Council, Thursday 28 November 2019

General Fund Capital Programme Update and New Bids

Agreed Committee 2 papers

Council agreed this item on Thursday 28 November 2019. Below is the council's own wording, with the papers it was decided on.

Item8f

Resolved

Council AGREED 1. The allocation of additional funding of £545,000 from the Renewables Reserve to complete the footpath lighting upgrades given the environmental benefits, acknowledging that a full report would be submitted to Cabinet for approval that outlines the programme of work, timescales, costs and payback period; 2. The allocation of funding of £1,300,000 from the Renewables Reserve for a range of energy efficiency and green energy measures at South Cambridgeshire Hall, acknowledging that a full report would be submitted to Cabinet for approval that outlines the range of modifications and enhancements proposed, costs and payback period; 3. The revised General Fund capital programme for the period 2019/2020 to 2024/2025, reproduced at Appendix C of the report of the Head of Finance, to reflect the new scheme bids, amendments to the programme and the reprofiling of expenditure identified in the report.
Word for word from the decision South Cambridgeshire published for this meeting. Source: scambs.moderngov.co.uk

Follow this further

Built from South Cambridgeshire's papers

What the report saysPro

Report to Council
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Budget reviewAppendix C 70 KB Copy on its way
PDF
General Fund Capital Programme Update and New BidsReport 502 KB Copy on its way

At this meeting

Whole meeting

On this subject at South Cambridgeshire

Search all
  1. General Fund Capital Programme Update and New BidsThis decision
  2. General Fund Revenue and Capital Budget 2026/27Approved
  3. General Fund Medium Term Financial Strategy (MTFS)Approved
  4. General Fund Revenue Bids and SavingsNoted
  5. General Fund Revenue and Capital Budget 2025/26Approved
  6. General Fund Medium Term Financial Strategy, Cabinet 24 September 2024Approved

More from South Cambridgeshire Council

All decisions
MeetingDecisionOutcome
17 Mar 2026 Consultation on a Centrally Led Development Corporation for Greater CambridgeCouncil has provided feedback to the Cabinet on the proposal to establish a Centrally Led Urban Development Corporati... Decided Open
24 Feb 2026 2026-27 Corporate Action PlanThe Council voted (30 voting in favour, 10 voting against, 0 abstaining from voting)) and resolved to: a) Approve and... Approved Open
24 Feb 2026 Capital StrategyThe Council voted (30 voting in favour, 10 voting against, 0 abstaining from voting) and resolved to approve the upda... Approved Open
24 Feb 2026 Treasury Management StrategyThe Council voted (30 voting in favour, 10 voting against, 0 abstaining from voting) and resolved to approve the upda... Approved Open
24 Feb 2026 General Fund Revenue and Capital Budget 2026/27The Council voted (10 voting in favour, 30 voting against, 0 abstaining from voting) on an amendment moved by Council... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies