Item8a
Resolved
Council Agreed to A) Acknowledge the 2021/22 general fund revenue outturn position as summarised in Appendix A, the operational underspend of £0.490 million, and the shortfall after income from Taxation and Government Grants in the year of £0.747 million, and the explanations provided for the variances compared to the revised 2021/22 revenue budget; B) Acknowledge the consequent increase in the General Fund as at 31 March 2022 of £2.955m to around £14.7m; C) In relation to the Capital Programme: (i) Note the 2021/22 capital outturn of £32,420 million; (ii) Acknowledge the performance achieved in relation to the Capital Programme schemes substantially completed in 2021/2022, summarised in Appendix B. (iii) Approve the carry forwards of £3.344 million in relation to General Fund capital projects due mainly to slippage.