DECISION: (1) That the Service Manager, Asset and Facilities, in agreement with the Portfolio Holder for Healthy Environment be authorised to negotiate a short term contract extension with the present incumbent, Leisure Connection. (2) This extension will be from 1 April 2008 until 30 June 2008, but will include provision for this period to be extended further by mutual consent on a monthly basis to a maximum of six months. Considerations / Reasons for decision: (1) Report number AFM 0050 submitted by the Healthy Environment Portfolio Holder. (2) Advice received from the Monitoring Officer and Section 151 Officer Other options considered and assessed: The transfer of staff from the existing contractor, ie , Leisure Connection, to work directly with South Kesteven District Council under TUPE transfer arrangements.
Word for word from the decision South Kesteven published for this meeting.Source: moderngov.southkesteven.gov.uk
2.1It is recommended that the Service Manager, Asset and Facilities, in agreement with the Portfolio Holder for Healthy Environment be authorised to negotiate a short term contract extension with the present incumbent, Leisure Connection.
2.2It is proposed that this extension will be from 1 April 2008 until 30 June 2008, but will include provision for this period to be extended further by mutual consent in blocks of months (1 or more).
3. DETAILS OF REPORT
3.1Progress with the procurement process is good and the dialogue with the two remaining bidders will close shortly.
3.2Evaluation of their final position will then be undertaken and a recommendation upon the preferred contractor reached.
3.3The recommendation under clause 2 will provide a platform for a smooth delivery and transition for the new management contract.
4. OTHER OPTIONS CONSIDERED
4.1Transfer staff from existing contractor, ie, Leisure Connection, to work direct with South Kesteven District Council under TUPE transfer arrangements. 5. COMMENTS OF SECTION 151 OFFICER
I can confirm that the proposed budget for 2008/09 contains sufficient sums to enable the continuation of the management fee at the current level for the period stated in the report (up to a period of no greater than six months).
6. COMMENTS OF MONITORING OFFICER
The original contract has been extended in accordance with the terms of the contract in the past. This further extension is required to enable the Council to conclude its negotiations on future provision of the service for a term of 15 years. Negotiations are currently being conducted under a competitive dialogue process in accordance with the Public Contract Regulations 2006. It is expected this process should be concluded by June 2008. Any extension should not continue indefinitely.
7. CONCLUSION/SUMMARY
A short term temporary contract will allow the Council to fully plan the implementation of the new Leisure Contract including potential Trust structures.
Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.