City Access Congestion Reduction Proposals: Consultation Responses and Next Steps

Agreed Committee 3 papers

Greater Cambridge Partnership Joint Assembly agreed this item on Wednesday 18 January 2017. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

The Joint Assembly RECOMMENDED that the Executive Board: a) Agrees that : i. Officers should work up and assess options for a package of physical demand management measures. [i] (please see footnote i at the end of this decision notice) ii. Officers should assess existing data and evidence of desired access between destinations to create an overview of measures that will increase access while reducing congestion. iii. Physical demand measures should make the best use of the limited road space and capacity in Cambridge, in order to improve bus reliability, cycling and walking, particularly within the designated Air Quality Management Area. iv. No further work is undertaken on the package of six peak-time congestion control points consulted upon. b) Agrees that officers should continue to work up and assess options for the other seven elements of the eight-point plan consulted on, including: i. A Workplace Parking Levy: Co-design a workplace parking levy (WPL) scheme with employers with more detail available for Board and public review later in 2017: 1. To work with individual employers and groups of employers during 2017 on the details of the scheme. 2. To determine the local transport priorities that will receive the revenue raised, building on employer evidence of transport needs and coordinated with Council infrastructure planners. 3. To be coordinated with and if feasible form a part of the City Deal and the Local Enterprise Partnership’s broader engagement with the business community. 4. The roll-out to include practical support for employers looking to manage their parking demand in advance of the levy coming into effect. 5. It is recommended that as far as possible, the Cambridge WPL should resemble the Nottingham template. However, there will need to be agreement on how to charge, the price, its geographical extent, exemptions and how it will be administered and enforced. ii. On-Street Parking Controls: Note that the Cambridge City Joint Area Committee (CJAC) is considering whether to recommend changes to parking policy in Cambridge and subject to business case, the City Deal would fund consultation on new residents’ parking zones and the costs of implementation. Although the Assembly NOTED this potential action, it DID NOT SUPPORT IT . The Assembly considered this should not go ahead until there was mitigating alternatives in place to counter the potential displacement of vehicles. iii. Improved Public Space and Air Quality: Agrees that officers should: 1. Assess the possibility of establishing a Clean Air Zone and the potential for the introduction of a pollution charge in central Cambridge within the existing Air Quality Management Area. Key criteria for assessing this should be its impacts on: health; the local environment, including air quality and public realm; bus reliability and cycling; business and the economy; deliverability and value for money. 2. Ensure that initiatives to improve city centre access should continue to consider opportunities for improving the city centre experience and economy and that this should be coordinated with other work across the Partnership that has similar objectives, including planning policy. iv. Better ...
Word for word from the decision South Cambridgeshire published for this meeting. Source: scambs.moderngov.co.uk

Follow this further

Built from South Cambridgeshire's papers

What the report saysPro

Report to Greater Cambridge Partnership Joint Assembly
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Agenda Item 7 City Access Congestion Appendix AAppendix 6 MB Copy on its way
PDF
Agenda Item 7 City Access Congestion Appendix BAppendix 7 MB Copy on its way
PDF
City Access Congestion Reduction Proposals: Consultation Responses and Next StepsReport 1 MB Withheld: personal details

At this meeting

Whole meeting

On this subject at South Cambridgeshire

Search all
  1. City Access Congestion Reduction Proposals: Consultation Responses and Next StepsThis decision
  2. City Access and Bus Service Improvements - updateNoted
  3. City AccessNoted
  4. City AccessDecided
  5. City Access Update Including Mode Shift and Demand Management OptionsAgreed
  6. City Access StrategyAgreed

More from South Cambridgeshire Greater Cambridge Partnership Joint Assembly

All decisions
MeetingDecisionOutcome
14 Jun 2018 Election of ChairpersonCouncillor Tim Wotherspoon was ELECTED Chairman of the Greater Cambridge Partnership Joint Assembly. Decided Open
14 Jun 2018 Election of Vice ChairpersonCouncillor Tim Bick was ELECTED Vice-Chairman of the Greater Cambridge Partnership Joint Assembly. Decided Open
14 Jun 2018 Apologies for AbsenceThere were no apologies for absence. Decided Open
14 Jun 2018 Declarations of InterestThere were no declarations of interest. Decided Open
14 Jun 2018 Minutes of Previous MeetingThe minutes of the meeting held on 28 th February 2018 were agreed as a correct record, subject to the following amen... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies