Application ref: S18/0093 Description: Construction of 49 dwellings, construction of new vehicular access - outline application with the matter of access included for consideration Location: Land east of Low Road, Barrowby

Agreed Planning 2 papers

Planning Committee agreed this item on Tuesday 13 November 2018. Below is the council's own wording, with the papers it was decided on.

Item39c

Resolved

To grant the application subject to conditions and completion of a Section 106 Agreement Noting comments made during the public speaking session by: Parish Council Councillor Tim Lees Applicant’s Agent Lynette Swinburne Together with: · No objection subject to conditions from Lincolnshire County Council Highways and SUDS Support · A request for a financial contribution from Lincolnshire County Council Education and Cultural Services · No objection from the National Grid · A request for a condition from SKDC’s Environmental Protection Services · No objection from Highways England · Comments made by Barrowby Parish Council · Comments and request for a condition from Heritage Lincolnshire · No request for contributions from NHS England · A request for a condition from Anglian Water Services · Comments from the Environment Agency · Comments from Lincolnshire Fire and Rescue Services · A representation from Persimmon Homes · 18 representations received as a result of public consultation · Provisions within the National Planning Policy Framework and the South Kesteven Core Strategy and supplementary planning documents · Site visit observations · Comments made by members at the meeting 15:55 – Councillors Dilks and Wood left the meeting and did not return. 16:02 – Councillors Exton and Kaberry-Brown left the meeting and did not return. 16:10 – As the meeting had been in progress for 3 hours, the Chairman asked for Members’ consent to continue. Members agreed. During debate Members referred to pieces of land that abutted the site and future connectivity as those other parcels of land were developed. The additional items paper issued on 9 November 2018 proposed two amended conditions to ensure connectivity. Some concern was expressed by Members as the trigger for the proposed connectivity conditions was “prior to the occupation of the twenty-fifth dwelling” . Consequently it was suggested that the conditions be re-worded to ensure that links would be built: 5. Notwithstanding the submitted Indicative Master Plan drawing number: LNBU 390793-03D, none of the dwellings hereby permitted shall be occupied until pedestrian, vehicle and bicycle connectivity is provided from the development site to the land immediately abutting the east of the site in accordance with details to have been submitted to and approved in writing by the Local Planning Authority. 6. Notwithstanding the submitted Indicative Master Plan drawing number: LNBU 390793-03D, none of the dwellings hereby permitted shall be occupied until pedestrian and bicycle connectivity is provided from the development site to Thorold Road to the north of the site in accordance with details to have been submitted to and approved in writing by the Local Planning Authority. It was proposed, seconded and agreed that the application be approved for the reasons set out in the case officer’s report and subject to the conditions set out on pages 44 to 46 of the case officer’s report subject to the amendments noted above, and subject to prior completion of a Section 106 agreement to secure the requirements specified in paragraph 10. Provided that if the Section 106 Agreement has not been completed within 6 weeks of the date of this meeting and the Head of Development Management, ... view the full minutes text for item 39c
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Planning Committee

DEVELOPMENT MANAGEMENT COMMITTEE

13 November 2018

Additional Information Report

S18/0093

Proposal: Construction of 49 Dwellings, construction of new vehicular access – Outline Application with the matter of access included for consideration

Location: Land East of Low Road Barrowby

Additional comments received not in the report

Persimmon Homes

Persimmon Homes who have an interest on the land adjacent to the site to the east have requested an amendment to condition 5 to ensure that there is no ransom strip to prevent connectivity between the site and their land that may be the subject of a future planning application.

Barrowby Parish Council

Have confirmed that they have no immediate plans to upgrade the adjacent playing field and request the flexibility that open space provision is either on site or in the form of a commuted sum for off-site improvements.

Officer Comments

As the matter of access is for consideration as part of this application it is considered appropriate to ensure that every endeavour is made to ensure good connectivity to the adjacent land that may be the subject of a future planning application.

Accordingly it is suggested that both condition 5 and 6 are amended.

It is not unusual to include within a S106 legal agreement to have either on site equipped play provision or an equivalent off-site contribution.

As an update to Section 7.5 Open Space and Section 10 Developer Contributions of the Officer Report the open space requirements for the site would be:

On site open space provision of 2350m2 of which 350m2 would be equipped children’s play area or an off-site contribution of £32,810 towards new provision or enhancement of facilities at Barrowby Playing Fields.

Plus an additional maintenance contribution or an appropriate management company would be required for on-site provision. These requirements would form the S106 agreement along with the for affordable housing, education and fire hydrant provision.

Additional Information Report (Version 1) Issue date – 9 November 2018 Alterations/Additional Conditions

That Condition 5 amended to the following:

Notwithstanding the submitted Indicative Master Plan drawing number. LNBU 390793003D, pedestrian, vehicle and bicycle connectivity must be provided to and abut land to the east of the site prior to the occupation of the 25th dwelling, in accordance with details to have been submitted to and approved in writing by the Local Planning Authority.

That Condition 6 amended to the following:

Notwithstanding the submitted Indicative Master Plan drawing number. LNBU 390793003D, pedestrian, and bicycle connectivity must be provided to and abut Thorold Road to the north of the site prior to the occupation of the 25th dwelling, in accordance with details to have been submitted to and approved in writing by the Local Planning Authority.

Changes to Recommendation

No change to recommendation.

Additional Information Report (Version 1) Issue date – 9 November 2018

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
3: KJC1: S18-0093: AIReport 85 KB DownloadRead as text
PDF
Application ref: S18/0093 Description: Construction of 49 dwellings, construction of new vehicular access: outline application with the matter of access included for consideration Location: Land east of Low Road, BarrowbyReport 1.1 MB Download

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. Application ref: S18/0093 Description: Construction of 49 dwellings, construction of new vehicular access - outline application with the matter of access included for consideration Location: Land east of Low Road, BarrowbyThis decision
  2. Application ref: S18/0937 Description: Reserved matters application for 174 dwellings and associated infrastructure pursuant to SK94/0125/12 Location: Elsea Park - Zone 9, Land east of A151, Raymond Mays Way, BourneRefused
  3. Application ref: S18/2003 Description: Erection of single storey side and rear extensions and detached garage Location: 21 Village Street, Frognall, Lincolnshire, PE6 8RSAgreed
  4. Application ref: S17/1900 Description: Residential development of up to 35 dwellings, associated estate roads, open space and Sustainable Drainage System (outline) Location: Old Langtoft Gravel Pit, land to the south of Stowe Road, LangtoftAgreed
  5. Application ref: S18/0937 Description: Reserved matters application for 174 dwellings and associated infrastructure pursuant to SK94/0125/12 Location: Elsea Park - Zone 9, Land east of A151, Raymond Mays Way, BourneRefused
  6. Application ref: S18/1752 Description: Erection of a 4-bedroom dwelling and garage Location: 23 Main Road, Dyke, PE10 0AFRefused

More from South Kesteven Planning Committee

All decisions
MeetingDecisionOutcome
3 Sep 2026 Application S26/0096Decision It was proposed, seconded and AGREED to authorise the Assistant Director – Planning & Growth to GRANT planni... Agreed Open
3 Sep 2026 Application S26/0354Decision It was proposed, seconded and AGREED to authorise the Assistant Director – Planning & Growth to GRANT planni... Agreed Open
3 Sep 2026 Application S25/1082Decision It was proposed, seconded and AGREED to authorise the Assistant Director – Planning to GRANT planning permis... Agreed Open
16 Apr 2026 Application S26/0363It was agreed that Officers would consult with Grantham Civic Society were the application approved and a note would ... Agreed Open
16 Apr 2026 Application S25/2342It was AGREED to extend the meeting until 18.00 The meeting adjourned at 16.52 and resumed at 17.01. Proposal: Outlin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies