St. Martin's Park, Stamford - Additional Costs

Approved Executive 1 paper

Cabinet approved this item on Tuesday 7 February 2023. Below is the council's own wording, with the papers it was decided on.

Item85

Resolved

Decision That Cabinet: 1. Approves the additional costs from the demolition contract with GF Tomlinson of £52,249.11 along with £49,000 for ongoing project management support. 2. Approves a reserve movement of £100,000 from the Local Priorities Reserve to the Regeneration Reserve in order to provide funding for the costs outlined in resolution 1. 3. Approves the funding of these additional costs from the Council’s Regeneration Reserve, having approved recommendation 2. Alternative options considered and rejected The Council was contractually required to settle the final invoice with GF Tomlinson. It could have decided not to progress with external project management support, but the Council did not have in-house expertise to support the progression of such a complex project. Reason for decisions The Council was contractually required to pay GF Tomlinson the remainder of the contract sum as the works had been instructed and completed. The initial sum granted for £1.3 million had no contingency monies built into it for unforeseen works, such as asbestos removal. The Council did not have the internal knowledge or resources to internally project manage this complex infrastructure/construction scheme. The lack of knowledge and continuation of a project manager would be a risk to the Council. In the report to the Finance, Economic Development and Corporate Services Overview and Scrutiny Committee in September 2022 it was identified to the Committee at that time that the contract was overspent due to unforeseen works that were not included in the original contract Cabinet on 18 October 2022 approved an additional £192,630.23. The final account (after detailed scrutiny) showed a contract overspend requiring Cabinet to approve the sum of £52,249.11 to pay this final invoice and conclude the contract. Project Management support had been ongoing from Avison Young with weekly meetings with the Head of Corporate Projects, Policy and Performance yielding advice regarding the complex demolition works required to the site. Cabinet approved the sum of £49,000 to continue this support due to the complex nature of the site and the lack of internal resource within the Council that had knowledge and skillset in this area.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Cabinet

Purpose of report

To provide the Cabinet with an update that the demolition works at the former Cummins factory site are complete and seeking additional funding for the project overspend with the contract and additional monies for ongoing project management support from Avison Young.

Recommendations

1. Cabinet approves the additional costs totalling £101,249.11 from the demolition contract with GF Tomlinson of £52,249.11 and £49,000 for ongoing project management support. 2. Approve a reserve movement of £100,000 from the Local Priorities Reserve to the Regeneration Reserve in order to provide funding for the costs outlined at recommendation 1. 3. Upon the approval of recommendation 2, approve the funding of these additional costs from the Council’s Regeneration Reserve. Decision Information

Does the report contain any No exempt or confidential information not for publication?

What are the relevant corporate Growth and our economy priorities?

Which wards are impacted? Stamford St Marys

1. Implications

Taking into consideration implications relating to finance and procurement, legal and governance, risk and mitigation, health and safety, diversity and inclusion, safeguarding, staffing, community safety, mental health and wellbeing and the impact on the Council’s declaration of a climate change emergency, the following implications have been identified:

Finance and Procurement

1.1The demolition contract was awarded to GF Tomlinson via the SCAPE framework following approval at Council on 27 January 2022 and the contract sum of £1.303m was monitored monthly as part of the client meetings. There were additional items that were instructed to the contract that were unforeseen at the time of award, in accordance with the financial regulations and Constitution the additional budget from reserves requires approval from Cabinet so that the final account can be settled with GF Tomlinson.

The additional funding requirement of £101,249.11 can only be met from the Regeneration Reserve once a movement of £100,000 from the Local Priorities reserve has been undertaken. This is due to there being insufficient balance in the Regeneration Reserve to meet these unexpected costs. These additional costs are split between £52,249.11 for GF Tomlinson and £49,000 for Avison Young for project management fees. These costs are additional to the budget increase that was approved by Cabinet on 18 October 2022.

Richard Wyles, Chief Finance Officer

Legal and Governance

1.2The contract was monitored and was reviewed by the Finance, Economic Development and Corporate Services Overview and Scrutiny Committee on the 27th of September 2022, and it was outlined at that meeting that there would be an overspend. In accordance with the Constitution Cabinet is required to approve the use of specific reserves.

1.3Project management support via an external consultant provides a robust mechanism for cost management and governance.

Mandy Braithwaite, Legal Executive

Risk and Mitigation

Construction risks were reviewed monthly as part of the project and mitigation identified where possible, but the additional items were unforeseen such as additional asbestos removal and drainage works which if not resolved immediately by the contractor would have had an impact on programme.

Health and Safety

1.4Construction Health and Safety was reviewed, and spot check visits conducted by the contractors Health and Safety advisors. The site has now been handed back to the Council as the demolition works have concluded and the site will be monitored by officers.

2. Background to the Report

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
St. Martin's Park, Stamford: Additional CostsReport 212 KB DownloadRead as text

More from South Kesteven Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 LGR - Response to Decision - Legal AdviceDecision Cabinet resolved to: A. Instruct the Director of Law and Governance to take all necessary and appropriate pr... Decided Open
21 Jul 2026 Warmer Homes GrantDecision That Cabinet: 1. Approve the acceptance of the additional £999k Warm Homes Social Housing Fund grant which h... Approved Open
21 Jul 2026 Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th... Approved Open
21 Jul 2026 2026/2027 Pay AwardDecision That Cabinet: Approved an additional budget of: · £214,000 from the Local Priorities Reserve to fund the Gen... Approved Open
21 Jul 2026 Refuse and Recycling Operational Policy UpdateDecision That Cabinet: Review and approve the updated Refuse and Recycling Operational Policy. Reasons for the decisi... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies