Cabinet, Monday 6 August 2007 at 11.00am

*Specifications for the delivery of leisure services

Approved Executive 1 paper

Cabinet approved this item on Monday 6 August 2007. Below is the council's own wording, with the papers it was decided on.

Item23

Resolved

DECISION: The Cabinet notes the current status of the procurement process and approves the methodology of the specification and tender documentation for seeking bids and also notes an extension of time to the timetable shown in the detail of 4 weeks generally, beginning with the closing date for submission of Invitation to Submit Detailed Solutions being returned by 14 September 2007. Considerations/Reasons for decision: (1) Report number AFM0040 of the Healthy Environment Portfolio Holder providing an update on leisure procurement for the district, and the approval of specifications for the delivery of leisure services; (2) A briefing paper from the consultant setting out key elements of the procurement process and documentation attached as appendix A; (3) Work done by the leisure procurement steering group with the appointed consultant in the preparation of a specification and tender documentation for the delivery of management of the leisure centres in South Kesteven; (4) The first part of the procurement process has been completed, having been carried out in accordance with OJEU (Official Journal of the European Union); (5) The timetable of each key stage as shown in report number AFM0040
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Cabinet

Recommendations

2.1That Cabinet notes the current status of the procurement process and approves the methodology of the Specification and tender documentation for seeking bids and also an extension of time to the timetable shown in the detail of 4 weeks generally, beginning with the closing date for submission of Invitation to Submit Detailed Solutions being returned by 14th September 2007.

3. DETAILS OF REPORT

3.1The Tender Process to Date

On 15 May 2007 a notice was published in the Supplement to the official Journal of the European Union seeking expressions of interest from private sector Bidders. An information Memorandum and Pre-qualification Questionnaire were forwarded to interested parties and the completed Pre-Qualification questionnaires were returned by 22 June 2007. Bidders are now being invited to Submit Detailed Solutions (ISDS).

3.2Tender Process

As stated in the OJEU notice, the Council’s intention was to invite a minimum of three and a maximum of six Bidders to submit detailed solutions. It was then intended to reduce the number of Bidders during the evaluation and dialogue phase, so that two to three Bidders may be invited to submit Final Tenders.

The first stage of the procurement process, pre-qualification, is now complete and five Bidders have been selected. The broad detail of how the remainder of the procurement process will be conducted is set out below.

3.3Phase Two – Invitation to Submit Detailed Solutions

The aim is to enable the Council to discuss all aspects of the Leisure Management Agreement with Bidders so that a solution is reached which is capable of satisfying the Council’s needs and requirements.

During this stage Bidders will be asked to make a full priced response to the Services Specification and Payment Mechanism and to comment on the acceptability of the draft Leisure Management Agreement. This stage is designed to test Bidders’ detailed proposals.

As required by the Public Contracts Regulations 2006, the Council will assess the tenders received on the basis of the award criteria specified in this Descriptive Document. (see below). An evaluation matrix will be used to assess responses to the ISDS.

2 Clarification meetings will be held with each Bidder during this stage. Once the Council is confident that it will receive tenders capable of meeting its needs, it will formally close the dialogue phase and may invite two to three Bidders to submit final tenders for final evaluation.

3.4Phase Three – Final Tenders Phase

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
*Specifications for the delivery of leisure servicesReport 102 KB DownloadRead as text

More from South Kesteven Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 LGR - Response to Decision - Legal AdviceDecision Cabinet resolved to: A. Instruct the Director of Law and Governance to take all necessary and appropriate pr... Decided Open
21 Jul 2026 Warmer Homes GrantDecision That Cabinet: 1. Approve the acceptance of the additional £999k Warm Homes Social Housing Fund grant which h... Approved Open
21 Jul 2026 Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th... Approved Open
21 Jul 2026 2026/2027 Pay AwardDecision That Cabinet: Approved an additional budget of: · £214,000 from the Local Priorities Reserve to fund the Gen... Approved Open
21 Jul 2026 Refuse and Recycling Operational Policy UpdateDecision That Cabinet: Review and approve the updated Refuse and Recycling Operational Policy. Reasons for the decisi... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies