Voids Process and Performance - Housing Technical Services

Approved Executive 2 papers

Cabinet approved this item on Tuesday 12 January 2021. Below is the council's own wording, with the papers it was decided on.

Item46

Resolved

Cabinet notes the content of the report. 2. Cabinet approves Option 2 as providing the most efficient operational way forward to implement changes to the process and management of voids at this time. 3. Cabinet requests that the Rural and Communities Overview and Scrutiny Committee consider at its next scheduled meeting in February 2021 proposals for a new suite of Key Performance Indicators relating to the effective monitoring of void property management performance, and thereafter to receive updated performance data, and progress on further actions being taken to improve overall void management performance. 4. Cabinet receives a following up report within six months relating to the implementation of the Option 2 proposals. 5. Cabinet receives a comprehensive report covering the full review of the revised void management and process changes, to ensure the objectives and anticipated benefits have been achieved, within the next 12 months. 6. That Officers update Cabinet on the progress made to introduction imprest van stocks through a preferred supplier, and the impacts anticipated in the context of the current stores and stock arrangements be subject to a further report to Cabinet. Considerations/reasons for decision · Report from the Cabinet Member for Housing and Planning updating Members on the progress towards an efficient voids process and to begin considerations of appropriate performance measures. · The need for a comprehensive review of the Council’s management of void properties to put an efficient and effective process in place. · The introduction and deployment of a Northgate Integrated Housing Management System in summer 2021. · The introduction of new streamlined void work processes and targets. · The introduction of Key Performance Indicator data to be reviewed regularly through the Rural and Communities Overview and Scrutiny Committee. · Changes to the structure of the Technical Services void team. · Consultation undertaken within the Technical Service and Housing Management Services, amendments made based on feedback and good practice principles. Other Options considered 1) Leave as current. This was not a viable option and entailed carrying on the existing processes. 2) Investigate the potential for all void works to be delivered by an external contractor/s through a price per void contract.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Cabinet

Cabinet 12 January 2021

Report of: Councillor Robert Reid Cabinet Member for Housing and Planning

Void Process and Performance – Housing Technical Services This report seeks to update members on the progress towards an efficient voids process and to begin the consideration of appropriate performance measures.

Report Author

Paul Crow, Interim Head of Technical Services [phone removed] [email protected]

Corporate Priority: Decision type: Wards:

Growth Key All Wards

Reviewed by: Chris Stratford, Interim Assistant Director for Housing 30 December 2020

Approved by: Karen Bradford, Chief Executive 18 December 2020

Signed off by: Councillor Robert Reid, Cabinet Member for Housing 22 December 2020 and Planning

Recommendation (s) to the decision maker (s)

1. It is recommended that Cabinet notes the contents of the report. 2. Approves Option 2 as providing the most efficient operational way forward to implementing changes to the process and management of voids at this time. 3. Requests the Rural and Communities OSC to consider, at its scheduled meeting in February 2021 proposals for a new suite of KPIs (Key Performance Indicators) relating to the effective monitoring of void property management performance, and thereafter to receive updated performance data, and progress on further actions being taken to improve overall void management performance. 4. Receives a follow up report within six months relating to the implementation of the option 2 proposals. 5. Receives a comprehensive report covering the full review of the revised void management and process changes, to ensure the objectives and anticipated benefits have been achieved, within the next 12 months. 6. That Officers update Cabinet on the progress made to introduce imprest van stocks through a preferred supplier, and the impacts anticipated in the context of the current stores and stock arrangements be subject to a further report to Cabinet. 1 The Background to the Report 1.1 The Council manages approximately 5,950 rented homes of which at present approximately 5.68% (338 properties) become vacant each year. These vacant properties are known as voids.

1.2A review of void properties, including benchmarking against comparable authorities suggests that the Council’s management of voids requires a comprehensive review. It is further recognised that to move from the current arrangements to a fully improved position will not be possible to achieve in one move.

1.3There are a complex set of processes which need to be fundamentally revised to reach ‘good practice’ and this involves reviewing not only the process, but structures, and working practices between teams not currently in place. This report identifies changes that can be made now or relatively quickly to begin the journey to improvement, but also highlights those other operational and process management issues which will be subject to further work and engagement with Members through further reports in the future. At the end of the process improvements it is intended to produce a new voids policy statement for Cabinet to consider and approve.

1.4It is vital when dealing with void properties that the management is efficient and effective in order to:

• Reduce turnaround times to a minimum so that potential tenants can access properties quickly; • Maximise rental income by reducing rental loss by minimising void periods through good management; • Ensure void works are of a high quality, whilst driving cost down wherever possible; and • Ensure void property improvements are necessary, timely, sustainable, environmentally friendly and cost effective.

1.5The Council’s objective must be to significantly improve void performance with appropriate changes to process and management in the short term, whilst aiming to achieve long term improvements year on year through other more significant changes. Overall, these objectives involve;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
SKDC Void StandardAppendix 1 174 KB Download
PDF
Voids Process and Performance: Housing Technical ServicesReport 657 KB DownloadRead as text

At this meeting

Whole meeting

More from South Kesteven Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 LGR - Response to Decision - Legal AdviceDecision Cabinet resolved to: A. Instruct the Director of Law and Governance to take all necessary and appropriate pr... Decided Open
21 Jul 2026 Warmer Homes GrantDecision That Cabinet: 1. Approve the acceptance of the additional £999k Warm Homes Social Housing Fund grant which h... Approved Open
21 Jul 2026 Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th... Approved Open
21 Jul 2026 2026/2027 Pay AwardDecision That Cabinet: Approved an additional budget of: · £214,000 from the Local Priorities Reserve to fund the Gen... Approved Open
21 Jul 2026 Refuse and Recycling Operational Policy UpdateDecision That Cabinet: Review and approve the updated Refuse and Recycling Operational Policy. Reasons for the decisi... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies