Corporate Risk Register Update

Approved Finance 2 papers

Governance and Audit Committee approved this item on Thursday 1 December 2016. Below is the council's own wording, with the papers it was decided on.

Item42

Resolved

To approve the updated Corporate Risk Register as attached at appendix A of report number CFM401. The Corporate Risk Register, which formed a key part of the Council’s governance framework was presented to the Governance and Audit Committee every 6 months. The register was last presented to the Committee on 30 June 2016 when it had been updated with more strategic and longer-term risks. The existing controls were incorporated and the gross risk score identified with additional actions outlined. This update report summarised progress in delivering those actions and the anticipated timeline for their completion. Members were interested in the potential risks around the contract database. Officers explained that the existing system required manual data entry by a number of officers when a contract had been awarded. A new contract database had been procured for use across Lincolnshire which would automatically pull through contractors’ details. The new database was due to be in place by January/February 2017. Further discussion ensued around the timeline for the Council’s Corporate Governance Framework and its relationship with the Annual Governance Statement. Members turned their attention to political oversight of the award of contracts. There was discussion about the roles of Executive Members and the extent of officers’ authority and accountability. Views varied from allowing officers to work within their delegated authority, requiring oversight of tender opening by the appropriate executive member and ensuring that the whole Council was aware of contracts. The contents of the report were noted and it was proposed, seconded and agreed that it be approved.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Governance and Audit Committee

Recommendation

The Governance & Audit Committee is requested to:

i) note the contents of this report; and ii) review and approve the updated Corporate Risk Register (CRR) as attached at Appendix A

Page 1 2. PURPOSE OF THE REPORT

One of the key areas for the Committee as part of its terms of reference is to monitor and review the risk management arrangements in place, and the activities that are being undertaken in order to mitigate those risks. In accordance with the agreed work plan the Committee is presented with the CRR on a six monthly basis.

3. DETAILS OF REPORT

The Committee last reviewed the Corporate Risk Register at its meeting on 30 June 2016. Since that time officers responsible for specific actions have been implementing the necessary actions in accordance with the timeline in order to ensure the overall risk exposure is reduced. An updated narrative is shown in the column marked ‘action update’. Following the review, and in line with best practice, it is appropriate to review the risk register in its entirety to ensure it reflects the environment (both internal and external) the Council is working within and to propose any new risks that may have corporate implications. The outcomes of the review will be presented to the Committee at the next risk register update presentation in June.

The updated Corporate Risk Register, showing the progress against actions, is attached as Appendix A.

4. OTHER OPTIONS CONSIDERED

None

5. RESOURCE IMPLICATIONS

This report has no direct impact on the Council’s resources, including finance/ budget, people, land/property etc.

6. RISK AND MITIGATION (INCLUDING HEALTH AND SAFETY AND DATA QUALITY)

The contents of this report do not require impact analysis. Any action required to address risk identified may be the subject of equality analysis when the action is undertaken.

7. ISSUES ARISING FROM IMPACT ANALYSIS

None

8. CRIME AND DISORDER IMPLICATIONS

None

9. COMMENT OF FINANCIAL SERVICES

These are contained within the report.

10. COMMENT OF LEGAL AND DEMOCRATIC SERVICES

Page 2 Members of the Committee are responsible for monitoring actions taken and to be taken on behalf of the Council to identify corporate business risks and assess whether they are being effectively managed. It is essential they are kept up to date with details of the risks and how they have been mitigated.

11. COMMENTS OF OTHER RELEVANT BUSINESS MANAGER

None

Appendices

Appendix A – Corporate Risk Register

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CFM401 Appendix A DRAFT Corporate Risk Register December 2016Appendix 83 KB Download
PDF
Corporate Risk Register UpdateReport 58 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. Corporate Risk Register UpdateThis decision
  2. Corporate Risk Register UpdateNoted
  3. Corporate Risk Register UpdateApproved
  4. Risk Management, including Corporate Risk Register Update and Business Continuity Annual Report 2016/17Approved
  5. Risk Management and Business Continuity Annual Report including Corporate Risk RegisterApproved
  6. Risk Management - Corporate Risk Register UpdateApproved

More from South Kesteven Governance and Audit Committee

All decisions
MeetingDecisionOutcome
23 Jul 2026 Risk Management Annual Report 2025/26Agreed’; 1% ‘Not Agreed’ and 2% ‘Don’t Know’. Themes for improvement were identified for Governance, Health and Safet... Agreed Open
25 Jun 2026 Draft Annual Governance Statement 2025/26Decision on LGR structure expected in July 2026 · Lincolnshire Chief Executives and Leaders to develop a constituted ... Noted Open
18 Mar 2026 2025-26 Action Plan for Draft Statement of AccountsIt was agreed at the previous meeting of the committee that the Section 151 Officer would present proposed actions be... Agreed Open
18 Feb 2026 Statement of Accounts 2024-25It was agreed with audit that this would remain unadjusted as it was below our materiality threshold of £1.7m. During... Agreed Open
24 Sep 2025 Risk Management Annual Report 2024/25Agreed’ with 83% of the statements on assurance with the remainder being 14% ‘Partially Agreed’; 1% ‘Not Agreed’ and ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies