South Kesteven District Council
Cabinet, Thursday 11 January 2018 at 2.00pm

Housing Development Programme

Approved Executive 1 paper

Cabinet approved this item on Thursday 11 January 2018. Below is the council's own wording, with the papers it was decided on.

Item109

Resolved

Cabinet approves the 10 potential development sites detailed in report number RIM402 for further evaluation and inclusion in the Phase 3 – Housing Development Programme 2. That the potential benefits of delivering all of the development programme in partnership with Gravitas Ltd (a company wholly owned by South Kesteven District Council) be considered as part of the procurement options 3. Cabinet approves the adoption of a more agile approach to funding the development of housing (including essential site acquisition) by the creation of a development reserve with the ability to fund changes to the programme over time as part of the budget development process for 2018/19 Considerations/Reasons for decision: 1. Report number RIM402 of the Cabinet Member for Communities 2. A pipeline of potential new schemes utilising Council-owned land was compiled for the Homes and Communities Agency equity funding under the Starter Homes (Unlocking Land Fund) and feasibility work carried out on each of those sites 3. Recent advice from the Home and Communities Agency that the programme was unlikely to go ahead and alternative means of delivery were consequently required 4. Details of a shortlist of 10 sites, their current uses and proposed tenure 5. Data held by the Council on housing need in the areas of the district where the 10 shortlisted sites were located 6. Programme outcomes included addressing demand for new homes for sale, increasing revenue income for the Housing Revenue Account and General Fund, generating new homes bonus, increasing council tax income and generating a commercial return from sales for the Council through Gravitas 7. Greater opportunities for flexibility in procurement provided by using Gravitas as the delivery mechanism Other options considered 1. Sale of land to a developer The sale of these sites for development outside of the Council’s control would not provide any degree of certainty around the speed at which they are brought forward 2. Disposal of land to a Registered Provider Registered Providers may be interested in acquiring some of the sites. However, this would not mitigate losses arising from Right to Buy sales and would not provide any certainty as to the timescale for development at these locations. Nomination rights would need to be secured with the Registered Provider to enable people in priority need to benefit from these developments.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Cabinet

CABINET

Report of: Councillor Nick Neilson Cabinet Member for Communities

Report to: Cabinet

Date: 11th January 2018

Subject: Housing Development Programme (RIM402)

Decision Proposal: Approval to Progress Plans Relevant Cabinet Councillor Nick Neilson Member: Cabinet Member for Communities

Report author: Andrew Sweeney: [email protected] Service Manager Housing Development & Improvements Tel: 01476 406411 Date: 19th December 2017

Reviewed by: Richard Wyles: [email protected] Assistant Director Finance Tel : 01476 406210 Date: 20th December 2017

Signed off by: Tracey Blackwell: [email protected] Strategic Director Environment and Property Tel: 01476 406058 Date: 21st December 2017

Approved for Councillor N. Neilson publication Cabinet Member for Communities [email protected] Tel: 01476 406408 Date: 22nd December 2017

SUMMARY The second phase of the Council’s current affordable housing programme will be completed in December 2017 delivering 27 homes adding to the 33 delivered under the previous phase one schemes. Continuation of the programme was planned following the successful bid last year for Homes and Communities Agency (HCA) equity funding for the development of new starter homes. However advice from the HCA since the award of the bid has confirmed that the programme is unlikely to proceed. In preparation for this programme work continued over the last 12 months to determine capacity to develop new market sale and affordable homes utilising District Council owned land in line with government policy.

This report provides details of a potential programme for the delivery of 105 new homes over 10 sites in Council ownership which, if supported, would enable the continuation of the housing programme and secure the delivery of new homes in the district.

The programme includes 56 affordable homes which are intended to be brought into the Council’s own housing stock and introduces the concept of using intermediate rent levels for this new programme rather than social rent levels to increase the return on investment and the Council’s borrowing capacity for future schemes.

It considers the advantages and disadvantages of alternative approaches to securing the design and construction of the homes and highlights the benefit of taking a more agile approach to funding this type of development in contrast to the allocation of an annual budget.

The Growth Overview and Scrutiny Committee considered and supported the recommendations included in the report at its meeting on 13th December 2017 and for submission for Cabinet approval.

RECOMMENDATION It is recommended that: 1. The 10 potential development sites detailed in the report be approved for further evaluation and included in the Phase 3 - Housing Development Programme. 2. The potential benefits of delivering all of the development programme in partnership with Gravitas Ltd (a company wholly owned by South Kesteven District Council) be considered as part of the procurement options. 3. Cabinet approves the adoption of a more agile approach to funding the development of housing (including essential site acquisition) by the creation of a development reserve with the ability to fund changes to the programme over time as part of the budget development process for 2018/19.

1. BACKGROUND TO REPORT

1.1Phase 2 of the Council’s housing programme will be completed in December 2017 delivering 27 new homes in Grantham (22) and Barrowby (5).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Housing Development ProgrammeReport 130 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. Housing Development ProgrammeThis decision
  2. Core Strategy Development Plan Document - Amendment to Affordable Housing Policy (H3)Agreed
  3. *Core Strategy Development Plan Document: Amendment to Affordable Housing Policy (H3)Agreed
  4. S07/0555/35 – primary care centre, extra care housing and residential development, springfield park, springfield road, granthamApproved
  5. Local Development Framework: Economic & Housing DPDApproved
  6. Local Development Framework: Housing and Economic Development PlanDecided

More from South Kesteven Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 LGR - Response to Decision - Legal AdviceDecision Cabinet resolved to: A. Instruct the Director of Law and Governance to take all necessary and appropriate pr... Decided Open
21 Jul 2026 Warmer Homes GrantDecision That Cabinet: 1. Approve the acceptance of the additional £999k Warm Homes Social Housing Fund grant which h... Approved Open
21 Jul 2026 Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th... Approved Open
21 Jul 2026 2026/2027 Pay AwardDecision That Cabinet: Approved an additional budget of: · £214,000 from the Local Priorities Reserve to fund the Gen... Approved Open
21 Jul 2026 Refuse and Recycling Operational Policy UpdateDecision That Cabinet: Review and approve the updated Refuse and Recycling Operational Policy. Reasons for the decisi... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies