South Kesteven District Council
Cabinet, Tuesday 30 May 2023 at 2.00pm

Local Development Scheme for the Local Plan - Revised Timetable

Approved Executive 3 papers

Cabinet approved this item on Tuesday 30 May 2023. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

Decision That Cabinet approves the proposals for the revised Local Development Scheme 2023 - 2026, as attached at Appendix A of the report. Alternative options considered and rejected The alternative of not reviewing the Local Development Scheme was discounted. Failing to keep the Local Development Scheme up to date would contravene the statutory requirements of the Planning and Compulsory Planning Act 2004 (as amended by the Localism Act 2011) and Town and Country Planning (Local Planning) (England) Regulations 12. Reasons for decision The reason for the decision was to ensure the Council was providing an up-to- date position and an accurate timeline for the production of development plan documents. This would ensure the Council was acting in accordance with the requirements of the Planning and Compulsory Purchase Act 2004 (as amended). Maintaining an up to date Local Development Scheme would ensure a transparent process. This was important because the local community and others with an interest in the district would be kept aware of development plan production and stages of consultation. Supporting the continuity of the planning function in South Kesteven would aid the recovery of the local economy and the economic resilience of the District by providing greater certainty and confidence for future investment and development. In December 2022 the government published a consultation on amendments to the National Planning Policy Framework (NPPF). A new framework was awaited, which would have implications for the Local Plan. Changes were proposed to the timetable of the Local Plan to consider the implications of delaying the consultation on the draft Local Plan, resulting in an overall delay of nine months. This enabled the Council to prepare a Local Plan that was in accordance with National Policy. Consultation on the Draft Local Plan was now expected in Winter 2023. All key stakeholders, including District Councillors, and Town and Parish Councils would be notified of the revised timetable. The following points were raised during debate: · Many other Councils have put a hold on their Local Plan, therefore this approach was one of common sense. · The report identified a number of risks which could affect the work programme and timetable, that could be addressed through robust planning. These risks included: o Changes in legislation or the National Planning Policy o Higher than expected response to consultation o Covid-19 restrictions or similar o Planning Inspectorate unable to meet the timetable o Failure to comply with Duty to Cooperate o Plan being found unsound o Legal challenge to the Local Plan o Reduced number of officers and knowledge within the team because of staff illness/turnover o Financial resources o Failure of external consultants · Officers involved in compiling the report were praised for the quality of the risk assessments contained within the report. · It was confirmed that there was no risk of the Council breaching any statutory obligations as a result of this decision. · There was no intention to indefinitely ... view the full minutes text for item 6.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Cabinet

Purpose of report

To seek approval to a revision to the timetable associated with the Local Development Scheme (LDS).

Recommendation

It is recommended Cabinet: 1. Approves the proposals for the revised Local Development Scheme 2023 - 2026 (at Appendix A). Decision Information

Is this a Key Decision? Yes

Does the report contain any No exempt or confidential information not for publication? What are the relevant corporate Housing that meets the needs of all residents priorities?

Which wards are impacted? All

1. Implications

1.1Taking into consideration implications relating to finance and procurement, legal and governance, risk and mitigation, health and safety, diversity and inclusion, staffing, community safety, mental health and wellbeing and the impact on the Council’s declaration of a climate change emergency, the following implications have been identified:

Finance and Procurement

1.2There are no financial implications associated with this report as it relates to the revision of the timetable associated with the Local Development Scheme (LDS). The cost of undertaking the Local Plan is included within the approved budget for the current financial year.

Completed by: Alison Hall-Wright, Assistant Director of Finance

Legal and Governance

1.3The preparation of a Local development Scheme and Local Plan are statutory requirements of the Planning and Compulsory Planning Act 2004 (as amended by the Localism Act 2011) and Town and Country Planning (Local Planning) (England) Regulations 12. There is a need to ensure the Local Plan is up to date through a review. Failure to have an up-to-date Local Plan in place, limits the Council’s ability to influence the quantum, location and quality of development in its area. The Government have made clear they expect Council’s to have a Local Plan in place.

1.4The Council must publicise its intended timetable for producing the Local Plan. This information is contained in the proposed Local Development Scheme which authorities should publish on their website and must be kept up to date. The Council has a legal duty to ensure that the Local Development Scheme is kept up to date.

Completed by Mandy Braithwaite, Legal Executive Risk and Mitigation

1.5Publishing a Local Development Scheme and keeping it up to date is a regulatory requirement. The Council currently has a Local Development Scheme in place, but an update is required due to a timetable delay which has triggered a review of the Local Development Scheme. The delay is due to proposed amendments to the National Planning Policy Framework (NPPF) which are expected to be published by the Government ‘in due course’. Local Plans must be in conformity with the NPPF and the Council has consequently delayed publication of the Draft Local Plan to consider the proposed changes through the Local Plan Review.

Completed by Richard Wyles, Chief Finance Officer

Health and Safety

1.6The production of a Local Development Scheme has no identified impact on health and safety.

Diversity and Inclusion

1.7The planning process seeks to meet the needs of our diverse community. The emerging Local Plan will be supported by evidence-based reports such as a Local Housing Needs Assessment; Gypsy & Traveller Accommodation Assessment; and Employment Land Review which will identify the accommodation and employment needs of our community up to 2041. The emerging Local Plan seeks to meet the need by identifying suitable land allocations. The planning process requires developers to meet all housing needs, providing appropriate type and sized dwellings to meet the needs of current and future households.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Local Development Scheme 2023-2026_Appendix A 350 KB Download
PDF
Stages of Local Plan Production_Appendix B 138 KB Download
PDF
Local Development Scheme for the Local Plan: Revised TimetableReport 233 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. Local Development Scheme for the Local Plan - Revised TimetableThis decision
  2. Local Development SchemeApproved
  3. Local Development Scheme (2025 - 2028)Approved
  4. Local Development Scheme (2024 - 2027)Approved
  5. Local Development Scheme for the Local PlanApproved
  6. *A Local Plan for South Kesteven, evidence base and Local Development Scheme (timetable)Approved

More from South Kesteven Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 LGR - Response to Decision - Legal AdviceDecision Cabinet resolved to: A. Instruct the Director of Law and Governance to take all necessary and appropriate pr... Decided Open
21 Jul 2026 Warmer Homes GrantDecision That Cabinet: 1. Approve the acceptance of the additional £999k Warm Homes Social Housing Fund grant which h... Approved Open
21 Jul 2026 Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th... Approved Open
21 Jul 2026 2026/2027 Pay AwardDecision That Cabinet: Approved an additional budget of: · £214,000 from the Local Priorities Reserve to fund the Gen... Approved Open
21 Jul 2026 Refuse and Recycling Operational Policy UpdateDecision That Cabinet: Review and approve the updated Refuse and Recycling Operational Policy. Reasons for the decisi... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies