CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
South Kesteven District Council
Cabinet, Monday 11 September 2023 at 2.00pm

Proposed Replacement Depot Turnpike Close Grantham

Refused Executive 5 papers

Cabinet refused this item on Monday 11 September 2023. Below is the council's own wording, with the papers it was decided on.

Item23

Resolved

Decision To recommend to Council: 1. That an allocation of £8million be included in the General Fund Capital Programme to provide funding to construct a new depot at Turnpike Close, Grantham. 2. A delegation of authority to the Council’s Section 151 Officer, in consultation with the Leader and Deputy Leader of the Council, to allocate further funding if required due to unforeseen costs during the project. 3. A request that the Finance and Economic Overview and Scrutiny Committee adds the replacement depot to its work programme and establishes a working group to receive regular updates and monitor the project. Alternative options considered and rejected Option 1 - To do nothing, not approve the budget for the construction of a new depot and remain at Alexandra Road. This had been discounted due to the growth of the District as identified in the Local Plan and the inability of the existing site to meet growth demands. Option 2 – Investigate whether Alexandra Road (under the ownership of South Kesteven District Council) could be re- modelled to reconfigure the site. Option 3 – Sell the Turnpike Close site and look for another site to purchase. Reasons for decision The site was chosen and purchased as the ideal situation for a replacement depot. The costs for the scheme were volatile but the building of the site was a priority due to potential changes in the Environment Act. The Council needed to find an alternative provision for delivering its statutory function of this service. The site at Alexandra Road was geographically constrained and therefore could not accommodate any further service growth to meet future operational needs as identified in the Local Plan. The welfare facilities did not meet modern standards for the Council’s workforce. A new facility would provide drying areas, new locker provisions as well as canteen and training facilities. The training room could be used by officers and Members providing a multipurpose space. The ability to maximise sustainable systems so that the operational cost of the facility was lower showed a progressive approach working towards a carbon reduction target of 30% by 2030 and zero carbon by 2050. The Leader of the Council and Cabinet Member for Property and Public Engagement highlighted several key points on the depot: · An options appraisal on the Alexandra Road site still needed to be undertaken. · The Lincolnshire County Council waste recycling centre must remain on the Alexandra Road site until at least April 2025 so as not to disrupt crucial services. · The priority of delivering a new depot was highlighted in the Corporate Plan when it was being drafted in 2020, under the priority ‘building a fit for purpose depot’. The current site was not fit for purpose and had no capacity for key areas such as welfare facilities and the workshop to expand into. · The Design team had worked on plans ... view the full minutes text for item 23.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Cabinet

Purpose of report

Cabinet is asked to consider the proposals and agree next steps to enable the development of a new depot at Turnpike Close in Grantham.

Recommendations

Cabinet is asked: 1. To recommend to Council that an allocation of £8m be included in the General Fund Capital Programme to provide funding to construct a new depot at Turnpike Close, Grantham. 2. To delegate authority to the Council’s s151 Officer, in consultation with the Leader and Deputy Leader of the Council, to allocate further funding if required due to unforeseen costs during the project. 3. To request that the Finance and Economic Overview and Scrutiny Committee adds the replacement depot to its work programme and establishes a working group to receive regular updates and monitor the project. Decision Information

Is this a Key Decision? Yes

Does the report contain any No exempt or confidential information not for publication?

What are the relevant corporate Clean and sustainable environment priorities?

Which wards are impacted? All wards

1. Implications

Taking into consideration implications relating to finance and procurement, legal and governance, risk and mitigation, health and safety, diversity and inclusion, safeguarding, staffing, community safety, mental health and wellbeing and the impact on the Council’s declaration of a climate change emergency, the following implications have been identified:

Finance and Procurement

1.1This proposal is a significant capital outlay for the Council and demonstrates the Council’s commitment to provide a new modern fit for purpose depot that will serve the District in the medium to long term. The combined cost for the capital is approximately £10m and the Council will be required to provide a minimum revenue provision (MRP) over a 50-year period which is the expected life of the asset. The MRP is calculated at £200k per annum (the actual calculation will be based on the final spend level) for 50 years and is a new budgeted cost the Council will incur once the asset becomes operational. Therefore, the Council’s Medium Term Financial Plan will be required to incorporate this new cost and therefore this will be a necessity to identify the financial headroom in the budget setting proposals.

1.2The suggested financial strategy will be to undertake internal borrowing as a short-term solution as this will enable the Council to avoid undertaking external borrowing and therefore not incurring Public Works Loan Board (PWLB) interest costs. Whilst this will not avoid incurring the annual MRP cost it will enable the Council to minimise the annual financial impact of the new depot scheme. Based on current interest rates of 5.34%, this would be a further £550k per annum for 50 years in addition to the annual MRP cost. It is expected there will be only a marginal change to the operational costs of the new depot when compared to the current location as the larger size of the depot will be offset by the energy efficiency initiatives that will be incorporated into the new depot design. 1.3 The financial strategy also underway is to generate capital receipts from the disposal of surplus assets and utilise those receipts to offset the amount of borrowing (internal and external) that will be necessary. The amount of receipts that will be available at the time of borrowing is not possible to anticipate at this time but will be kept under review.

1.4The proposed budget is based on accurate projected costs provided by external cost consultants. In the unlikely event that the projected costs exceed the proposed budget allocation, then the Council can utilise the reserves to respond to any cost volatility.

Completed by: Richard Wyles, Chief Finance Officer

Legal and Governance

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Site PlanAppendix 1 4.1 MB Download
PDF
Business Case: March 2021Appendix 2 2.6 MB Download
PDF
Proposed Site PlanAppendix 3 2.1 MB Download
PDF
Order of CostAppendix 4 727 KB Download
PDF
Proposed Replacement Depot Turnpike Close GranthamReport 382 KB DownloadRead as text

More from South Kesteven Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 LGR - Response to Decision - Legal AdviceDecision Cabinet resolved to: A. Instruct the Director of Law and Governance to take all necessary and appropriate pr... Decided Open
21 Jul 2026 Warmer Homes GrantDecision That Cabinet: 1. Approve the acceptance of the additional £999k Warm Homes Social Housing Fund grant which h... Approved Open
21 Jul 2026 Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th... Approved Open
21 Jul 2026 2026/2027 Pay AwardDecision That Cabinet: Approved an additional budget of: · £214,000 from the Local Priorities Reserve to fund the Gen... Approved Open
21 Jul 2026 Refuse and Recycling Operational Policy UpdateDecision That Cabinet: Review and approve the updated Refuse and Recycling Operational Policy. Reasons for the decisi... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies