AGREED to authorise the Assistant Director of Planning to GRANT planning permission, subject to conditions and the completion of a Section 106 Agreement. Time Limit for Commencement 1 The development hereby permitted shall be commenced before the expiration of three years from the date of this permission. Reason: In order that the development is commenced in a timely manner, as set out in Section 91 of the Town and Country Planning Act 1990 (as amended). Approved Plans 2 The development hereby permitted shall be carried out in accordance with planning application form, and with the following list of approved plans: i. The Location Plan, received on 27 April 2023 ii. Drawing 23.006PLPL-01-3A ‘Existing and Proposed Elevations’, received on 19 June 2023 iii. Drawing 23.006PL01-2A 'Proposed Plans', received on 14th August 2023. iv. Design/Access/Planning Statement, received on 27 April 2023 Unless otherwise required by another condition of ... view the full minutes text for item 34.
Word for word from the decision South Kesteven published for this meeting.Source: moderngov.southkesteven.gov.uk
This report sets out additional information in relation to planning applications for consideration at the Planning Committee on 24th August 2023 that was received after the Agenda was published. S23/0836
Proposal: Conversion of office building to create 12(no.) self-contained flats. Site Address: 6-7 St Peter’s Hill Grantham, Lincolnshire
Additional Information Received
Following the publication of the Agenda Officers have been in discussions with the applicant in relation to the unit sizes in relation to “Technical housing standards -nationally described space standards”, a document produced by the Department for Levelling Up, Housing and Communities and the Ministry of Housing and Local Government (2015). The applicant has amended the schedule of accommodation to reflect these space standards by removing the 2 bed three persons flats and replacing them with either 1 bed two person or 1 bed one person flats. The accommodation now meets or exceeds these space standards. See Drawing 23.006PL01-2A received on 14th August 2023. Approved plan Condition 2 has been updated to reflect this amended plan below: Approved Plans 2. The development hereby permitted shall be carried out in accordance with planning application form, and with the following list of approved plans: i. The Location Plan, received on 27 April 2023 ii. Drawing 23.006PLPL-01-3A ‘Existing and Proposed Elevations’, received on 19 June 2023 iii. Drawing 23.006PL01-2A ‘Proposed Plans’, received on 14th August 2023. iv. Design/Access/Planning Statement, received on 27 April 2023 Unless otherwise required by another condition of this permission. Reason: To define the permission and for the avoidance of doubt. Environmental Protection The following comments have been received in relation to noise and asbestos. Noise I would recommend that the applicant provides a noise impact assessment to protect the residential amenity of the future occupiers. It must also be ensured that the sub-divisions of the building have a reasonable resistance to the transmission of airborne sound via walls, floors and stairs, as well as to impact sound via floors and stairs. The development must therefore comply with the requirements of Part E of Schedule 1 of the Building Regulations 2000 - Resistance to the passage of sound. Asbestos Due to the age of the building, I recommend that the applicant carries out an asbestos survey to protect the future users.
Response to Additional Comments It is not considered necessary for a noise report to be submitted in that there are no specific noise sources in close proximity that would be likely to result in an unacceptable impact on the amenity of the future occupiers. Additionally, as this is a town centre location it is accepted that the background noise levels would be higher than that of an isolated rural location. The request for appropriate noise insulation between the units is also noted. However, as this is a requirement of Building Regulations a planning condition requiring the submission of such information is not necessary as it would duplication of other legislation and ultra vires. The request for an asbestos survey is noted. The proposed development is for the conversion of the existing building and not demolition. Asbestos is managed by the Control of Asbestos Regulations 2012. As such it is considered appropriate to attach a note to applicant to any grant of planning permission in this regard. Suggested Note to Applicant: The applicant’s attention is drawn to the Control of Asbestos Regulations 2012, and the Approved Code of Practice should any asbestos be found on site.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.