Cabinet, Tuesday 24 September 2024 at 10.00am

South Kesteven Regulation 19 Pre-Submission Local Plan

Approved Executive 2 papers

Cabinet approved this item on Tuesday 24 September 2024. Below is the council's own wording, with the papers it was decided on.

Item41

Resolved

Decision Cabinet endorsed the preparation of the Regulation 19 Pre-Submission Local Plan in accordance with the approved Local Development Scheme (Contained as Option 1 within the report). Alternative options considered and rejected Other Options considered, and discounted, included: Option 2: Pause Local Plan preparation Option 2 assumed that the consultation National Planning Policy Framework (NPPF) would be finalised ‘as is’ requiring the Council to revise the Local Plan to take into account the new NPPF, as such the following steps would have been undertaken: • Pause preparation of the Regulation 19 Local Plan · Commence work on revising the Local Plan to take into account the revised NPPF, with the view of publishing a Regulation 18 Draft Local Plan, including additional sites to meet the increased housing need, as soon as possible after the NPPF was published, to meet the December 2026 Submission deadline. · Since the publication of the consultation version of the NPPF, work on evidence had temporarily paused until a decision was made as to how to proceed. As Option 2 paused plan preparation, evidence work would also continue to be paused until the NPPF was published. However, to take into account a revised NPPF with increased housing numbers and new national policy, it was anticipated that approximately five evidence-based documents would require review with unknown cost implications. · Officers had carried out a high-level assessment of the potential housing sites that had been submitted through the ‘call for sites’ process and believed that, in the event of a higher housing requirement as proposed in the consultation NPPF, the Council would not need to reopen the call for sites. · If, when the ‘new’ NPPF was published, it transpired that the Council could have proceeded using the current housing requirements and the deadline for submission to the Secretary of State was not extended beyond the June 2025 deadline, this option would have meant that the Council would not be able to submit its Local Plan for examination. The risks associated with this option are set out in the risk assessment contained within the report. Reasons for decision It was resolved to proceed with Regulation 19 Pre-Submission, pushing consultation to January 2025. It was important to note, that amending the consultation date to January remained in accordance with the Council’s published Local Development Scheme which scheduled consultation of the Pre-Submission Local Plan to commence in Winter 2024. Whilst this option was at risk, it was deemed that the Council would be in the best position to switch to either Option 1 Scenario a or b depending on the outcome of the NPPF, once published. Whilst Option 1 Scenario a would inevitably require review of a raft of evidence documents, the government had indicated that: “We recognise that these arrangements would require some local planning authorities to undertake unforeseen additional work and reopen engagement with communities. Therefore, the Government will provide direct ... view the full minutes text for item 41.
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Cabinet

Purpose of report

The purpose of the report is to explain the implications of the emerging National Planning Policy Framework on the South Kesteven Local Plan review and recommend that Cabinet endorses the continuing preparation of the Regulation 19 Pre-Submission Local Plan in accordance with the approved Local Development Scheme.

Recommendations

Cabinet is recommended to endorse the preparation of the Regulation 19 Pre-Submission Local Plan in accordance with the approved Local Development Scheme (Option 1).

Decision Information

Is this a Key Decision? No Does the report contain any exempt or confidential information not for No publication? What are the relevant corporate priorities? Connecting communities Sustainable South Kesteven Enabling economic opportunities Housing Effective council Which wards are impacted? (All Wards); 1. Implications

Taking into consideration implications relating to finance and procurement, legal and governance, risk and mitigation, health and safety, diversity and inclusion, safeguarding, staffing, community safety, mental health and wellbeing and the impact on the Council’s declaration of a climate change emergency, the following implications have been identified:

Finance and Procurement

1.1There are no financial implications arising directly from the report

Completed by: Paul Sutton Interim Head of Finance (Deputy 151)

Legal and Governance

1.2There are no governance concerns with this report, as the approved Local Development Scheme indicates completion of the Pre-submission Local Plan by Winter 2024/2025. If Option 1 within the report is endorsed, this deadline would be adhered to.

Completed by: James Welbourn, Democratic Services Manager and Deputy Monitoring Officer

Risk and Mitigation

1.3A table of risks is included at Appendix A which details anticipated risks of all options set out in the report. The risk of proceeding with the preferred option (Option 1) is the likely incurment of currently unknown costs due to the necessity to update evidence if higher housing numbers are imposed through the new NPPF. However, this is assessed against the risk of not proceeding with the preferred option which may result in the derailment of the Local Plan and the Council unable to meet the current government-imposed deadline for submission of the Local Plan to Secretary of State by January 2025.

1.4The preferred option (Option 1) enables the Council to stay on track in line with the current legal framework, and the approved Local Plan timetable as published through the Local Development Scheme. Option 1 also gives the Council the opportunity to flex to either scenario a or b (or any other scenario which may arise), once the NPPF is published, which is expected by the end of the year.

Completed by: Tracey Elliott, Governance & Risk Officer 2. Background to the Report

Current Local Plan Timetable

2.1South Kesteven District Council is preparing a Local Plan in accordance with the December 2023 National Planning Policy Framework, and the published Local Development Scheme which sets out the following timeline for plan production.

Key Milestones Regulation Timescale

Commencement of Completed: April 2020 document preparation Consultation on the Regulation 18 Completed: 12 October – scope of the Plan 23 November 2020 Consultation on Draft Regulation 18 Completed: 29 February – Local Plan 25 April 2024 Consultation on the Pre- Regulation 19 Winter 2024/2025 submission Local Plan Submission Regulation 22 Summer (June) 2025

Examination Regulation 24 Summer 2025 – Spring 2026 Inspector’s Report Regulation 25 Spring 2026

Adoption Regulation 26 Summer 2026

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
for South Kesteven Regulation 19 Pre-Submission Local PlanAppendix 1 83 KB Download
PDF
South Kesteven Regulation 19 Pre-Submission Local PlanReport 316 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. South Kesteven Regulation 19 Pre-Submission Local PlanThis decision
  2. South Kesteven Shopfront Design Guide ReviewNoted
  3. MHCLG Statutory Consultation on Proposals for Local Government Reorganisation in Greater Lincolnshire: Response by South Kesteven District CouncilApproved
  4. Climate Action Plan for South KestevenApproved
  5. Biodiversity Action Plan for South KestevenNoted
  6. South Kesteven Design Code Statutory ConsultationApproved

More from South Kesteven Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 LGR - Response to Decision - Legal AdviceDecision Cabinet resolved to: A. Instruct the Director of Law and Governance to take all necessary and appropriate pr... Decided Open
21 Jul 2026 Warmer Homes GrantDecision That Cabinet: 1. Approve the acceptance of the additional £999k Warm Homes Social Housing Fund grant which h... Approved Open
21 Jul 2026 Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th... Approved Open
21 Jul 2026 2026/2027 Pay AwardDecision That Cabinet: Approved an additional budget of: · £214,000 from the Local Priorities Reserve to fund the Gen... Approved Open
21 Jul 2026 Refuse and Recycling Operational Policy UpdateDecision That Cabinet: Review and approve the updated Refuse and Recycling Operational Policy. Reasons for the decisi... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies