climate Change) is scheduled for Q1 2026/27, with action plans, delivery pathways, resource requirements and milestones to be defined. Report P40, P44
Other: Children's risks including ORG002, CF010 and CF021 are to be regularly reported to the Children and Families Scrutiny Committee, and the EHCP backlog was considered by that committee on 20 April. Report P40, P45
Other: All 249 active risks are recorded in the Ideagen Risk and Performance Management System, with 38 high-scoring (16+) risks reported for Q4 compared to 39 in Q3. Report P16, P17, P18
Who and where
All Somerset Council directorates (Adults and Housing; Children's, Families and Education; Community, Place and Economy; Finance and Procurement; Resources, Strategy and Transformation) Report P3, P54
Members of Scrutiny Corporate and Resources Committee and Audit Committee Report P38
Children and Families Scrutiny Committee, for ongoing reporting of children's risks and the EHCP backlog Report P40, P45
Council residents, through risks to service delivery, housing, bridges, traffic signals and digital services Report P25, P30
Timeline
January to March 2026 (Q4): Risk profile reviewed and reported Report P13
1 April 2026: Executive to consider the new Climate and Ecological Vision and carbon baseline, informing review of ORG005 Report P40, P44
20 April 2026: Children and Families Scrutiny Committee considered the EHCP backlog Report P45
Q1 2026/27: Full review of strategic risk ORG005 to be undertaken Report P44
3 June 2026: Executive meeting endorsing the Q4 risk report
10 June 2026: Scrutiny Corporate & Resources Committee to consider the quarterly risk report Report P38
25 June 2026: Audit Committee to consider the report, focusing on adequacy of risk arrangements Report P38
Plain English for the jargon
Strategic risks: Risks with a significant impact on the delivery of the Council's objectives.
Tactical risks: Risks identified within a Directorate or Programme Board that have a significant impact on the Directorate or on Inspiring Innovation transformation delivery.
Operational risks: Risks identified at service level from service planning, service improvement plans or project delivery, with potential negative effect on completion of service or project objectives.
RAG Matrix: Red, Amber, Green scoring matrix used to rate risk severity; revised version included as Appendix A and applied using 2026/27 financial criteria.
Ideagen: The Council's Risk and Performance Management System, holding all risk records and mitigations.
EHCP: Education, Health and Care Plan, referenced in the context of a backlog considered by the Children and Families Scrutiny Committee.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
Having been duly proposed and seconded, the Executive Resolved to:- · Consider and endorse the current strategic risk profile set out in Appendix B. · Consider the current high scoring tactical and operational risks set out in Appendices C D, E, F, & G (detailed by directorate). · Consider whether the proposed mitigating actions were adequate and appropriate to address concerns. · Consider and identify any areas for potential scrutiny focus. · Consider referring any matters of concern to the relevant Scrutiny Committee.
Word for word from the decision Somerset published for this meeting.Source: democracy.somerset.gov.uk
This report provides an update on the Council’s Strategic Risk Profile (Appendix B) and High Scoring (16+) Tactical and Operational Risks. Of the 13 Strategic Risks, 12 risk scores remain the same compared to quarter 3 (Q3). One risk has reduced from 12 to 8 – ORG007. This reduction is due to the implementation of a new Corporate Organisational Assurance Dashboard for the Annual Governance Statement, Internal & External Auditor, Corporate Peer Challenge and other reviews.
There are currently 26 high-scoring tactical and operational risks. Compared to Q3, this includes one new risk (STRICT017 – Appendix G) and one risk that has increased in score from 12 to 20 (STRCIG002 – Appendix G). Four risks have reduced to below 16 (ASH011 – Appendix C; CPEHRA001 and CPEIT009 – Appendix E; and STRTD004 – Appendix G), with the rationale set out in the relevant appendices.
The following appendices contain further details organised by Executive Directorate: • Appendix C – Adults and Housing • Appendix D – Children, Families and Education • Appendix E – Community, Place and Economy • Appendix F – Finance and Procurement • Appendix G – Resources, Strategy and Transformation
Update to the RAG Matrix
Following Members request at Scrutiny Corporate and Resources, the revised risk scoring matrix is appended to this report as Appendix A. All risks are now assessed on the financial criteria set for 2026/27. The financial criteria will be updated annually in line with the MTFS, based on best practice using thresholds as a percentage of our net revenue budget. Revisions to Risk Report and Appendices
Following Member’s requests, we have streamlined the Q4 risk report and appendices. These changes are designed to simplify and improve the navigation around the report. There is now one appendix per directorate which includes a summary of tactical and operational risks within each Directorate, the detail of each risk that is held in the Council’s Ideagen Risk Management System, and the rationale for any de-escalated risks.
Recommendations
Executive is recommended to: • Consider and endorse the current strategic risk profile set out in Appendix B. • Consider the current high scoring tactical and operational risks set out in Appendices C D, E, F, & G (detailed by directorate). • Consider whether the proposed mitigating actions are adequate and appropriate to address concerns. • Consider and identify any areas for potential scrutiny focus. • Consider referring any matters of concern to the relevant Scrutiny Committee.
Reasons for Proposals
The Executive are responsible for overseeing the Council’s approach to managing risk. This involves considering risk oversight and policies, as well as regularly assessing corporate risk.
Member oversight plays an important role in ensuring risks to Somerset Council are being effectively managed, reviewed and any areas of concern are identified and addressed.
Report Authors: Sarah Hawkins, Head of Assurance, Performance & Risk (APR), Contact details: 01823 355340, [email protected], Pam Pursley, Risk Officer, APR, Strategy, Performance & Communications. Contact details: 01823 359062, [email protected]. Nikki Allen, Risk Officer, APR, Strategy, Performance & Communications. Contact details: [email protected] Main report and supporting information
Background and purpose of report
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Scrutiny Recommendations to ExecutiveThe Executive Resolved to:- 1) Consider the comments and recommendations made by the four Scrutiny Committees during ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.