Financial Outturn 2016/17

Approved Finance 2 papers

Governance and Audit Committee approved this item on Thursday 29 June 2017. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

That the Governance and Audit Committee 1. Approves the Revenue and Capital Outturn report and associated appendices for 2016/17 2. Approves the set-asides and reserve movements as detailed in report number CFM418 3. Approves the Capital slippages from the 2016/17 Capital Programme as detailed in report number CFM418 Report number CFM418 of the Cabinet Member for Finance detailed the Council’s Revenue and Capital outturn for 2016/17 for both the General Fund and Housing Revenue Account (HRA). It provided commentary on the outturn position for both accounts and the reserves statement. The committee was also asked to consider proposed set-asides and slippages in the 2016/17 Capital Programme. The report also highlighted and gave commentary on key variances against budgeted levels, which included unexpected costs and income, and savings and efficiencies achieved. Several issues related to Council’s reserves were specifically highlighted for members: · A £52k bequest made in respect of Stamford Arts Centre · A top-up of £100k to the Insurance Fund in light of recent insurance activity · A movement in the local priorities reserves where the residual balance had been taken at the outturn position and replenished to support the Big Clean project · The triennial review of pensions planned for 2017/18 could affect the position of that reserve · An in-year increase to the Useable Capital Receipts Reserve was the result of sales of vehicles and property assets · Should the council wish to repay the £25m maturity loan in 2020, sufficient funds were available in the HRA reserve The set-asides were shown in table 3 of the report; these had been created in the first instance to fund projects in 2015/16 and carried forward to 2016/17 to complete activity. The report proposed transferring the balance of £20k in the People and Organisational Development set-aside into a specific reserve for 2017/18 to facilitate delivery of the learning and development programme for officers and members. Table 4 gave an overview of activity in relation to the Housing Revenue Account. Members’ attention was drawn to the positive position achieved in respect of rent collection and recovery. The Committee also noted that the revenue account had experienced a gain of approximately £48k as a result of the revaluation of the Council’s housing stock; this was an accounting entry and reflected changes within the wider property market. The report showed an underspend against the Capital Programmes for both the General Fund and the HRA. Members noted that at the present all capital projects were internally funded, meaning any slippage did not negatively impact on the Council’s financial position as it would have done if the projects were funded through borrowing. Within the General Fund the majority of the underspend related to slippage in the St. Peter’s Hill and the implementation of the commercial investment strategy. The priorities for the Council remained unchanged and both allocations had been included in the 2017/18 Capital Programmes. Committee members asked questions around the underspend on the HRA Capital Programme. Specific reference was made to the housing improvement programme which had seen ... view the full minutes text for item 6.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Governance and Audit Committee

SUMMARY OF GENERAL FUND ESTIMATES Appendix A

2016/17 Outturn

2016/17 2016/17 2016/17 2016/17 2016/17 Original Adjusted Outturn Variance Variance Base Base Original Adjusted £'000 £'000 £'000 £'000 £'000

1 Growth 523 511 169 (354) (342) 2 Environment 6,379 6,361 6,026 (353) (335) 3 Culture 2,885 2,958 3,104 219 146 4 Housing 1,088 1,137 1,154 66 17 5 Corporate 4,551 4,459 4,253 (298) (206) 6 Capital Charges 0 0 246 246 246 7 Accounting Adjustments (IAS19) 0 0 177 177 177

8 NET SERVICE COSTS 15,426 15,426 15,129 (297) (297)

9 Depreciation and Impairment charged to Revenue Accounts (3,028) (3,028) (3,195) (167) (167) 10 Movement in fair value of investment property 0 0 81 81 81 11 Net movement on Pension interest costs and Return on assets 0 0 1,027 1,027 1,027 12 Interest and Investment Income (185) (185) (410) (225) (225) 13 Interest Payable 12 12 12 0 0

14 NET OPERATING EXPENDITURE 12,225 12,225 12,644 419 419

15 Net movement in General Fund Specific Reserves (689) (689) (527) 162 162 16 Revaluation Gains/ (losses) 0 0 (76) (76) (76) 17 Amortisation of Intangible Assets 0 0 (84) (84) (84) 18 Revenue Contribution to Capital 500 500 657 157 157 19 Revenue Expenditure Financed by Capital Through Statute 0 0 (568) (568) (568) 20 Minimum Revenue Provision 159 159 159 0 0 21 Precepts of Local Precepting Authorities 1,548 1,548 1,547 (1) (1)

22 AMOUNT TO BE MET FROM GOVERNMENT GRANTS AND LOCAL TAXPAYERS 13,743 13,743 13,752 9 9

23 Council Tax Income (8,048) (8,048) (8,137) (89) (89) 24 Revenue Support Grant (1,700) (1,700) (1,700) 0 0 25 Business Rates (net) (4,060) (4,060) (3,169) 891 891 26 Pooling Gain (274) (274) (246) 28 28 27 S31 Business Rates Grant 0 0 (693) (693) (693) 28 Rural Grant (293) (293) (293) 0 0 29 Other Grants 0 0 (23) (23) (23) 30 Collection Fund Deficit 632 632 623 (9) (9)

31 (SURPLUS)/DEFICIT IN YEAR 0 0 114 114 114

General Fund Revenue Balances 32 (Increase)/Reduction in working balance 0 0 114 114 114 33 Balance at Beginning of Year (1,912) (1,912) (1,912) 0 0

34 BALANCE AT END OF YEAR (1,912) (1,912) (1,798) 114 114

Page 1 GROWTH Appendix A 2016/17 Outturn 2016/17 2016/17 2016/17 2016/17 2016/17 Detail Original Adjusted Outturn Variance Variance Base Base Adjusted Adjusted £'000 £'000 £'000 £'000 % Front Line Services

1 Alma Park, Grantham 13 13 13 0 0% 2 Bus Stations 96 96 92 (4) (4)% 3 Car Parks (629) (630) (692) (62) 10 % 4 Conservation 93 93 84 (9) (10)% 5 Development Management 251 256 108 (148) (58)% 6 Economic Development 462 461 430 (31) (7)% 7 Graham Hill Way, Bourne (32) (32) (39) (7) 22 % 8 Hollis Road, Grantham (7) (7) 2 9 (129)% 9 Markets 46 45 105 60 133 % 10 Mowbeck Way, Grantham (13) (13) (7) 6 (46)% 11 Northfields, Market Deeping (395) (395) (483) (88) 22 % 12 Planning Policy 428 414 338 (76) (18)% 13 Public Conveniences 163 163 170 7 4% 14 Street Numbering & Naming 47 47 48 1 2%

15 NET GENERAL FUND CHARGE 523 511 169 (342) (67)%

Page 2 ENVIRONMENT Appendix A 2016/17 Outturn

2016/17 2016/17 2016/17 2016/17 2016/17 Detail Original Adjusted Outturn Variance Variance Base Base Adjusted Adjusted £'000 £'000 £'000 £'000 %

Front Line Services

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CFM418 AppendicesReport 203 KB DownloadRead as text
PDF
Financial Outturn 2016/17Report 157 KB Download

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. Financial Outturn 2016/17This decision
  2. Draft Financial Outturn 2021/22Agreed
  3. Financial Outturn 2017/18Approved
  4. Draft Financial Outturn 2015/16Approved
  5. Draft financial outturn 2011-12Approved
  6. Financial reports for 2009/10 – Monitoring Information and forecast OutturnNoted

More from South Kesteven Governance and Audit Committee

All decisions
MeetingDecisionOutcome
23 Jul 2026 Risk Management Annual Report 2025/26Agreed’; 1% ‘Not Agreed’ and 2% ‘Don’t Know’. Themes for improvement were identified for Governance, Health and Safet... Agreed Open
25 Jun 2026 Draft Annual Governance Statement 2025/26Decision on LGR structure expected in July 2026 · Lincolnshire Chief Executives and Leaders to develop a constituted ... Noted Open
18 Mar 2026 2025-26 Action Plan for Draft Statement of AccountsIt was agreed at the previous meeting of the committee that the Section 151 Officer would present proposed actions be... Agreed Open
18 Feb 2026 Statement of Accounts 2024-25It was agreed with audit that this would remain unadjusted as it was below our materiality threshold of £1.7m. During... Agreed Open
24 Sep 2025 Risk Management Annual Report 2024/25Agreed’ with 83% of the statements on assurance with the remainder being 14% ‘Partially Agreed’; 1% ‘Not Agreed’ and ... Agreed Open