South Kesteven District Council
Planning Committee, Tuesday 24 September 2013 at 1.00pm

NEIGHBOURING AUTHORITY CONSULTATION ON PLANNING APPLICATION (NEWARK AND SHERWOOD REF: 13/00889/FULM), THE CONSTRUCTION AND OPERATION OF A WIND FARM CONSISTING OF FOUR 139 METRE HIGH TO BLADE TIP WIND TURBINES, AN 80 METRE ANEMOMETRY MAST AN

Agreed Planning 1 paper

Planning Committee agreed this item on Tuesday 24 September 2013. Below is the council's own wording, with the papers it was decided on.

Item174

Resolved

- That the Chairman and Vice-Chairman and Development Management Service Manager be authorised to formulate and agree the Committee’s views on the application for submission to Newark and Sherwood District Council, noting the views now expressed by the Committee. Members had before them report PLA1011 from the Development Management Service Manager on a neighbouring authority consultation from Newark and Sherwood District Council. The consultation had been considered at the last meeting and deferred to enable a detailed considered response tested against the SKDC Wind Energy SPD. Newark and Sherwood District Council had been asked to allow sufficient time, suggested at 6 weeks, for this response. The Case Officer presented an updated report, advising Members that the Case Officer at Newark and Sherwood had confirmed that the earliest committee date for consideration of the application would be early November. However, a firm assurance could not be given, and the application could be refused under delegated powers if an adjoining wind farm, currently at appeal, was dismissed. No extra time would be given for the South Kesteven response. The nearest parishes within South Kesteven , Claypole , Long Bennington and Westborough and Dry Doddington had not been consulted by Newark and Sherwood. All documents connected to the application were available on the Newark and Sherwood website, some 175 in total, and the Case Officer showed several plans of the location, at different scales, of the proposed turbines and of the proximity of nearby villages, heritage assets and other schemes within the area. Photo-montages from various viewpoints were also shown. The Committee had requested that the SPD be used as a tool to identify any areas where the application was lacking information, or where it would be clearly contrary to the SPD. It had not been possible to assess this information to the same degree as with an application in South Kesteven . However, in accordance with committee instructions officers had carried out the exercise and found the application to be deficient in a number of areas which it was considered should be pointed out as far as South Kesteven was concerned, and he then detailed these for the information of Members, as landscape/visual assessment, residential visual amenity, cumulative impact assessment, ecology, historic environment and noise. In addition, and although not previously stated, there was a need to take into account the Thacksons Well and Palmer’s Hollow appeal decisions, which would have a significant bearing on the acceptability of commercial scale wind farms in this area. In summarising, the Case Officer said that the proposal would have a significant impact on South Kesteven , and that the level of information provided was inadequate for the impact on South Kesteven to be properly assessed. On that basis the application in its current form should be refused or Newark and Sherwood should require this information to be submitted by the applicant and South Kesteven to be re-consulted. A lengthy discussion took place, during which Members considered that the response suggested in the report was not ... view the full minutes text for item 174.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Planning Committee

REPORT TO DEVELOPMENT CONTROL COMMITTEE

REPORT OF: Pat Reid – Development Management Service Manager

REPORT NO: PLA 1011

DATE: 24 September 2013

TITLE: Neighbouring Authority Consultation on planning application (Newark and Sherwood ref 13/00889/FULM)

The construction and operation of a wind farm consisting of 4 130 metre high to blade tip wind turbines, an 80 metre anemometry mast and associated infrastructure for a period of 27 years

Field reference 8884, Cotham Road, Hawton, Notts KEY DECISION OR N/A POLICY FRAMEWORK PROPOSAL:

PORTFOLIO HOLDER: N/A NAME AND DESIGNATION:

CONTACT OFFICER: Phil Moore

INITIAL IMPACT Carried out and Full impact assessment ANALYSIS: Referred to in Required: paragraph (7) below Equality and Diversity

N/A N/A

FREEDOM OF This report is publicly available via the Your Council INFORMATION ACT: and Democracy link on the Council’s website: www.southkesteven.gov.uk

Page 1 BACKGROUND Planning application S13/2071 PAPERS (Newark and Sherwood ref: 13/00889/FULM)

Page 2 1. RECOMMENDATION

1.1That Newark and Sherwood District Council be advised that due to the size and proximity of the turbines to South Kesteven there is likely to be a significant impact. Planning permission should be refused for the following reasons:

1. Visual Impact The impact on the landscape character of that part of South Kesteven District which is closest to the site i.e. The Trent and Belvoir Vales landscape character area (as identified in the South Kesteven Landscape Character Assessment) be fully assessed. This part of South Kesteven is generally low lying with flat or gently undulating topography and as such the proposed windfarm is likely to be extensively visible and would form a prominent feature within this landscape.

2. Impact on Heritage Assets The impact on any heritage assets in that part of South Kesteven District which is closest to the site, in particular the grade I listed St Peter’s Church at Claypole which is particularly prominent in the Vale as well as grade I listed Belton House and Park/Gardens. It is acknowledged that Belton House is a significant distance from the site. However, one factor that led to the dismissal at appeal (appeal ref: APP/E2530/A/08/2073384/NFW ) of the proposed Thackson’s Well windfarm at Allington (10km from Belton House) was the impact on the historically significant designed view of Belton House and its wider setting from the Belmount Tower within the park. The proposal which is the subject of this application, although 5-7km further away from Belton House, is for larger turbines and is potentially more visible within the view from Belmount Tower being less screened by intervening hills. It may be prudent for NKDC to delay the decision until the appeal for the single turbine at Marston (PINS ref: APP/E2530/A/13/2200452) has been decided, as this much smaller turbine would appear in the same view.

3. Cumulative Impact The cumulative impact of the proposed windfarm (on both landscape character and heritage assets) taking into account all consented or proposed schemes in Newark and Sherwood District that could affect South Kesteven District as well as the following other wind energy schemes in South Kesteven:

a. 5 x 125m wind turbines, Temple Hill, Brandon (Scoping Opinion – SKDC ref: S12/0857, planning application expected in September 2013) b. 1 x 100m wind turbine, Top Farm, Foston (Scoping Opinion – SKDC ref: S12/2856, planning application received, currently invalid – SKDC ref: S13/1963) c. 1 x 74m wind turbine, Green Lane, Marston (refused, currently under appeal – SKDC ref: S12/2411, PINS ref: APP/E2530/A/13/2200452)

Page 3 Also need to take the following into account:

4. The impact on residential amenities (noise and outlook) of occupiers of the nearest properties within South Kesteven, particularly those close to Valley Lane, and Fen Lane, Long Bennington.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
NEIGHBOURING AUTHORITY CONSULTATION ON PLANNING APPLICATION (NEWARK AND SHERWOOD REF: 13/00889/FULM), THE CONSTRUCTION AND OPERATION OF A WIND FARM CONSISTING OF FOUR 139 METRE HIGH TO BLADE TIP WIND TURBINES, AN 80 METRE ANEMOMETRY MAST AND ASSOCIATED INFRASTRUCTURE FOR A PERIOD OF 27 YEARS, FIELDReport 74 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. NEIGHBOURING AUTHORITY CONSULTATION ON PLANNING APPLICATION (NEWARK AND SHERWOOD REF: 13/00889/FULM), THE CONSTRUCTION AND OPERATION OF A WIND FARM CONSISTING OF FOUR 139 METRE HIGH TO BLADE TIP WIND TURBINES, AN 80 METRE ANEMOMETRY MAST ANThis decision
  2. Neighbouring authority consultation on planning application (south holland ref h03-0776-13) installation of 1 endurance 50kw wind turbine with overall tip height of 46.3m including an electrical kiosk and associated temporary infrastructure. little duke farm, main road, deeping st nicholas, spaldingAgreed
  3. Neighbouring authority consultation on planning application (rutland county council ref: 2013/0516/ful), erection of 1 no. 51.2m (hub) high, 65.7m (tip) high wind turbine plus ancillary equipment, land to the west of great north road, strettonAgreed
  4. Neighbouring authority consultation on planning application (rutland county council ref: 2013/0516/ful), erection of 1 no. 51.2m (hub) high, 65.7m (tip) high wind turbine plus ancillary equipment, land to the west of great north road, strettonDeferred
  5. Neighbouring authority consultation on planning application (newark and sherwood ref: 13/00889/fulm), the construction and operation of a wind farm consisting of four 139 metre high to blade tip wind turbines, an 80 metre anemometry mast anNoted
  6. Neighbouring authority consultation - south holland application ref. h14-0110-13 - installation of nine 126 metre (tip height), wind turbines, sub-station and access track at fen farm, south fen, west pinchbeckAgreed

More from South Kesteven Planning Committee

All decisions
MeetingDecisionOutcome
3 Sep 2026 Application S26/0096Decision It was proposed, seconded and AGREED to authorise the Assistant Director – Planning & Growth to GRANT planni... Agreed Open
3 Sep 2026 Application S26/0354Decision It was proposed, seconded and AGREED to authorise the Assistant Director – Planning & Growth to GRANT planni... Agreed Open
3 Sep 2026 Application S25/1082Decision It was proposed, seconded and AGREED to authorise the Assistant Director – Planning to GRANT planning permis... Agreed Open
16 Apr 2026 Application S26/0363It was agreed that Officers would consult with Grantham Civic Society were the application approved and a note would ... Agreed Open
16 Apr 2026 Application S25/2342It was AGREED to extend the meeting until 18.00 The meeting adjourned at 16.52 and resumed at 17.01. Proposal: Outlin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies