Executive, Wednesday 23 September 2026 at 11.00am

Somerset Flood Resilience Programme

Approved Executive 1 paper

AI summarySomerset Council Executive approved in principle £50m Defra flood resilience funding for 15 projects and added £42.5m to its capital programme, delegating delivery to the Executive Director for Economy, Place and Climate to meet a 30 September 2028 deadline.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved15 projects get funding allocation, £42.5m capital grant added
Money£50.0mDefra Section 31 grant: £42.5m capital, £7.5m revenue
What happens nextDelegated authority to Executive DirectorFor business cases and remaining funding allocation
Who it affectsSomerset flood-risk residents and partnersIncluding Environment Agency, IDBs, community groups

What was decided

Approved in principle the funding allocation for 15 projects, delegating authority to the Executive Director for Economy, Place and Climate to authorise business cases and funding agreements. Report P6

Delegated authority to the same Executive Director, in consultation with the Head of Legal, Section 151 Officer and Lead Executive Member, to approve the remaining allocation of funding within the programme. Report P7

Approved adding the £42.5m capital grant to the Council's capital programme. Report P7, P102

Why

The Defra Section 31 grant totals £50.0m and must be spent by 30 September 2028 to help Somerset recover from the major flooding incident declared on 26 January 2026, when 82 homes and businesses were flooded. Report P12, P13, P14, P17, P18, P101

The proposals are needed to ensure successful delivery of the grant, that funds are spent in line with Executive wishes, and that spending complies with external and internal guidelines. Report P9

Scrutiny Committee broadly supported the approach, direction of travel and specific recommendations after considering the report twice. Report P1, P88

What happens next

The Programme Board, including the Executive Director and Section 151 Officer, will begin monthly meetings to provide assurance and strategic oversight. Report P22, P23

13 additional programme roles will be recruited, fully funded from the revenue allocation. Report P76, P77, P78

Further Scrutiny Committee updates will be brought forward as delivery progresses, with project information shared with members where appropriate. Report P93

The money

  • £50.0m Total Defra Section 31 grant for Somerset flood resilience Report P17, P101
  • £42.5m Capital works allocation, to be added to capital programme Report P17, P102
  • £7.5m Revenue allocation, to be held in a specific revenue reserve Report P17, P104
  • £10m Initial allocation for the 15 projects approved in principle Report P36
  • c£40m Indicative collective budget for the 15 projects Report P49
  • £10m Forecast value for the My Community village and town programme Report P50
  • £7.5m Forecast value for TTC5 left bank defences of River Tone in Taunton Report P58
  • £5m Forecast value for replacing and adopting Vinney's Bridge at Fordgate Report P64

Options considered

  • Chosen: Approve in principle and delegate authority as recommended. Specific nature of the Defra grant means no other options were considered Report P84

Implications

  • Financial: As 100% grant funding, the £42.5m addition will not increase the Council's overall borrowing requirement, and no match funding is requested; unspent funds must be repaid. Report P73, P75, P103
  • Risk: Key risks include delays to permissions and consents, securing executive approvals, adverse weather, and pressure on Environment Agency and partner staff resources. Report P67, P68
  • Legal: Legal advice has been sought on the risks of the governance and approvals process and will be shared with the Programme Board. Report P107
  • Climate: All projects will contribute to climate resilience and adaptation, including natural flood management, and align with the Council's declared Climate and Ecological Emergency and Carbon Neutral 2030 pledge. Report P119, P120
  • Equalities: Older people, carers and low income residents may benefit as works focus on rural and flood-risk areas; equalities impacts will be considered at individual project level. Report P113, P139, P141
  • Staffing: Additional workload has fallen on existing staff, to be offset by recruiting 13 new roles fully funded from the revenue allocation. Report P76, P77, P78, P111

Who and where

  • Somerset residents and businesses in flood-risk areas, including 82 homes and businesses flooded in January 2026 Report P14
  • Risk Management Authority partners: the Environment Agency, Natural England, Wessex Water and the Internal Drainage Boards Report P24
  • Parish and town councils, flood groups and Local Community Networks involved in the My Community programme Report P50, P92, P99
  • Non-Governmental Organisations including the National Farmers' Union and Somerset Wildlife Trust Report P24
  • Somerson Rivers Authority, contributing to its 20-year flood risk action plan Report P81

Timeline

  • January 2026: Second wettest January on record; major incident declared on 26 January 2026 with 82 homes and businesses flooded Report P12, P13, P14
  • 10th February 2026: Under Secretary of State for Water and Flooding Emma Hardy visited Somerset to see flooding impacts Report P15
  • 4 March 2026: Full Council approved the 2026/27 budget, not yet including this new grant funding Report P101
  • 1 October 2026: Start of scheduled grant spending period Report P101
  • 30 September 2028: Deadline by which grant funds must be spent, with possible mutual extension Report P18, P101

Plain English for the jargon

  • Defra: Department for Environment, Food and Rural Affairs, the UK government department providing the grant
  • Section 31 grant: A specific government grant paid to local authorities under Section 31 of the Local Government Act
  • IDB: Internal Drainage Board, a Risk Management Authority responsible for drainage in low-lying areas
  • RMA: Risk Management Authority, organisations with statutory duties for flood and coastal erosion risk management
  • PAG: Programme Advisory Group, providing partner and community input without executive powers
  • TTC5: Tone Tone Corridor project 5, works to improve the left bank defences of the River Tone in Taunton
  • TTC10: Tone Tone Corridor project 10, works to improve flood defences at the Firepool weir
  • SUDS: Sustainable Drainage Systems, surface water management approaches
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item62

Resolved

Having been duly proposed and seconded, the Executive Resolved to:- 1. Approve in principle the funding allocation for the 15 projects for delivery highlighted within the report and delegate authority to the Executive Director for Economy, Place and Climate (CPE) in consultation with Head of Legal, the Section 151 Officer (or Deputy) and the Lead Executive Member for Communities, Environment and Climate Change to authorise the business cases for each project and funding agreements (capital and revenue budgets). 2. Delegate authority to approve the remaining allocation of funding (both capital and revenue) within the programme to the Executive Director for Economy, Place and Climate (CPE) in consultation with Head of Legal, the Section 151 Officer (or Deputy) and the Lead Executive Member for Communities, Environment and Climate Change. 3. Approve the £42.5m in capital grant being added to the Council’s capital programme.
Word for word from the decision Somerset published for this meeting. Source: democracy.somerset.gov.uk

Follow this further

Built from Somerset's papers

What the report saysPro

Report to Executive

Executive summary

The Flood Resilience Programme has now attended Scrutiny Committee twice, receiving broad support for the approach taken so far, direction of travel and the specific recommendations proposed in this report.

Four meetings of the stakeholder Programme Advisory Group have also taken place and there is broad support for the approach from Risk Management Authority partners, Non-Governmental Organisations and community representatives.

Given the challenging nature of the task, the programme is not without risk. However, the programme team have carefully evaluated risks and benefits and have set out the approach that gives the Council the best possible chance of delivering successful outcomes and effectively managing risks.

Approval for relevant actions is now required to progress.

Recommendations to Executive Committee:

1. Approves in principle the funding allocation for the 15 projects for delivery highlighted within the report and delegates authority to the Executive Director for Economy, Place and Climate (CPE) in consultation with Head of Legal, the Section 151 Officer (or Deputy) and the Lead Executive Member for Communities, Environment and Climate Change to authorise the business cases for each project and funding agreements (capital and revenue budgets).

2. Delegate authority to approve the remaining allocation of funding (both capital and revenue) within the programme to the Executive Director for Economy, Place and Climate (CPE) in consultation with Head of Legal, the Section 151 Officer (or Deputy) and the Lead Executive Member for Communities, Environment and Climate Change. 3. Approves the £42.5m in capital grant being added to the Council’s capital programme.

Reasons for Proposals

The proposals are required to ensure successful delivery of the £50m grant provided to Somerset Council, ensure that the funds are spent in accordance with Executive’s wishes and are compliant with relevant external and internal guidelines.

Report Authors: Piers Hooper, Strategic Manager, Flood Resilience Programme, Community, Place and Economy Directorate Contact Details: [email protected] [phone removed]

James Divall, Head of Service: Climate and Natural Environment, Community, Place and Economy Directorate, Contact Details: [email protected] [phone removed] Background

1. January 2026 was the second wettest on record (records go back to 1871), second only to 2014, with a third of this rain falling in only two days.

2. A major incident was called by Somerset Council on the 26th January 2026.

3. Alongside large areas of land flooding, the county saw impacts to local rail and road networks, as well as 82 homes and businesses flooded across Somerset.

4. On the 10th February 2026, Emma Hardy, the Under Secretary of State for Water and Flooding visited Somerset to see the impact of flooding.

5. The Defra grant has been provided as additional support to Somerset following the major incident.

6. The Defra grant is a Section 31 grant for Somerset to improve Flood Resilience across the County. This grant includes £42.5m for capital works and £7.5m for revenue resulting in a total allocation of £50.0m.

7. The funds must be spent by 30th September 2028, although there is an option to extend this deadline if both parties agree.

Purpose of the report

8. To provide the Executive Committee with an update on progress made to date and provide assurance that governance, resourcing, and financial management controls are being put in place.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Somerset Flood Resilience ProgrammeReport 369 KB DownloadRead as text

At this meeting

Whole meeting
60Public Question TimeOn the agenda
62Somerset Flood Resilience ProgrammeThis decision
63Saxonvale, FromeApproved

On this subject at Somerset

Search all
  1. Somerset Flood Resilience ProgrammeThis decision
  2. Somerset Flood Resilience ProgrammeNoted

More from Somerset Executive

All decisions
MeetingDecisionOutcome
7 Oct 2026 Scrutiny Recommendations to ExecutiveThe Executive Resolved to:- 1) Consider the comments and recommendations made by the four Scrutiny Committees during ... Decided Open
7 Oct 2026 Somerset Parking Review and Charging Principles – October UpdateHaving been duly proposed and seconded, the Executive Resolved to:- a) Approve a 10% increase in all existing car par... Approved Open
7 Oct 2026 Somerset’s Local Transport Delivery Plan 2026-27 to 2029-30Having been duly proposed and seconded, the Executive Resolved to:- · agree the final Local Transport Delivery Plan, ... Agreed Open
7 Oct 2026 Adoption of reviewed Street Naming and Numbering Policy for Somerset CouncilHaving been duly proposed and seconded, the Executive Resolved to approve and adopt the Street Naming and Numbering P... Approved Open
7 Oct 2026 Medium Term Financial Plan Update 2027-28 to 2031-32Having been duly proposed and seconded, the Executive Resolved to:- a) Note the updated budget gap. b) Note the revis... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies