(1) Report number LEG/0167 presented by the Solicitor to the Council on behalf of the Property Performance Management Group outlining the current position relating to the investigation of contamination at the Council’s Wharf Road Car Park, Stamford; (2) The pollution of controlled waters is likely to arise as a result of the contamination and the Council has a duty to prevent this; (3) The current provision of an interceptor only decontaminates surface water before it enters the River Welland, the full remediation works would also clean ground water by removing the contamination; (4) Option B would only disrupt the use of the car park for eight weeks and the costs of the works would be £235,000 plus VAT; (5) Short-term monitoring of effectiveness of the works would be required; (6) The remediation would be sustainable, resulting in the site being suitable for re-use as commercial or residential without gardens; (7) An application has been submitted to DEFRA’s Capital Project Programme. Options A and B, during initial discussions, have been identified as favourable because they present a sustainable solution. Alternative Options considered and assessed: (1) Constructing a barrier only (option A): rejected as the Council would be totally reliant on the barrier for providing protection; (2) Complete source removal by dig and dump and installation of barrier (option C): rejected because of longer-term and complete disruption to car park and works would not provide sustainable remediation thereby reducing the chance of receiving a grant from DEFRA.
Word for word from the decision South Kesteven published for this meeting.Source: moderngov.southkesteven.gov.uk
• To inform Cabinet of the current position relating to the investigation of contamination at the Council’s Wharf Road Car Park, Stamford. • To consider the options available for cleaning up the site. • To recommend the remediation strategy for implementation subject to inclusion in the Capital Programme to be put before full Council in September 2004
Summary
The car park shown edged red on the attached plan has been declared statutorily contaminated land resulting from its former use as a Gas Works. The Council has a duty to enforce remediation of contamination under Part IIA of the Environment Protection Act 1990. As current owner of the land, the Council may have a liability to carry out the remediation required.
2. DETAILS OF REPORT
Introduction
In accordance with its Contaminated Land Inspection Strategy, the Council has investigated contamination at its Wharf Road Car Park Stamford. As a result of this investigation, the Council has made a declaration that the land is contaminated. The Council is the freehold owner of the site, which it inherited from the Mayor Aldermen and Burgesses of the Borough of Stamford. Part only of the whole gas work site was purchased. The remainder was retained by the Gas Board until 2002 when it was transferred to a property developer for residential development. Planning permission has now been granted for the development of that site which is shown edged blue on the attached plan with thirteen town houses. This planning permission is subject to a condition relating to approval of voluntary remediation scheme for that site. The developers have submitted their remediation scheme and the Environment Agency and the Council have approved the proposed remediation subject to conditions. This involves the construction of a barrier between the Council owned land and the development land to prevent any flow of contaminants from the Council land to the development land
Current Position
The Council has carried out a full contamination survey of its site and, as a result of this survey, has made a declaration that the site is contaminated because ‘the pollution of controlled waters is likely to be caused’. As such, the site must be cleaned up to prevent contaminants entering into the ground water. As enforcer of the contaminated land regime and landowner, the Council must consider the type of clean up required for this land.
2 3. OPTIONS AND FINANCIAL ANALYSIS
The options for remediation vary in cost and in degree of disruption to the car park. Options available are detailed below: (note: all prices and timescales quoted are subject to a full tendering process and can only be estimates at this stage)
(A) Barrier only.
• Cost:£145,000 + vat • Timescales: 4 Weeks • Advantages: Sustainable remediation, Quick, low cost solution, Minimal disruption to car park (northern section of car park likely to remain operational throughout works) • Disadvantages: Totally reliant on barrier providing protection, Site to remain for car park end use only, long term monitoring required
(B) Barrier & Hotspot removal
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.