Resolved
AGREED: That the report be noted with any further comments to be provided following detailed consideration.
AI summarySouth Holland councillors note Castle Sports diving pool pump failure, with replacement still being made in Italy more than three months after the original broke down.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
AGREED: That the report be noted with any further comments to be provided following detailed consideration.
The Castle Sports diving pool pump was replaced in July 2025. The pump completely failed in February 2026. This report sets out the timeline involved in bringing the matter to the current position. The players in the timeline are SHDC, Parkwood, the Council’s leisure operator/agent, Xylem Water Solutions, the pump manufacturer, and Glen Farrow, the Council’s pool plant contractor.
Summary Timeline:
1. 16/02 – following a fault report from Parkwood, Glen Farrow attend to replace the pumps ‘N Plate’ as advised by Xylem, the pump manufacturer, but when attending find a series of damaged O rings, preventing repair, which Glen Farrow immediately advise to SHDC. 2. 16/02 – SHDC Assets team approve purchase order for new O rings. 3. 06/03 – O rings eventually arrive through the supply chain from Italy and are replaced but do not resolve the problem as the pump then throws an error code. Glen Farrow consult Xylem on the code and are advised it is a motor error associated with the rotor. 4. 08/03 – Xylem engineer attends call out to pump to inspect and clarify the issue. 5. 09/03 - Xylem contacted by SHDC following their site visit; SHDC are advised that if the issue is a manufacturing fault, the pump will be covered by warranty and repaired/replaced, to determine the fault fully, the pump will need to removed by Glen Farrow and returned to the manufacturer for full technical inspection, a full report should be completed within 10 working days of the pump being returned to Xylem. 6. 09/03 – ELDC Mechanical and Electrical engineer consulted on the pump fault and rotor issue; their review, as others had been, suggested the most likely cause of the problem being cavitation (aggressive bubbling) which had been experienced previously at the pool with former equipment and is well documented as causing serious system damage. 7. 12/03 – SHDC Asset team advise Leisure team a new pump will be arranged with the current one sent back to the manufacturer for full assessment. If repaired under warranty, it then becomes an item held as stock. 8. 13/03 – SHDC ask Glen Farrow to remove pump and return to manufacturer for assessment and replace the one removed. 9. 07/04 – SHDC chase Glen Farrow on position with new pump who advise they will chase Xylem. 10. 13/04 – SHDC chase position with replacement pump further with Glen Farrow who advise they couldn’t actually find that SHDC had issued a purchase order, however, the lead engineer had been away on leave and would check further. 11. 21/04 – SHDC again chase Glen Farrow on position with the replacement pump to be advised for the first time that SHDC purchase orders go to the company’s general account and can sometimes not be forwarded into the engineering team so the purchase order was copied directly to lead engineer by SHDC which is the model now followed for all Glen Farrow orders. 12. As at 22/05, the pump was still in manufacture in Italy as they are bespoke orders, and not items held as stock. As with the O ring supply, the lead time for the pump has been significantly longer than the two to four weeks initially advised.
PMP Note the issue, making any recommendations it sees appropriate.
As a scrutiny body, PMP have asked for this summary and will make any recommendations it sees appropriate.
Other Options Considered
No other options than to present the summary requested are acceptable.
1. Report
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Castle Sports Swimming Pool Pump UpdateReport | 139 KB | DownloadRead as text |
Follow Performance Monitoring Panel at South Holland and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | ActionsAGREED: That the update to actions be noted. | Agreed | Open |
| 2 Sep 2026 | Key Decision PlanAGREED: That the be noted. | Agreed | Open |
| 2 Sep 2026 | Overview and Scrutiny Annual Report 2025/26AGREED: That the Overview and Scrutiny Annual Report 2025/26 be noted and recommended to Council. | Agreed | Open |
| 2 Sep 2026 | Performance Monitoring Panel Work ProgrammeAGREED: That the Work Programme be noted. | Agreed | Open |
| 26 May 2026 | Key Decision PlanAGREED: That the be noted. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.