*Bourne Core Area Regeneration Proposal

Approved Executive 1 paper

Cabinet approved this item on Monday 7 February 2011. Below is the council's own wording, with the papers it was decided on.

Item55

Resolved

1) To adopt option 1 to act as lead developer and undertake proposals for delivering the Bourne Core Area development to include: i ) Refurbish Wherry’s Mill for residential flats, ii) Demolish the existing warehouse extension and develop two further blocks to the rear of the Mill containing ground floor retail units and residential flats above, iii) On the remainder of the site owned by the Council, demolish the existing garage and two residential properties to provide fully serviced development sites for a mix of residential and retail uses, iv) Provide public open space on the sites above 2) That Cabinet recommends to Council that provision of capital funding for the phased scheme be made to a maximum figure of £2.35 million. 3) That Cabinet authorises officers to undertake a marketing exercise in parallel to the commencement of the works and dispose of the development at the best price reasonably obtainable. 4) The Council to identify potential development partners or purchases for the site(s) and to enter into a development agreement for the remainder of the site. Considerations/reasons for decision: 1) Report PLA869 from the Portfolio Holder Economic Development. 2) The aim of the scheme to create a mixed used scheme on a under developed site comprising retail, residential and public realm in keeping with the townscape characteristic and providing strong linkages to the existing town centre. 3) The Retail Needs Study 2010 supports the growth of 6,400 square metres of retail development in Bourne by 2016 and 9,800 square metres by 2021. 4) Option 1 provides the Council with the greatest control while offering flexibility in terms of managing the process, securing best value and working in partnership with private sector to secure a mixed use scheme fully in keeping with the townscape of the area and delivering the aspirations of the local community. 5) Comments made by Cabinet Members at the meeting confirming commitment to the project. Other Options Considered: Two other possible alternatives have been considered to redevelop the site. 1)Proposal 1 - Refurbish Wherry’s Mill for four residential flats, demolish the existing warehouse extension, garage and two residential properties, build no housing and maintain access to the site with potential for public open space. This is the lowest cost option and requires the private sector to bring forward a development proposal on the whole of the site excluding the Mill building. The concern over this option is that the site would remain undeveloped until the market had more confidence which might leave the site empty for several years 2)Proposal 3 - Refurbish Wherry’s Mill for four residential flats or offices,demolish the existing warehouse extension and develop two further blocks to the rear of the Mill containing ground floor retail and residential flats above. On the current site of the Masonic Lodge demolish building and create new retail on the ground floor with residential flats above. On the remainder of the site demolish the garage and two residential properties and ... view the full minutes text for item 55.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Cabinet

Recommendations

1.1The Cabinet adopt option 1 to act as lead developer and undertake proposals for delivering the Bourne Core Area development to include:

a. Refurbish Wherry’s Mill for residential flats, b. Demolish the existing warehouse extension and develop two further blocks to the rear of the Mill containing ground floor retail units and residential flats above, c. On the remainder of the site owned by the Council, demolish the existing garage and two residential properties to provide fully serviced development sites for a mix of residential and retail uses, d. Provide public open space on the sites above

1.2The Cabinet recommends to the Council to provide capital funding for the phased scheme to a maximum figure of £2.35 million.

1 1.3 The Cabinet authorises officers to undertake a marketing exercise in parallel to the commencement of the works and dispose of the development at the best price reasonably obtainable

1.4The Council to identify potential development partners or purchasers for the sites(s) to enter into a development agreement for the remainder of the site.

Purpose of the report

2.1The report outlines the development opportunities for the Bourne Core Area to refurbish an existing mill building, demolish and remediate an area of 0.31 ha and bring forward for mixed use of residential and retail development in 2011/12 to 2012/13.

3. PRIORITY THEME

3.1Good for Business - Sustainable growth through promotion of key town centre sites for new retail facilities and high quality office accommodation in Grantham and Bourne

4. DETAILS OF REPORT

Background

4.1The original proposal was for a much larger scheme identified within the June 2009 Supplementary Planning Guidance of an area totalling 2.0 hectares (20,000 square metres) bordered by Burghley Street, West Street and North Street. (see Appendix A for attached map)

4.2The original suggestion in 2003/2004 was estimated to cost approximately £25 million and involved a complex array of over 35 land owners.

4.3Following the departure of the original developer and a reappraisal of the scheme a smaller more manageable proposition has been designed centred on Wherry’s Lane.

4.4The Council has previously acquired Wherry’s Mill together with Freemans Motor Repairs, 15a and 15b Burghley Street with support from other public agencies. The Council has recently acquired the Masonic Hall (see Appendix B for council landowning map).

4.5As well as the Council, the only other landowner within the site area is the County Council and early indications are that they would be supportive of any scheme that would be put forward.

4.6The Council has consulted widely on the draft proposals as part of a series of meetings held in Bourne with the business community and the local council at the end of May and the general public in early July where there was strong support for the new proposition. (see Appendix C)

Aim

4.7To create a mixed use scheme on an under-developed site comprising retail, residential and public realm in keeping with the townscape characteristics and providing strong linkages to the existing town centre.

2 Objectives

4.8The objectives for the Bourne Core Area Regeneration proposal were as follows:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
*Bourne Core Area Regeneration ProposalReport 1.7 MB DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. *Bourne Core Area Regeneration ProposalThis decision
  2. *Bourne Core AreaApproved
  3. *Approval of Bourne Core Area Site Acquisition Strategy and Priority Purchase of Sites (subject to individual non key decisions)Approved
  4. *Bourne Core AreaAgreed
  5. Bourne Core AreaAgreed
  6. *Bourne Core AreaDecided

More from South Kesteven Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 LGR - Response to Decision - Legal AdviceDecision Cabinet resolved to: A. Instruct the Director of Law and Governance to take all necessary and appropriate pr... Decided Open
21 Jul 2026 Warmer Homes GrantDecision That Cabinet: 1. Approve the acceptance of the additional £999k Warm Homes Social Housing Fund grant which h... Approved Open
21 Jul 2026 Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th... Approved Open
21 Jul 2026 2026/2027 Pay AwardDecision That Cabinet: Approved an additional budget of: · £214,000 from the Local Priorities Reserve to fund the Gen... Approved Open
21 Jul 2026 Refuse and Recycling Operational Policy UpdateDecision That Cabinet: Review and approve the updated Refuse and Recycling Operational Policy. Reasons for the decisi... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies