Contingency Planning
For Large Business Failure, Closure or Accident resulting in large numbers of redundancies September 2008
Contents Page
Introduction …………………………………………………….. 1
Main Components …………………………………………….. 1
Detailed Workforce Profile ………………………………….. 2
Intervention scale …………………………………………….. 2
Identifying intervention services, products and tools … 3
South Kesteven Major Employers ………………………... 5
Breakdown of the 22 identified largest employers in South Kesteven …………………………………… 6
Conclusion ……………………………………………………… 7 -1-
Introduction
This report has been done as an action plan in case of business failure, closure or accident within the district. Large employers are defined as having over 100 employees and as such there is a risk that there could be a detrimental effect on the local economy. The action plan will assist officers and partners in delivering support should such a situation arise.
All redundancy situations are unique and elements of any local response must be developed in reaction to individual circumstances.
The key issues to consider is the role that each partner organisation can play and the tools they can apply to the situation they face. This can then be customised and developed into a strategy specific to the needs of each potential or confirmed redundancy situation.
Main Components
The main component, for a successful outcome to any redundancy situation, relies on good, rapid response from all appropriate agencies, and good communications between the company and all agencies.
The main components are:- • Protocol agreements on how the appropriate agencies will come together to establish leadership, agree strategy, and communicate with each other. • Regularly updated summaries of local labour market intelligence and workforce profiles • A protocol agreement on communications with trade unions, SKDC, the media and community at large, establishing a process to ensure that all external communications are vetted and agreed on by all relevant partners prior to general release. It should be recognised that most job losses will generate publicity and political interest at both local and national level. It is therefore important that all partners are fully briefed. • A checklist of the key issues for consideration in each major redundancy situation; the level of co-operation expected from the company; associated property issues; the expected impact on the local supply chain; and an assessment of the workforce profile against local labour market trends and opportunities. • An outline of the strengths that each agency can bring to a situation; the roles they can play; the procedures and time frames to which each agency is required to adhere to; the level of delegated authority empowered to designated representatives; and the key interventions that each agency can apply to adapt to redundancy situations.
-2-
Detailed workforce profile
Acquiring a detailed profile of the potentially displace workforce (including information on skills, qualification, age, gender, location, length of service and income levels) can greatly facilitate a rapid assessment of how readily the displaced workforce are likely to assimilate into the wider labour market. The same information will play an important role in supporting any effort to market a site to potential inward investors. Where early warning systems are effective, some or all of this information may already have been acquired by individual agencies or maybe made available by the company responsible. If the information is not readily available it maybe acquired through the use of a confidential questionnaire.
Intervention scale
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
001 Business Contingency Plan 2009 MasterReport | 179 KB | DownloadRead as text |
PDF |
Economic Development Business Contingency Action Plan 2009-2012Report | 92 KB | Download |
Follow Communities Policy Development Group at South Kesteven and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 May 2016 | Any other business, which the Chairman, by reason of special circumstances, decides is urgentIt was therefore agreed that future Communities PDG meetings would continue to be held at the current venue. | Agreed | Open |
| 8 May 2014 | Feedback from the executiveDecision Bulletins The Community Engagement and Policy Development Officer explained to the PDG that this item was fo... | Approved | Open |
| 14 Nov 2013 | Clean green and healthy strategyIt was agreed that as a district authority South Kesteven mainly supports in four of these themes through its wide ra... | Agreed | Open |
| 5 Sep 2013 | Adult safeguarding policyIt was agreed that the key was to avoid being judgemental but to make a clear judgement if informing services of any ... | Agreed | Open |
| 16 May 2013 | Private sector renewal policyAgreed The PDG agreed to hold a workshop to consider the private sector renewal policy in detail. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.