Corporate Performance Management Report Quarter One (End of June) 2026-27

Decided Executive 5 papers

AI summarySomerset Council Executive reviews Q1 2026/27 performance report showing £29.060m forecast revenue overspend, reserves below target, and 17 of 27 high-priority measures behind target.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedQ1 performance report considered, no actions taken
Money£29.060m forecast overspendAgainst approved budget for Q1 2026/27
What happens nextScrutiny review on 14 October 2026Performance shared with Scrutiny Corporate & Strategic
Who it affectsSomerset Council services and residentsPerformance across all three Council missions

What was decided

The Executive reviewed the Q1 2026/27 performance information in appendices A, B, C and D and considered referring concerns to Scrutiny Committees. Report P7

The Executive noted the baseline position showing 88 of 100 actions on track, 9 at risk of delay and 3 off track, with 28 performance measures rated red. Report P4, P25, P26

Why

The Council adopted a refreshed Vision and Corporate Plan for 2026-28, requiring performance reporting to be restructured around three missions: Opportunity, Connection and Homes. Report P2, P9, P14

Effective performance management is needed to identify and address areas of concern. Report P10

What happens next

Quarter 1 performance will be shared with Scrutiny Corporate & Strategic at their meeting on 14 October 2026. Report P44

From quarter 2, Corporate Performance Reporting will be aligned to quarterly Risk Reporting. Report P21

The money

  • £29.060m Forecast revenue overspend at Q1 2026/27 Report P36
  • £24.780m MTFP savings required to be delivered in 2026/27 Report P36
  • £2.945m Undelivered savings carried from 2025/26 Report P36
  • £21.067m Savings achieved or on track for delivery (86%) Report P36
  • £3.713m Savings identified as at risk or unachievable Report P36
  • £67,362,952 General Fund Reserve balance (9% of Net Revenue Income) Report P36
  • £74,252,100 10% reserve requirement for 2026/27 Report P36
  • £53,009,651 Business Risk Reserve balance (7% of Net Revenue Income) Report P36

Options considered

  • Chosen: Review and note Q1 performance report. Aligns with refreshed Corporate Plan and Vision adopted for 2026-28 Report P7, P9

Implications

  • Financial: General Fund reserve at 9% (£67,362,952) is below the 10% target of £74,252,100; Business Risk Reserve at 7% also below target. Report P36
  • Financial: Forecast revenue overspend of £29.060m driven by residential placements, unregistered placement costs, Learning Disabilities pooled budget changes, and reduced income in Traffic Management, Road Safety and Parking. Report P36
  • Financial: £3.713m of required 2026/27 savings identified as at risk or unachievable; recovery plans being developed. Report P36
  • Equalities: No equalities implications identified, though poor performance in services tailored to specific protected groups could disproportionately affect those groups. Report P53, P54
  • Legal: No direct legal implications; some measures relate to statutory functions where continued underperformance could give rise to legal and regulatory risks. Report P49
  • Risk: Failure to manage performance could lead to service deterioration and failure to deliver priorities; risks are monitored through quarter 3 strategic risks report. Report P47
  • Climate: Climate change resilience is a Council Vision principle; performance affected by changes to working patterns during extremely hot and dry weather. Report P29, P58
  • Other: Corporate Peer Challenge Action Plan: 64 of 69 original actions completed, 5 remain in progress. Report P38

Who and where

  • Children with SEND and their families Report P28, P29
  • Adults requiring Care Act assessments Report P29
  • Households in temporary accommodation, including families with dependent children and rough sleepers Report P29, P30
  • Children in care, particularly those placed outside Somerset or in residential care Report P30
  • Council housing tenants Report P30, P36
  • Residents across Somerset using council services Report P4, P14

Timeline

  • Q1 2026/27 (end of June 2026): Performance reporting period covered by this report Report P1, P4
  • August 2026: Executive agreed new Council Vision and Corporate Plan 2026-2028 Report P1, P14
  • 5 August 2026: Executive meeting that agreed the Corporate Plan Report P64
  • 14 October 2026: Scrutiny Corporate & Strategic meeting to consider Q1 performance Report P44
  • December 2026: Two new Green Estate Management Plans to be produced Report P29
  • March 2028: Maximum due date for Corporate Plan actions, aligning with Plan lifespan Report P18

Plain English for the jargon

  • RAG rating: Red, Amber, Green system for rating performance status
  • Q1: Quarter one, covering April to June 2026
  • MTFP: Medium-Term Financial Plan
  • SEND: Special Educational Needs and Disabilities
  • EHCP: Education, Health and Care Plan
  • B&B: Bed and Breakfast accommodation, used as emergency housing
  • Corporate Peer Challenge: Local Government Association peer review process; Somerset's took place in November 2024
  • Ideagen: Council's risk and performance management system
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

The Executive reviewed the performance information provided within appendices A, B, C and D and considered referring any matters of concern to the relevant Scrutiny Committee.
Word for word from the decision Somerset published for this meeting. Source: democracy.somerset.gov.uk

Follow this further

Built from Somerset's papers

What the report saysPro

Report to Executive, 15 pages

Executive summary

This baseline report outlines the performance of Somerset Council for quarter one (Q1, end of June ‘26) of the 2026/27 financial year and presents a refreshed approach, aligned to the new Council Vision and Somerset’s Corporate Plan 2026- 2028, which was agreed by Executive in August.

The actions and performance measures that are included within the Corporate Plan now form the basis of Corporate Performance reporting (Appendix A – Q1 2026/27 Corporate Performance Report). The report is structured around the Council's vision of "A fairer, better future" and the three missions of Opportunity, Connection and Homes, bringing together and monitoring progress of the outcomes the Council is seeking to achieve, the actions identified to achieve those outcomes, and the measures used to understand impact and improvement.

The report also includes a set of high-priority performance measures, maintaining visibility of areas of significant member and public interest.

This report provides a baseline from which progress towards outcomes will be assessed. There are currently 88 on-track actions, 3 off-track actions and 9 at risk of delay. 28 performance measures have a red RAG rating, 20 are ragged amber and 32 are ragged green. 17 of the 27 high-priority measures are reporting as behind target (11 of which are significantly behind and ragged red).

Measures that are annual or are under development and are therefore not yet available are detailed in Appendix B – Annual Performance Measures and Measures Under Development.

This report also concludes delivery progress of our Corporate Peer Challenge Action Plan, which set out priority areas for improvement for 2025/26 following the Council’s Peer challenge in November 2024 (Appendix C – Corporate Peer Challenge Action Plan Progress and Future Assurance and Appendix D – Corporate Peer Challenge Action Plan Overview). Recommendations

The Committee is asked to review the performance information provided within appendices A, B, C and D and consider referring any matters of concern to the relevant Scrutiny Committee.

Reasons for Proposals

As the Council has now adopted its refreshed Vision and Corporate Plan for 2026- 28, it is right that the Corporate Performance Report reflects this new direction and aids understanding of the Council’s delivery progress and performance.

To ensure performance management is being effectively managed, reviewed and any areas of concern identified and addressed.

Report Author: Sarah Hawkins, Head of Assurance, Performance and Risk Contact Details: [email protected] 01823 355340 Main report and supporting information

Background and purpose of report

1. This report presents a refreshed approach to corporate performance reporting for 2026/27 and outlines the performance of Somerset Council for quarter one (Q1, end of June 26) of the 2026/27 financial year.

2. The quarterly Corporate Performance Report reflects and aligns with the Corporate Plan 2026-2028, agreed by Executive in August 2026. The report is structured around the Council's vision of "A fairer, better future" and the three missions of Opportunity, Connection and Homes, providing a clear connection between the outcomes the Council is seeking to achieve for Somerset residents, the actions identified within the Corporate Plan to support those outcomes, and the measures used to understand their impact and performance improvement.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Q1 2026-27 Corporate Performance ReportAppendix A 68 pages Download
PDF
Annual Performance Measures and Measures Under DevelopmentAppendix B 5 pages Download
PDF
Corporate Peer Challenge Action Plan Progress and Future AssuranceAppendix C 6 pages Download
PDF
Corporate Peer Challenge Action Plan OverviewAppendix D 8 pages Download
PDF
Corporate Performance Management Report Quarter One (End of June) 2026-27Report 15 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 9 attended
BR
Councillor Bill RevansChair, expected
LL
Councillor Liz LeyshonVice-Chair, expected
TB
Councillor Theo Butt PhilipCommittee Member, expected
EP
Councillor Evie Potts-JonesCommittee Member, expected
MR
Councillor Mike RigbyCommittee Member, expected
HS
Councillor Heather ShearerCommittee Member, expected
FS
Councillor Federica Smith-RobertsCommittee Member, expected
SW
Councillor Sarah WakefieldCommittee Member, expected
RW
Councillor Richard WilkinsCommittee Member, expected

On this subject at Somerset

Search all
  1. Corporate Performance Management Report Quarter One (End of June) 2026-27This decision
  2. Quarter 4 Corporate PerformanceNoted
  3. Corporate Performance Management Report 2025-26 Q4Decided
  4. Corporate Performance Report 2025/2026 (Q3)Noted
  5. Corporate Performance Report (Q2)Agreed
  6. Corporate Performance Report - Q3Noted

More from Somerset Executive

All decisions
MeetingDecisionOutcome
7 Oct 2026 Scrutiny Recommendations to ExecutiveThe Executive Resolved to:- 1) Consider the comments and recommendations made by the four Scrutiny Committees during ... Decided Open
7 Oct 2026 Somerset Parking Review and Charging Principles – October UpdateHaving been duly proposed and seconded, the Executive Resolved to:- a) Approve a 10% increase in all existing car par... Approved Open
7 Oct 2026 Somerset’s Local Transport Delivery Plan 2026-27 to 2029-30Having been duly proposed and seconded, the Executive Resolved to:- · agree the final Local Transport Delivery Plan, ... Agreed Open
7 Oct 2026 Adoption of reviewed Street Naming and Numbering Policy for Somerset CouncilHaving been duly proposed and seconded, the Executive Resolved to approve and adopt the Street Naming and Numbering P... Approved Open
7 Oct 2026 Medium Term Financial Plan Update 2027-28 to 2031-32Having been duly proposed and seconded, the Executive Resolved to:- a) Note the updated budget gap. b) Note the revis... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies