Application Ref: S17/1622 Description: Variation of S.106 Agreement in relation to planning permission S02/1169 to allow financial contribution in lieu of off-site highway works to the A1 southbound slip road junction with Harlaxton Road Location: A1 southbound junction/Harlaxton Road, Grantham

Approved Planning 1 paper

Planning Committee approved this item on Tuesday 29 May 2018. Below is the council's own wording, with the papers it was decided on.

Item5c

Resolved

To approve the revision of the Section 106 Agreement As the application was part-heard and Councillors Judy Smith, Stevens, Brenda Sumner and Trollope-Bellew had not been present when it had been considered previously, they did not participate in discussion or vote on the application. Noting: · Comments from Lincolnshire County Council Highways and SUDS Support · Comments from Highways England · The outcome of dialogue between the relevant County Councillor and Lincolnshire County Councils Highways team, together with further comment from Highways England · 1 representations received as a result of public consultation · Provisions within the National Planning Policy Framework and the South Kesteven Core Strategy and supplementary planning documents · Comments made by members at the meeting · Comments made by members on 6 March 2018 when the application was first considered It was proposed, seconded and agreed that the application be approved for the reasons set out in the case officer’s report and subject to the signing of a Section 106 Deed of Variation. Provided that if the Deed of Variation has not been signed within 6 weeks of the date of this meeting and the Service Manager for Development Management and Implementation, after consultation with the Chairman or Vice Chairman of the Development Management Committee, considers there are no extenuating circumstances which would justify an extension (or further extension) of time, the Service Manager for Development Management and Implementation be authorised to refuse the application.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Planning Committee

KJC2 S17/1622 Target Decision Date:25th October 2017 Committee Date:29th May 2018

Applicant [name removed] East Midlands Unit 2 The Osiers Business Park Laversall Way Leicester Agent [name removed] Services Ltd Country Works 7 Gateshead Close Sunderland Road Sandy Proposal Variation of S106 Agreement in relation to Planning Permission S02/1169 to allow financial contribution in lieu of off-site highway works to the A1 Southbound slip road junction with Harlaxton Road Location A1 Southbound Junction /Harlaxton Road Grantham Application Type Modify or discharge planning obligation Parish(es) Grantham

Reason for Referral to The application relates to a variation of an existing S106 legal Committee agreement Recommendation That the application is:- Approved conditionally Report Author Kevin Cartwright - Principal Planning Officer 01476 406080 Ext: 6390 [email protected] Report Reviewed By Justin Johnson - Planning Operations Lead 01476 406080 Ext: 6392 [email protected]

Key issues

Whether or not the highway junction improvement works are required

Technical Documents Submitted with the Application

Transport Assessment Report on Transport Assessment Reassessment of S106 agreement

35 36 1.0 Introduction

1.1Members may recall that the application was deferred from the Development Management meeting on 6th March 2018 to enable further consultation with Lincolnshire County Council highways to ascertain if any highway improvements, which fulfilled the statutory tests, were required as a consequence of the development. This was to be led by Cllr Adam Stokes in his capacity as District and County Councillor for the area in the vicinity of the junction. The original report is reproduced in full below (Appendix 1)

1.2This has taken place and the comments of Lincolnshire County Council highway authority referred Cllr Stokes to Highways England as the part of the highway network most affected by the junction improvements works not taking place would be the A1 slip road which is under the jurisdiction of Highways England, not Lincolnshire County Council.

1.3The comments of Highways England are summarised below:

1.3.1 “The information that has been submitted demonstrates that the junction improvements will not be required as the impact of the development is limited.

1.3.2 The wider mitigation of the Grantham Southern Relief Road should improve traffic around Grantham.”

2.0Conclusion

2.1It is considered that the above comments reiterate the conclusion of the previous committee report and the recommendation remains unchanged.

37 38 Appendix 1 Officer Report Ref: S17/1622 Original Committee Date 6 March 2018

KJC1 S17/1622 Target Decision Date:25th October 2017 Committee Date:6th March 2018

Applicant [name removed] East Midlands Unit 2 The Osiers Business Park Laversall Way Leicester Agent [name removed] Services Ltd Country Works 7 Gateshead Close Sunderland Road Sandy Proposal Variation of S106 Agreement in relation to Planning Permission S02/1169 to allow financial contribution in lieu of off-site highway works to the A1 Southbound slip road junction with Harlaxton Road Location A1 Southbound Junction /Harlaxton Road Grantham Application Type Modify or discharge planning obligation Parish(es)

Reason for Referral to The application relates to a variation of an existing S106 legal Committee agreement Recommendation That the application is:- Approved conditionally Report Author Kevin Cartwright - Principal Planning Officer 01476 406080 Ext: 6390 [email protected] Report Reviewed By Justin Johnson - Planning Operations Lead 01476 406080 Ext: 6392 [email protected]

Key issues

 Whether or not the highway junction improvement works are required

Technical Documents Submitted with the Application

 Transport Assessment  Report on Transport Assessment  Reassessment of S106 agreement

39 1.0 Description of Proposal

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Application Ref: S17/1622 Description: Variation of S.106 Agreement in relation to planning permission S02/1169 to allow financial contribution in lieu of off-site highway works to the A1 southbound slip road junction with Harlaxton Road Location: A1 southbound junction/Harlaxton Road, Grantham PDFReport 1.1 MB DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. Application Ref: S17/1622 Description: Variation of S.106 Agreement in relation to planning permission S02/1169 to allow financial contribution in lieu of off-site highway works to the A1 southbound slip road junction with Harlaxton Road Location: A1 southbound junction/Harlaxton Road, GranthamThis decision
  2. Application ref: S18/0937 Description: Reserved matters application for 174 dwellings and associated infrastructure pursuant to SK94/0125/12 Location: Elsea Park - Zone 9, Land east of A151, Raymond Mays Way, BourneRefused
  3. Application ref: S18/2003 Description: Erection of single storey side and rear extensions and detached garage Location: 21 Village Street, Frognall, Lincolnshire, PE6 8RSAgreed
  4. Application ref: S17/1900 Description: Residential development of up to 35 dwellings, associated estate roads, open space and Sustainable Drainage System (outline) Location: Old Langtoft Gravel Pit, land to the south of Stowe Road, LangtoftAgreed
  5. Application ref: S18/0937 Description: Reserved matters application for 174 dwellings and associated infrastructure pursuant to SK94/0125/12 Location: Elsea Park - Zone 9, Land east of A151, Raymond Mays Way, BourneRefused
  6. Application ref: S18/1752 Description: Erection of a 4-bedroom dwelling and garage Location: 23 Main Road, Dyke, PE10 0AFRefused

More from South Kesteven Planning Committee

All decisions
MeetingDecisionOutcome
3 Sep 2026 Application S26/0096Decision It was proposed, seconded and AGREED to authorise the Assistant Director – Planning & Growth to GRANT planni... Agreed Open
3 Sep 2026 Application S26/0354Decision It was proposed, seconded and AGREED to authorise the Assistant Director – Planning & Growth to GRANT planni... Agreed Open
3 Sep 2026 Application S25/1082Decision It was proposed, seconded and AGREED to authorise the Assistant Director – Planning to GRANT planning permis... Agreed Open
16 Apr 2026 Application S26/0363It was agreed that Officers would consult with Grantham Civic Society were the application approved and a note would ... Agreed Open
16 Apr 2026 Application S25/2342It was AGREED to extend the meeting until 18.00 The meeting adjourned at 16.52 and resumed at 17.01. Proposal: Outlin... Agreed Open