Resolved
a. That the budgeted and forecast Capital Programme expenditure in 2018/19 and its funding be noted; b. That the new and amended schemes be approved; c. That the 2018/19 budget virements approved under delegated authority be noted; d. That the recommendations regarding the acquisition of land in connection with the Avonmouth / Severnside Enterprise Area (Appendix 7 – Exempt) be approved; e. That the £75k reprofiling of capital expenditure from 19/20 to 18/19 be approved; f. That the £75k to underwrite a potential maximum contribution shortfall to the Winterbourne Medieval Barn project be approved.