Resolved

- To determine applications, or make observations, as listed below:- 13:05 Councillor Morgan entered the meeting 13:08 Councillor Powell entered the meeting 13:10 Councillor Jacky Smith left the meeting having declared an interest in application S13/3444/MJRR 13:10 Councillor Stevens entered the meeting KJC1 Application ref: S13/3444/MJRR Description: Approval of reserved matters for residential development of 70 dwellings Location: Poplar Farm, Barrowby Road, Grantham, Lincolnshire, NG31 8AF Approved subject to no adverse comments from the Environment Agency Noting comments made during the public speaking session from:- · Nick Worboys – agent for the applicant together with comments from the Partnerships Project Officer, Community Archaeologist, Crime Prevention Design Advisor, Environmental Health Services and the Lincolnshire Bat Group, no objection from Natural England, a number of objections from nearby residents, an affordable housing position statement from the applicants; additional information report circulated to members before the meeting including an amended plan showing a pedestrian cycleway link, further comments from the Partnerships and Project Officer together with Development Management Officer comments thereon and two additional conditions; report of site inspection and comments made by Members at the meeting. 13:22 Councillor Ashberry entered the meeting. Being part-way through consideration of this application, Councillor Ashberry did not participate in discussion or vote on the application. Following discussion on the proposal, particularly in relation to sound insulation, the accessibility of the site and the Council policy on the clustering of affordable housing as stated in paragraph 2.1.28 to 2.1.31 of the Planning Obligations Supplementary Planning Document (SPD) it was proposed and seconded that the application be deferred for the following to be carried out: · An independent sound assessment of the railway’s impact on housing · Provision of a detailed travel plan · A traffic assessment of the development The Committee discussed the proposal and the proposer and seconder agreed to add a further requirement: “for another look to be taken at the compatibility of the location and mixture of the affordable housing development in the scheme as a whole in the context of paragraphs 2.1.28 to 2.1.31 of the Planning Obligations Supplementary Planning Document” The Lead Officer Development Management advised the Committee that Environmental Health had been consulted on the application and an acoustic fence was considered an appropriate and sufficient treatment to mitigate the impact of sound from the railway; that travel formed part of the S.106 Agreement that would be triggered as part of a later phase of the development; highways issues were considered as part of the outline application and that each application for clusters of affordable housing should be determined on its own merits. The proposal was put to the vote and lost. It was then proposed and seconded that the application be approved, with authority delegated to the Lead Officer Development Management in consultation with the Chairman / Vice-Chairman subject to the summary of reasons set out by the Case Officer in the circulated report, subject to no adverse comments from the Environment Agency and subject to the conditions and notes set out on ... view the full minutes text for item 226.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Planning Committee

Development Control Committee 11 February 2014

Additional Information

KJC1 - S13/3444

Proposal Approval of Reserved Matters for residential development of 70 dwellings, Poplar Farm, Barrowby Road, Grantham

Information Received

An amended plan has been received which shows a pedestrian cycle way link to the future development site and back into the existing estate.

Further comments from the Partnerships and Project Officer

For clarification a comparison of the proposed affordable housing provision with that approved on the neighbouring Bellway and David Wilson developments is summarised below:

David Wilson site 2 beds 3 beds

63m² 78m²

Bellway Homes 2 beds 3 beds

60m² 72m²

L&HH 2 beds 3 beds

68m² 83m² larger private space majority with 2 parking spaces sheds with secure cycle storage water butts recycling storage in property rotary dryers Code level 3

1 “As Longhurst’s affordable housing is being built to Code Level 3 which is a higher spec than private development requirements, the cost of heating these units will be reduced even though they are bigger than the Bellways and Wilsons units.

With regards to creating a sustainable community not only do you have the mix tenure, with the opportunity of staircasing out on the shared ownership and the ‘Right to Acquire’ the rented units. There is also a good mix of accommodation from one bed houses, two bed bungalows (a couple adapted), one and two bed flats and two and three bed houses. Therefore the residents on site will be mixed from single persons through to families and a mixed age range potentially from 18 years to elderly”.

Officer Comment on Information Received

The floor area of the proposed affordable units is larger than those being provided on the adjacent sites. The mix of house types and tenure is specific to meet the identified local need for affordable housing in terms of size, type and tenure.

Alterations/Additional Conditions

Two additional conditions are required in addition to those included in the main report in relation to the existing trees along the southern boundary of the site and to ensure that any future link between the extra care apartments and the hospice is not used by members of the public as a shortcut.

Condition 1

It is important to ensure that the proposed development would not have any impact on the welfare of the existing trees/hedgerow that bounds the southern boundary of the site.

A condition requiring details of the construction of the foundations for the bungalows and plots 27-31 and the vehicle parking and turning to plots 34-54 is suggested.

“Prior to the commencement of plots 27-31 and the parking and turning area to the apartments (34-54) precise details of the foundation construction shall be submitted to and approved in writing by the local planning authority.

The development shall be constructed in accordance with any such details as are approved.

Reason: To ensure that there is no significant impact on the existing trees”.

2 Condition 2

To ensure that the there is no opportunity for an informal pedestrian short cut to be established from the site through the hospice site to Barrowby Road. If any pedestrian link if proposed, prior to it being used a scheme demonstrating how it would be managed is required.

“There shall be no pedestrian link between the hospice and the application site until details are submitted to and approved in writing by the local planning authority demonstrating how the link would be managed to ensure that it is not used by members of the public. These details shall include gates/means of enclosure, and means of locking and future management.

Reason: To ensure that the access is not used by members of the public as a informal short cut to Barrowby Road to the detriment of the amenity of neighbouring occupiers”.

Changes to Recommendation

No change to recommendation.

3 JJ1 - S13/3167

Proposal: Erection of 12 dwellings and 8 flats, land off Lincoln Road, Stamford

Summary of information received:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Additional Info: 11 02 14Report 133 KB DownloadRead as text
PDF
Agenda: 11 02 14Agenda 3 MB Copy on its way
PDF
PLANNING MATTERSReport 44 KB Download

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. PLANNING MATTERSThis decision
  2. Procedure for returning consultations on planning applications being determined by neighbouring authorities and county matters being determined by Lincolnshire County CouncilAgreed
  3. Planning mattersApproved
  4. Planning mattersRefused
  5. Planning mattersApproved
  6. Planning mattersApproved

More from South Kesteven Planning Committee

All decisions
MeetingDecisionOutcome
3 Sep 2026 Application S26/0096Decision It was proposed, seconded and AGREED to authorise the Assistant Director – Planning & Growth to GRANT planni... Agreed Open
3 Sep 2026 Application S26/0354Decision It was proposed, seconded and AGREED to authorise the Assistant Director – Planning & Growth to GRANT planni... Agreed Open
3 Sep 2026 Application S25/1082Decision It was proposed, seconded and AGREED to authorise the Assistant Director – Planning to GRANT planning permis... Agreed Open
16 Apr 2026 Application S26/0363It was agreed that Officers would consult with Grantham Civic Society were the application approved and a note would ... Agreed Open
16 Apr 2026 Application S25/2342It was AGREED to extend the meeting until 18.00 The meeting adjourned at 16.52 and resumed at 17.01. Proposal: Outlin... Agreed Open