(1) Report number PLA555 by the Head of Planning Policy and Economic Regeneration providing an update on progress made with the development of the Council’s Local Development Framework; (2) There had been a degree of slippage to the timetable but the Head of Planning Policy and Economic Regeneration was confident that some of this lost time could be recovered; (3) Whether the slippage would affect the award of Planning Delivery Grant was unclear at the present time although the award was given on the basis of performance.
Word for word from the decision South Kesteven published for this meeting.Source: moderngov.southkesteven.gov.uk
2.1Members are asked to note the progress which has been made to date in developing the council’s Local Development Framework.
2.2Members are also asked to note the changes which are proposed in this report to the timetable and the LDS arising from delays which have already occurred and to delegate approval of a revised LDS to the Economic portfolio holder.
3. DETAILS OF REPORT PROGRESS TO DATE
3.1Statement of Community Involvement
3.1.1 The final version of the Statement of Community Involvement (SCI) was submitted to the Secretary of State on 14th November 2005. Submission coincided with a six week public consultation period, during which formal representations should have been submitted. Any representations made at this stage should have been related to one of nine tests of soundness (which have been prescribed by the ODPM and the Planning Inspectorate and are appended to this report at Appendix a) and will be considered by the Planning Inspectorate through a public examination process.
3.1.2 During the consultation period (which was extended to 6th January 2006 to allow for delays and time lost over the Christmas period) five formal Representation forms. Two informal representations and 29 letters of acknowledgement were received.
3.1.3 The main issues raised in formal representations were concerns that parish and town councils are not kept informed about changes in planning applications and decisions; the role of the planning panel in determining applications and that resources are not available to realistically manage community involvement effectively. The formal representations commented on four of the nine tests of soundness which were
-2- • No 4 – that the SCI identifies how the community and other bodies can be involved in a timely and accessible manner • No 5 – that the methods of consultation to be employed are suitable for the intended audience and for the different stages in the preparation of Local Development Documents • No 6 – that resources are available to manage community involvement effectively • No 9 – that the SCI clearly describes the planning authority’s policy for consultation on planning applications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.