(1) Report number DCS39 of the Economic Development Portfolio Holder providing progress reports for Welham Street and East Street sites and recommendations for progressing the development; (2) Design Presentation Day held on Wednesday 1 March 2006, when each of the 4 contractors who had submitted tenders gave a short presentation on their design submissions: how they fulfilled the brief and any information that may not have been clear from their submissions; (3) SMART tree technique and ratio of 50:50 price:quality to identify preferred contractor; (4) Discussions with Anglian water over the diversion of a sewer culvert; (5) Demolition works at East Street are expected to be completed by 31 March 2006. Resurfacing and setting up of a temporary parking facility are expected to be complete by 21 April 2006; (6) The District valuer has been requested to carry out a review of the site valuation on the basis that the site is cleared of buildings and free from contamination. This would highlight any funding issues between the construction of the new car park and the value of the East Street site (7) Time delays would impact on the budget, so the preservation of East Street as a car park until completion of Welham Street would ensure an income stream is protected.
Word for word from the decision South Kesteven published for this meeting.Source: moderngov.southkesteven.gov.uk
2.1Cabinet are requested to approve the following recommendations:
(i) To accept the tender submitted by Allenbuild Ltd of Derby, subject to the Contractor obtaining full planning permission and incorporating minor modifications identified at the Design Presentation Day. This was the lowest of 4 tenders received and falls within the budget provision of £2,500,000. Details of tenders are attached as Appendix A and is exempt information as described in Paragraph 3 of Part 1 of Schedule 12A of the Local Government Act 1972.
(ii) To approve officers negotiations regarding the most satisfactory option for diverting the foul sewer culvert.
(iii) To note that other variations to the project may be necessary within the overall budget provision of £2,500,000 identified within the Council’s 2006/2007 Capital Programme.
(iv) To approve the seeking of outline planning permission in preparation for the marketing of East Street.
(v) To approve the marketing of East Street from May onwards.
(vi) To note the progress achieved to date.
3.0CURRENT POSITION (Welham Street)
3.1Outline planning permission was granted on the 6th December 2005.
3.2All-inclusive tenders for the design, construction, completion and commissioning of the multi-storey car park were opened on Friday 3 February 2006. This return date reflected a request from the tenderers for an extension of time for preparing their submissions due to the volume of work entailed in ensuring full compliance with the Specification.
3.3All of the 4 Contractors invited returned tenders. These compared favourably with the budget estimate of £2,500,000 for the actual construction costs.
3.4As part of the scheme selection process, and due to the fact that they compared favourably with the budget estimate, all 4 tenderers were invited to a Design Presentation Day on Wednesday 1 March 2006. Each Contractor was afforded
2 the opportunity to give a short presentation of their individual design submission in order to demonstrate how they satisfied the design brief and elaborate on any particular innovations that may not have been obvious from the limited information submitted with their tenders. The Contractors answered a range of questions from SKDC officers and members present.
3.5A unanimous verdict from all SKDC attendees at the presentations was that the best 2 designs were from the lowest and third place tenderers by cost. Further investigation of the assessment forms completed on the day also revealed 2:1 in favour of the design submitted by the lowest tenderer.
3.6Subsequent to the presentations a scoring matrix using a SMART tree technique and a ratio of 50.50 price: quality clearly indicates the preferred Contractor as the lowest tenderer, Allenbuild Ltd.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.