Election of Chairperson
Decision: Councillor Tim Wotherspoon was ELECTED Chairman of the Greater Cambridge Partnership Joint Assembly. Decision page
What the committee will consider, in order, with every paper attached to its item. Milton Road is the main business.
Decision: Councillor Tim Wotherspoon was ELECTED Chairman of the Greater Cambridge Partnership Joint Assembly. Decision page
Decision: Councillor Tim Bick was ELECTED Vice-Chairman of the Greater Cambridge Partnership Joint Assembly. Decision page
To authorise the Assembly to sign the Minutes of the meeting held on 28 February 2018 as a correct record.
Decision: The minutes of the meeting held on 28 th February 2018 were agreed as a correct record, subject to the following amendment: Replacing the figure ‘200,000’ with ‘20,000’ on page 5 of the minutes in relation to the additional jobs planned in the west and to the south of Cambridge. Decision page
Decision: The Chairman notified the Joint Assembly that a petition had been received regarding Histon Road, asking to ‘implement a 20 mph speed limit for the lower part of Histon Road and a night time HGV Traffic Control Order’. The petition contained more than 50 signatures but had not reached the required 500 signatures to be formally considered by the Joint Assembly. Decision page
Update on work to further define the public transport elements of the Greater Cambridge Partnership’s transport strategy.
Decision: The Joint Assembly considered the report which updated the Assembly on the work to further define the public transport elements of the Greater Cambridge Partnership’s transport strategy, and provided a reminder of the range of schemes under development. There was broad agreement from the Joint Assembly members who welcomed the paper. Decision page
Full Outline Business Case for options for investment Cambourne to Cambridge. PAPER WITHDRAWN – Due to pause requested in Mayoral Transport Statement. Decision deferred to October 2018.
Decision: A paper on the A428 Cambourne to Cambridge had been withdrawn from the agenda due to a pause requested in the Mayoral Interim Transport Statement, as agreed a the Cambridgeshire and Peterborough Combined Authority meeting on 30 May 2018. This decision was deferred until October 2018. Decision page
To consider the preferred option preliminary design for along with the strategic outline business case as a basis for public consultation to facilitate the final preliminary design and outline business case.
Decision: The Joint Assembly considered the report which set out the preferred option design for which met the original objectives of the scheme and took into account the considerable public engagement that had taken place. Joint Assembly members were broadly supportive of the overall design and approach being recommended to the Executive Board for . In addition to this the Joint Assembly supported the further exploration of a Traffic Regulation Order to be part of the plans and proposals going forward... Decision page
To update on the programme including a detailed intelligent signals review delivery plan and to give approval to consult on demand management principles and measures. PAPER AMENDED – Update on Programme, including report on future transport requirements. Decision on demand management principles deferred to October 2018 due to pause requested in Mayoral Transport Statement.
Decision: The Joint Assembly considered the report which provided an update on work to explore a number of options for reducing congestion and improving air quality in and around Cambridge. Joint Assembly members were broadly supportive of the proposals set out in the report and for work proceeding on this. Decision page
To consider the outcomes of initial engagement and approve public consultation on proposals during 2018.
Decision: The Joint Assembly considered the report which provided an update on the progress of the creation of a network of and set out a programme designed to deliver short term improvements to the network. Joint Assembly members indicated their broad support for the initiative. Whilst supporting the initiative however, concerns were raised regarding the maintenance of and the importance of schemes coming forward with a maintenance plan was highlighted. Decision page
Presenting results of public consultation and to note preparation of Outline Business Case. PAPER AMENDED – Presenting results of public consultation and approval of programme quick wins. Decision on strategy approach deferred to October 2018 due to pause requested in Mayoral Transport Statement. The Survey Responses 2018 can be viewed here: www.greatercambridge.org.uk/cambridgesoutheast
Decision: The Joint Assembly considered the report which set out the results of the public consultation on the Cambridge South East Transport Study. Decision page
To monitor progress across the GCP workstreams including financial monitoring information.
Decision: The Joint Assembly received and noted the Quarterly Progress Report. Decision page
To note that the next meeting will take place at 2pm on Thursday 20 September 2018.
Decision: The Joint Assembly noted that the next meeting would take place on Thursday 20 September 2018 at 2pm. Decision page
Item 10 is where most of this meeting's papers sit: 4 papers, about 45 MB.
To consider the preferred option preliminary design for along with the strategic outline business case as a basis for public consultation to facilitate the final preliminary design and outline business case.
This committee has dealt with the subject before.
Get the decision the day it is recorded, and anything that comes back to the committee on this subject.
All 12 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
The committee last met on 28 February 2018. 5 of its items lead into this meeting; 3 items are new. Point at any item to follow a thread. Procedural items are left out.
Questions from Members of the Public, Histon Road: Bus, Cycling and Walking Improvements Final Concept, Western Orbital: Progress on Additional Park & Ride capacity; and Submission to Highways England on Girton Interchange and M11 Smart Motorway, Greater Cambridge Partnership Future Investment Strategy do not return this time.
See the 28 February meetingEvery Greater Cambridge Partnership Joint Assembly meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
South Cambridgeshire, Greater Cambridge Partnership Joint Assembly
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Greater Cambridge Partnership Joint Assembly, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.