South Kesteven District Council
Council, Thursday 16 July 2026 at 2.00pm

Warm Homes Social Housing Fund Grant

Approved Committee 1 paper

AI summarySouth Kesteven District Council recommended Cabinet accept a £999k Warm Homes Social Housing Fund grant and approved a £1.598m HRA budget rise with a £599k reserve transfer, subject to Cabinet accepting the grant. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedChanges were approved, conditional on Cabinet accepting the grant. [D]
Money£999k grant [D]Match: £999k. HRA Capital Programme increase: £1.598m. [1.1] [1.2]
What happens nextCabinet grant decision [2.1]Cabinet considers acceptance on 21 July 2026. [2.1]
Who it affects106 council properties [2.1]Energy efficiency works are planned during 2026/27. [2.1]

What was decided

Council recommended that Cabinet accept the additional £999k Warm Homes Social Housing Fund grant awarded by DESNZ. [D] Report P3

Council noted the grant’s attached match funding requirement. [D] Report P4

Subject to Cabinet accepting the grant, Council approved a £1.598m HRA Capital Programme increase and a £599k transfer from the HRA Priorities Reserve. [D] Report P5, 1.3

Why

The match is met with £599k from the HRA Priorities Reserve and £400k already in the HRA Capital Programme. [1.1] Report 1.1

The funding supports the target of EPC rating C across the housing stock by 2030. [3.1] Report 3.1

It enables energy efficiency works on 106 properties, including heat pumps, insulation, replacement windows and solar PV panels. [2.1] [P23] Report 2.1, P23

What happens next

Cabinet will consider accepting the grant on 21 July 2026. [2.1] Report 2.1

Once the grant is accepted, the Council can proceed with the proposed works during 2026/27. [5.1] [2.1] Report 5.1, 2.1

The grant must be spent by 31 March 2027. [2.1] Report 2.1

The money

  • £999k Additional grant awarded by DESNZ Report P1, P3
  • £1.598m Increase to the HRA Capital Programme Report 1.2, 2.5
  • £999k Required match funding Report 1.1, 2.4
  • £599k Transfer from the HRA Priorities Reserve for match funding Report 1.1, 2.4, 2.5
  • £400k Existing HRA Capital Programme budget used for match funding Report 1.1, 2.5, P26
  • £200k Budget transfer from the window and doors programme Report 2.4
  • £200k Budget transfer from the heating programme Report 2.4

Options considered

  • Chosen: Accept the grant and approve the related HRA budget changes. This supports EPC rating C across the housing stock by 2030 and enables the proposed works. Report P3, P5, 3.1, 5.1
  • Rejected: Do not approve the HRA budget increase and reserve transfer. This would not support achievement of EPC rating C across the housing stock by 2030. Report 4.1

Implications

  • Financial: The HRA Capital Programme for 2026/27 must increase by £1.598m to reflect the additional works. [1.2] Report 1.2
  • Financial: The £999k grant requires equal match funding, met from £599k of reserve funding and £400k already budgeted. [1.1] Report 1.1
  • Legal: Full Council approval is required because of the budget increase and is conditional on Cabinet accepting the grant. [1.3] Report 1.3
  • Climate: The grant funds energy efficiency and heat decarbonisation measures in Council owned properties. [1.4] Report 1.4
  • Climate: Works are intended to move properties rated D, E or F to EPC rating C. [2.2] Report 2.2
  • Risk: Retrofit surveys and energy modelling may identify alternative works at each property. [2.3] Report 2.3
  • Other: The investment will help reduce tenant running costs and address fuel poverty. [1.4] Report 1.4
  • Financial: The grant must be spent by 31 March 2027. [2.1] Report 2.1

Who and where

  • 106 Council housing properties Report 2.1, P23
  • Tenants in Council owned properties Report 1.4
  • Council housing stock targeted for EPC rating C Report 2.2, 3.1
  • All wards Report P6

Timeline

  • June 2026: The Council received confirmation that it had been awarded the grant. [2.1] Report 2.1
  • 21 July 2026: A report will go to Cabinet seeking approval to accept the grant. [2.1] Report 2.1
  • 2026/27: The additional energy efficiency works and capital programme increase apply. [1.2] [2.1] Report 1.2, 2.1
  • 31 March 2027: The grant must have been spent. [2.1] Report 2.1
  • 2030: The Council aims to achieve EPC rating C across its housing stock. [2.2] [3.1] Report 2.2, 3.1

Plain English for the jargon

  • WH-SHF: Warm Homes Social Housing Fund [P1]
  • DESNZ: Department for Energy Security and Net Zero [P1]
  • HRA: Housing Revenue Account [P1]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item21

Resolved

DECISION: That Council a) Recommend that Cabinet accept the additional £999k Warm Homes Social Housing Fund grant which has been awarded to the Council by the Department for Energy Security and Net Zero. b) Note there is a match funding requirement attached to the grant. c) Upon acceptance of the grant approve a budget increase to the HRA Capital Programme of £1.598m and approve the transfer of £599k from the HRA Priorities Reserve in order to comply with the match funding condition .
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Council, 4 pages

Purpose of report

To consider recommending to Cabinet the acceptance of the additional Warm Homes Social Housing Fund (WH-SHF) grant of £999k which the Council has been awarded by the Department for Energy Security and Net Zero (DESNZ), approve a budget increase of £1.598m to the Housing Revenue Account (HRA) Capital Programme and approve the transfer of £599k from the HRA Priorities Reserve in order to comply with the match funding condition.

Recommendations

Full Council is asked to:

1. Recommend that Cabinet accept the additional £999k Warm Homes Social Housing Fund grant which has been awarded to the Council by the Department for Energy Security and Net Zero.

2. Note there is a match funding requirement attached to the grant.

3. Upon acceptance of the grant approve a budget increase to the HRA Capital Programme of £1.598m and approve the transfer of £599k from the HRA Priorities Reserve in order to comply with the match funding condition. Decision Information

Does the report contain any exempt or No confidential information not for publication? What are the relevant corporate priorities? Sustainable South Kesteven Housing Effective council Which wards are impacted? (All Wards);

1. Implications

Taking into consideration implications relating to finance and procurement, legal and governance, risk and mitigation, health and safety, diversity and inclusion, safeguarding, staffing, community safety, mental health and wellbeing and the impact on the Council’s declaration of a climate change emergency, the following implications have been identified:

Finance and Procurement

1.1Following a grant application to DESNZ the Council has been successful in being awarded £999k which it is required to match fund to the same amount. The council’s element will be funded from a £599k transfer from the HRA Priorities Reserve and £400k already included in the HRA Capital Programme budget which meets the eligibility criteria.

1.2As a result, the capital programme for 2026/27 will need to be increased by £1.598m to reflect the cost of the additional works.

Completed by: David Scott – Assistant Director of finance and Deputy S151 Officer.

Legal and Governance

1.3Due to the level of proposed budgetary increase, Full Council are required to consider approving the expected increase to the HRA capital programme. This is subject to Cabinet accepting the grant funding.

Completed by: James Welbourn, Democratic Services Manager

Climate Change

1.4The allocation of additional funding via the Warm Homes: Social Housing Fund will allow for additional energy efficiency and heat decarbonisation measures to be installed in Council owned properties. Investment in these properties via grant funding and allocated HRA funding will also help to reduce running costs for tenants, address risk of fuel poverty and promote warm and efficient homes.

Completed by: Serena Brown, Sustainability and Climate Change Manager

2. Background to the Report

2.1The Council submitted a bid to Department for Energy Security and Net Zero (DESNZ) for additional grant from the Warm Homes Social Housing Fund of £999k to enable energy efficiency improvement works to be completed on an additional 106 properties in the Council’s Housing Stock during 2026/27. Confirmation was received in June 2026 that the Council has been awarded the grant which needs to be spent by 31 March 2027, a report will be presented to Cabinet on 21 July 2026 to seek approval to accept the grant.

2.2The planned energy efficiency improvement works will increase the EPC ratings on the properties included in the bid from a D, E or F to a C which will support the Council with achieving EPC rating of C by 2030 across the housing stock.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Warm Homes Social Housing Fund GrantReport 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. Warm Homes Social Housing Fund GrantThis decision
  2. Warmer Homes GrantApproved
  3. Contract Award for Warm Homes Social Housing Fund worksApproved

More from South Kesteven Council

All decisions
MeetingDecisionOutcome
16 Jul 2026 Annual Review of Overview and Scrutiny 2025/2026DECISION: That Full Council: Notes the Overview and Scrutiny Annual Report. Note: The meeting adjourned for a short b... Decided Open
21 May 2026 Election of ChairmanAGREED: To elect Councillor Anna Kelly as the Chairman of the Council for the 2026/2027 municipal year. The Chairman ... Agreed Open
21 May 2026 Election of Vice-ChairmanAGREED: To elect Councillor Pam Byrd as the Vice-Chairman of the Council for the 2026/2027 municipal year. The Vice-C... Agreed Open
21 May 2026 Programme of Meetings of Full Council, Cabinet and Committees for 2026/2027DECISION That Full Council approve the programme of Meetings of Full Council, Cabinet and Committees for 2026/2027 as... Approved Open
21 May 2026 Appointments to Committees and Panels of the Council and Appointment of Chairmen and Vice-ChairmenDECISION That Full Council: Note the changes in political proportionality of the Council and the consequent allocatio... Noted Open