Item66
Resolved
(1) On 11 th July 2005 the Cabinet considered a draft Town Centre Action Plan that set out a broad range of actions relating to the town centre Category A priority. The document, with a small number of modifications, was approved for consultation purposes; (2) Noting the summary of representations received, the subsequent commentary, and relevant amendments; (3) Noting advice from the Head of Planning Policy & Economic Regeneration regarding the representations which made specific reference to the Welland Quarter: the Welland Quarter had been identified as an area with opportunity for regeneration but there were a number of issues and constraints to be resolved. In the meantime, the Council would proceed with the Town Centre Action Plan through to the Master Plan stage; (4) The meeting of the Grantham local area assembly had agreed that the provision of a travel interchange in the town should be pursued.
Word for word from the decision South Kesteven published for this meeting.
Source: moderngov.southkesteven.gov.uk