Item9
Resolved
Cabinet agreed to (a) Acknowledge the 2023/24 revenue outturn position and the net underspend in the year of £0.511 million, and the explanations provided for the variances compared to the revised 2023/24 revenue budget. (b) Acknowledge the overall increase in the Housing Revenue Account balance as at 31 March 2024 to £3.007 million. (c) In relation to the Capital Programme: (i) Note the 2023/24 capital outturn of £56.622 million. (ii) Acknowledge the performance achieved in relation to the Capital Programme schemes substantially completed in 2023/24, summarised in Appendix A. (iii) Approve the carry forward amounts of £16.2 million to 2024/25 in relation to HRA housebuilding during 2023/24, due to slippage and £0.339 million for capitalised repairs.
Word for word from the decision South Cambridgeshire published for this meeting.
Source: scambs.moderngov.co.uk