Resolved
The Executive Board: 1) AGREED to support the preferred option design shown in Plans 1-3 as a basis for public consultation and further detailed design work, including preparation of the business case. 2) NOTED the new cost estimate of £16M in capital costs for delivery of this scheme. 3) AGREED to consider a Traffic Regulation Order (TRO) in respect of parking on verges in as part of the consultation on the scheme.