Resolved
The Committee approved the risk management annual report 2014/15
Governance and Audit Committee approved this item on Thursday 25 June 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee approved the risk management annual report 2014/15
The Governance & Audit Committee is asked to approve the risk management annual report.
In accordance with the terms of reference of the Committee it is a requirement to produce an annual report on the risk management arrangements in place and the Page 1 activities undertaken. Risk Management is fundamental to the Council’s achievement of its strategic objectives. The report being presented covers the 2014-15 period and details the various aspects of work delivered during the course of the year.
3. DETAILS OF REPORT
Risk Management Strategy
The Risk Management Strategy is currently under review and will be presented later in the year.
Risk Management Internal Audit
During the course of the year, and as part of the internal audit work plan for 2014-15, an audit was undertaken on the effectiveness of the risk management arrangements in place across the Council. The review focussed on ensuring that the current risk management processes are embedded within the Council and that all identified risks and controls are in place and agreed actions are followed up on a timely basis. This is to ensure that the Council has an adequate Risk Management Framework in place which is sufficient to identify, monitor and mitigate the risks that it faces.
The development and maintenance of an effective risk management system and assurance framework is a key element for providing on-going assurance to management and members over the effectiveness of controls identified to mitigate principal risks that threaten the achievement of strategic objectives.
The review took into account all aspects of how the Council manages risk. As part of the review internal audit identified that the Council has continued to monitor its Corporate and Business Risks as part of a formalised process and that changes in the Business Risk profile have been reported where appropriate for consideration on the Corporate Risk Register, showing that the Council has a level of understanding between the relationship between its risks.
Taking account of there being no issues identified, the Council was given a substantial assurance that the controls upon which the organisation relies to manage risk are suitably designed, consistently applied and effective.
The report itself was presented to the Committee at its meeting in March 2015.
Risk Management Group
Risk Management Group, consisting of all Business Managers (and where appropriate) Team Leaders and chaired by the Governance & Risk Officer, met bimonthly to discuss Risk Management and issues relating to Internal Audit, Insurance, Counter Fraud and Governance.
During the year the group has looked at a number of areas such as risk management, internal audits and business continuity. An overview of insurance claims is a regular agenda item and ongoing issues are also discussed and relevant officer training is provided where necessary.
Page 2 Strategic Reporting
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk Management and Business Continuity Annual ReportReport | 84 KB | DownloadRead as text |
Follow Governance and Audit Committee at South Kesteven and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Jul 2026 | Risk Management Annual Report 2025/26Agreed’; 1% ‘Not Agreed’ and 2% ‘Don’t Know’. Themes for improvement were identified for Governance, Health and Safet... | Agreed | Open |
| 25 Jun 2026 | Draft Annual Governance Statement 2025/26Decision on LGR structure expected in July 2026 · Lincolnshire Chief Executives and Leaders to develop a constituted ... | Noted | Open |
| 18 Mar 2026 | 2025-26 Action Plan for Draft Statement of AccountsIt was agreed at the previous meeting of the committee that the Section 151 Officer would present proposed actions be... | Agreed | Open |
| 18 Feb 2026 | Statement of Accounts 2024-25It was agreed with audit that this would remain unadjusted as it was below our materiality threshold of £1.7m. During... | Agreed | Open |
| 24 Sep 2025 | Risk Management Annual Report 2024/25Agreed’ with 83% of the statements on assurance with the remainder being 14% ‘Partially Agreed’; 1% ‘Not Agreed’ and ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.