Agreed Planning 1 paper

AI summarySouth Holland District Council's Planning Committee approved 76 homes at Horseshoe Road, Spalding, subject to conditions and a Section 106 agreement. [D] There will be no upfront affordable housing or financial infrastructure contributions, and a viability review could recover contributions. [P247] [P219]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreed76 homes with conditions and a Section 106 agreement. [D]
MoneyNo upfront contributions [P247]Nil upfront contributions. [P247] A review may secure contributions. [P219]
What happens nextFinalise agreement and conditions [D]The Planning Manager receives authority over the schedule. [D]
Who it affectsResidents and services [P218] [P239]Housing, transport, school and health needs remain. [P218] [P239] [P240]

What was decided

South Holland District Council's Planning Committee approved the full application for 76 dwellings and associated infrastructure at Land at Horseshoe Road, Spalding, subject to the section 9.0 conditions and a strengthened Condition 20. Report P24

Approval accepts nil upfront affordable housing and financial Section 106 contributions. The Section 106 agreement will secure a viability review with triggers and arrangements for any resulting contributions, significant on site biodiversity gains through a Habitat Management and Monitoring Plan, and delivery of the play area and public open space by agreed occupation dates. Report P247, P143

Delegated authority was given to the Planning Manager to finalise the Section 106 agreement, the wording of the conditions and the approved document schedule.

Why

The site is allocated for housing, and the 76 homes would support housing delivery. This was given substantial weight because the council cannot demonstrate a 5 year housing land supply. Report P176, P193, P246

Independent viability evidence found the amended scheme could not support affordable housing or financial contributions, and this evidence received substantial weight. The absence of 19 affordable homes and requested infrastructure funding remained a material disadvantage. Report P216, P217, P218

The transport assessment showed safe access and capacity for the likely traffic, while the Highway Authority did not identify a specific junction, safety or capacity failure. The lack of strategic transport funding still weighed against the proposal, but did not alone justify refusal. Report P265, P268, P269, P321

What happens next

The Section 106 agreement must be completed with review triggers, arrangements for any resulting contributions, delivery and long term management of significant on site biodiversity gains through a Habitat Management and Monitoring Plan, and agreed deadlines for the play area and public open space. Report P142, P143, P448

The Planning Manager must finalise the agreement, condition wording and approved document schedule.

The approval requires delivery of access, footway, parking, drainage, flood resilience, landscaping, travel and lighting works. Visibility splays are required before access use, the pedestrian link and Broadway bus stop improvements before occupation, and all 76 dwellings must connect to the public foul sewer before occupation. Report P287, P289, P293, P307, P344, P365, P369, P415, P449

The money

  • £461,700 Requested towards the Spalding Western Relief Road Report P104, P222
  • £76,000 Requested towards bus service operations Report P104, P222
  • £993,299.46 Requested for primary, secondary and sixth form education Report P116
  • £69,521.76 Requested towards additional healthcare capacity, subject to indexation, with payment upon completion of 50% of the dwellings in each phase Report P118
  • £772,676 Residual land value in the updated independent appraisal Report P113
  • £785,125 Viability benchmark in the updated independent appraisal Report P113
  • £6,075 Requested per dwelling towards the Spalding Western Relief Road Report P104
  • £1,000 Requested per dwelling towards bus service operations Report P104

Options considered

  • Chosen: Approve with conditions and a Section 106 agreement. Independent viability evidence and the housing benefit of 76 homes on an allocated site justified nil upfront contributions, subject to conditions and a viability review. Report P246, P247
  • Rejected: Require 19 affordable homes upfront. The independent assessment found the amended scheme could not support affordable housing. Report P214, P216
  • Rejected: Require the requested transport, education and healthcare contributions upfront. The independent assessment found the amended scheme could not support these contributions, although their absence remained a material disadvantage. Report P214, P242
  • Rejected: Refuse because the Highway Authority objected. The transport assessment showed capacity and no specific junction, safety or capacity failure was identified. Report P268, P269, P282
  • Rejected: Allow package treatment plants for frontage dwellings. The Environment Agency held an objection, and officers considered a mains connection condition necessary. Report P120, P121, P123
  • Rejected: Require treatment capacity confirmation before occupation. Anglian Water identified available capacity on the submitted information, and officers considered the condition unnecessary given the site's allocated status and likely development timescale. Report P125, P371
  • Chosen: Require public sewer connections for all 76 dwellings. The condition excludes non mains foul drainage and requires the necessary drainage infrastructure to be operational before occupation. Report P369, P372

Implications

  • Financial: The approval accepts nil upfront affordable housing and financial Section 106 contributions. This leaves 19 affordable homes and identified transport, education and healthcare needs unmet. Report P214, P218, P244, P247
  • Financial: The viability review provides a route to secure contributions if the scheme's finances improve, but no future payment was assumed in the decision. Report P219, P242, P248
  • Legal: Completion of the Section 106 agreement is required, alongside the report's conditions. The Planning Manager has delegated authority to finalise the agreement, condition wording and approved document schedule.
  • Risk: The site is in Flood Zone 3 and remains dependent on flood defences, drainage infrastructure and maintenance. Conditions would secure flood resilience, coordinated levels and protection of neighbouring land. Report P45, P342, P344, P345
  • Risk: Surface water discharge would be limited to a combined maximum of 5 litres per second. The detailed drainage design must coordinate housing, habitats, neighbouring land and watercourse access. Report P350, P365
  • Climate: The surface water strategy includes a climate change allowance. An updated Travel Plan would identify implementation, monitoring and further measures if targets are not achieved. Report P294, P306, P348
  • Other: The Section 106 agreement must provide security for significant on site habitat creation and enhancement, together with its delivery, monitoring and long term management. Report P143
  • Legal: Lincolnshire County Council's refusal recommendation was maintained before approval. The conditions do not represent technical endorsement by the Highway Authority and do not replace strategic contributions. Report P266, P310, P319

Who and where

  • People needing affordable homes in South Holland Report P200, P218
  • Children needing school places Report P239
  • People needing additional NHS capacity Report P240
  • People using bus services in Spalding Report P105, P222
  • People using roads around the development Report P265, P282
  • Existing neighbours of the site Report P419, P421
  • Future residents of the 76 homes Report P25, P292, P444
  • Children needing nearby play space Report P447

Timeline

  • 22 May 2025: The application was received. Report P6
  • 21 October 2026: The Planning Committee approved the application, subject to conditions and the Section 106 agreement. Report P3
  • Before commencement: A Biodiversity Gain Plan and Habitat Management and Monitoring Plan must be prepared. Report P142
  • At agreed stages: Viability is to be reassessed, with contributions secured if the scheme becomes sufficiently viable. Report P219
  • Before the relevant access is brought into use: Visibility splays must be provided and retained free from obstruction. Report P287
  • Before development of the relevant plot or block commences: Revised floor plans and elevations are required for plots 55 to 58 and the S107 block. Report P423, P443
  • Before occupation: The pedestrian connection, Broadway bus stop improvements and public foul sewer connections must be completed. Report P289, P307, P369
  • By an agreed stage of occupation: The play area and public open space must be completed and available for use. Report P448

Plain English for the jargon

  • Section 106: A legal agreement used to secure planning obligations, including affordable housing and financial contributions. [P196]
  • Viability review: A review of the scheme's finances at agreed stages, allowing contributions to be secured if viability improves sufficiently. [P219]
  • Biodiversity net gain: The 10% biodiversity gain considered achievable by the ecological adviser. [P141]
  • Habitat Management and Monitoring Plan: The plan required before commencement for delivery and long term management of significant on site biodiversity gains. [P142] [P143]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item41

Resolved

AGREED: That the application be approved subject to the conditions outlined at section 9.0 of the report, with strengthening to Condition 20, and completion of a Section 106 agreement securing: - A viability review mechanism, including review triggers and arrangements for any resulting contributions. - Delivery and long-term management of significant on-site biodiversity gains through an agreed Habitat Management and Monitoring Plan. - Delivery of the play area and public open space by agreed occupation dates. That delegated authority be given to the Planning Manager to finalise the Section 106 agreement, the wording of the conditions and the approved-document schedule, and to issue the ... view the full minutes text for item 41.
Word for word from the decision South Holland published for this meeting. Source: democracy.sholland.gov.uk

Follow this further

Built from South Holland's papers

What the report saysPro

Report to Planning Committee

SOUTH HOLLAND DISTRICT COUNCIL

Report of: Lead Development Management Planner (Interim) - BBC & SHDC

To: Planning Committee - 21 October 2026

(Author: Mark Niland - Planning Officer)

Purpose: To consider Planning Application H16-0515-25

Application Number: H16-0515-25 Date Received: 22 May 2025

Application Type: FULL

Description: Residential development of 76 dwellings and associated infrastructure

Location: Land at Horseshoe Road Spalding

Applicant: Seagate Homes (UK) Limited Agent: Robert Doughty Consultancy Ltd

Ward: Spalding Monks House Ward Councillors: Cllr S Chauhan Cllr | H Sheard

You can view this application on the Council's web site at http://planning.sholland.gov.uk/OcellaWeb/planningDetails?reference=H16-0515-25

1.0

1.1

1.2

2.0

2.1

2.2

2.3

2.4

REASON FOR COMMITTEE CONSIDERATION

The application is presented to Planning Committee owing to the significant planning issues arising from the proposed absence of affordable housing and financial infrastructure contributions, the independent viability assessment, and the objections maintained by Lincolnshire County Council.

Officers considered the above topics reason to bring this item before planning committee. PROPOSAL

Full planning permission is sought for the erection of 76 dwellings with associated access, estate roads, parking, landscaping, public open space, a local area for play and drainage infrastructure.

The proposed accommodation comprises eight one-bedroom, seventeen two-bedroom, forty- five three-bedroom and six four-bedroom dwellings. The layout includes detached, semi- detached and terraced properties, together with a group of four one-bedroom quarter houses.

A principal vehicular access would be formed from Horseshoe Road. Further access arrangements serve the frontage properties. The scheme includes a footway along the site frontage connecting to the existing pedestrian network, internal pedestrian links, parking and cycle provision.

Public open space and a local area for play are proposed west of the principal access road. A surface-water attenuation area lies further south, with additional landscape planting and drainage features distributed throughout the development. A maintenance corridor is identified 2.5

2.6

3.0

3.1

3.2

3.3

3.4

4.0

4.1

4.2

4.3

alongside the eastern boundary watercourse.

The application has been amended during its consideration, including changes to dwelling types, garage provision, access details and the internal layout. The current site layout is drawing 10035-SGH-AR-SL-002 revision P11, which is viewable on the Council's online planning register.

The applicant proposes no upfront affordable housing or financial planning contributions on viability grounds. The Council's independent assessor supports that position. Biodiversity net gain and a viability review mechanism would nevertheless be secured.

SITE DESCRIPTION

The application site comprises approximately 2.93 hectares of agricultural land on the southern side of Horseshoe Road, on the western side of Spalding. It is allocated for residential development as site MONO05 in the South East Lincolnshire Local Plan 2019.

Existing residential development is situated adjacent to the site, including properties to the west and east. Agricultural land extends beyond the southern boundary. Horseshoe Road forms the northern frontage.

The site is generally flat. Watercourses, boundary vegetation and scattered trees contribute to its existing character.

The site lies within Flood Zone 3. The submitted Flood Risk Assessment considers the protection provided by existing flood defences and the local drainage network, together with residual flood risk and proposed mitigation.

RELEVANT PLANNING POLICIES

The development plan includes the South East Lincolnshire Local Plan 2011-2036. The policies relevant to this application include:

‘Policy 1: Spatial Strategy.

‘Policy 2: Development Management.

‘Policy 3: Design of New Development.

‘Policy 4: Approach to Flood Risk.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
H16-0515-25Report 17 MB Copy on its wayRead as text

At this meeting

Whole meeting

Who was there

0 of 18 attended
BA
Councillor Bryan AlcockCommittee Member, expected
JA
Councillor James AveryChairman, expected
PB
Councillor Paul BarnesCommittee Member, expected
AC
Councillor Allan C BealVice-Chairman, expected
HJ
Councillor Henry J W BinghamCommittee Member, expected
CJ
Councillor Christopher J T H BrewisCommittee Member, expected
AC
Councillor Anthony CassonCommittee Member, expected
SH
Councillor Sophie HutchinsonCommittee Member, expected
PA
Councillor Paul A RedgateCommittee Member, expected
TS
Councillor Thomas SneathCommittee Member, expected
AC
Councillor Andrew Charles TennantCommittee Member, expected
JT
Councillor Jack TyrrellCommittee Member, expected

All 18 on the meeting page

More from South Holland Planning Committee

All decisions
MeetingDecisionOutcome
21 Oct 2026 H16-0683-26AGREED: That the application be approved subject to the conditions outlined at section 9.0 of the report. (Moved by C... Agreed Open
21 Oct 2026 H14-0731-26AGREED: That the application be refused for the reasons stated at section 9.0 of the report. (Moved by Councillor Hut... Agreed Open
21 Oct 2026 Planning AppealsAGREED: That the report be noted. Agreed Open
23 Sep 2026 H09-0721-25AGREED: That the application be approved subject to the conditions outlined at section 9.0 of the report and addition... Agreed Open
23 Sep 2026 H16-0692-25AGREED: That the application be deferred to gain further clarity on the assessment of the entrance and exit of the si... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies