Internal audit management report quarter one 2015/2016

Noted Finance 5 papers

Joint Audit and Governance Committee noted this item on Monday 6 July 2015. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

RESOLVED : to note the internal audit management report for the first quarter of 2015/16.
Word for word from the decision South Oxfordshire published for this meeting. Source: democratic.southoxon.gov.uk

Follow this further

Built from South Oxfordshire's papers

What the report saysPro

Report to Joint Audit and Governance Committee

Purpose of report

1. The purpose of this report is:

 to report on management issues within internal audit;

 to summarise the progress against the 2015/2016 audit plan up to 23 June 2015; and

 to summarise the priorities for quarter two 2015/2016.

Page 27 Agenda Item 7

2. The contact officer for this report is Adrianna Partridge, Audit Manager for South Oxfordshire District Council and Vale of White Horse District Council, telephone 01235 540389.

Strategic objectives

3. Managing our business effectively.

Background

4. The CIPFA Code of Practice for Internal Audit in Local Government in the UK 2006 states that the head of internal audit should prepare a risk-based audit plan, which should outline the assignments to be carried out and the broad resources required to deliver the plan.

5. The CIPFA Code also states that the audit committee should approve the annual internal audit plan and monitor progress against the plan. The SODC committee approved the 2015/2016 annual internal audit plan on 17 March 2015 and the VWHDC committee approved the 2015/2016 annual internal audit plan on 19 March 2015.

Management issues

6. There has been an auditor vacancy throughout quarter one 2015/2016. An interim auditor has now been appointed to assist in the back log of work, and Peter Crabbe commenced on 22 June. We have successfully appointed to the permanent position and we anticipate the new auditor will commence 6 July 2015.

7. Following the Crowmarsh fire, internal audit is now implementing a fully electronic approach to testing, documenting and recording evidence obtained as part of the planned audit fieldwork. The current planned audits which are trialling this electronic approach may result in some additional time being spent whilst auditors embed it into normal working practices.

Progress against the 2015/2016 audit plan

8. Progress against the approved audit plan has been calculated for the quarter and year to date and is summarised in appendix 1 attached.

9. Performance figures to date are as follows:

Target YTD Q1 Q2 Q3 Q4 15/16 15/16 15/16 15/16 Chargeable 74% 60% 60% N/A N/A N/A (identifiable client and/or specific IA deliverable) Non-Chargeable 8% 10% 10% N/A N/A N/A (corporate, not IA deliverable) Planned Lost 16% 16% 16% N/A N/A N/A (i.e. leave) Unplanned Lost 2% 14% 14% N/A N/A N/A (i.e. study, sickness)

Page 28 Agenda Item 7

10. As at 23 June 2015 the status of audit work against the 2015/2016 audit plan is as follows:

Planned

Strategic, operational and financial assurance work known and approved by the Audit and Governance Committee.

In progress

commence 2015/2016

Complete Planned

Draft

To PLANNED 27 0 0 4 23 Joint 27 0 0 4 23

Adhoc

Unplanned project work based on agreed terms of reference with the audit manager (i.e. implementation of new systems) and responsive work issued and agreed by the section 151 officer, members or senior management team (i.e. investigations).

In progress 2015/2016

commence Requested

Complete

Draft

To ADHOC 0 0 0 0 0 Joint 0 0 0 0 0 SODC 0 0 0 0 0 VWHDC 0 0 0 0 0

Follow up

Work undertaken to ensure that agreed recommendations have been implemented. The number of follow-up audits is a rolling number, all internal audit reports are followed up after six months unless the area is subject to an annual review. commence Requested

2015/2016 Complete

progress Draft

To In

FOLLOW-UP 12 6 0 0 6 SODC 6 3 0 0 3 VWHDC 6 3 0 0 3 Page 29 Agenda Item 7

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal audit management report quarter one 2015/2016Report 185 KB DownloadRead as text
PDF
Management report appendix 2 Audit Plan Schedule 2015-2016Appendix 134 KB Download
PDF
Manrpt App1A1Report 80 KB Download
PDF
Manrpt App1BReport 72 KB Download
PDF
Manrpt App1CReport 62 KB Download

At this meeting

Whole meeting

Who was there

8 of 18 attended
EA
External AuditorPublic, expected
CB
Charles BaileyCommittee Member, present
SB
Steve BishopOfficer, expected
KB
Kevin BulmerCo-Chair, apologies, sent representative
SC
Steven CorriganOfficer, expected
SH
Susan HarbourOfficer, expected
PH
Paul HarrisonSubstitute, present as substitute
DH
Dudley HoddinottCommittee Member, present
SH
Simon HowellChairman, present
WJ
William JacobsOfficer, expected
FK
Fiona KaluzaOfficer, expected
CP
Chris PalmerCommittee Member, present

All 18 on the meeting page

On this subject at South Oxfordshire

Search all
  1. Internal audit management report quarter one 2015/2016This decision
  2. Internal audit annual report 2025/2026Noted
  3. Internal Audit Report Q1 2026/27Decided
  4. Internal audit plan 2026/27Approved
  5. Internal audit update report Q3 2025/26Decided
  6. New Global Internal Audit Standards in the UK Public Sector & Updated Internal Audit CharterNoted

More from South Oxfordshire Joint Audit and Governance Committee

All decisions
MeetingDecisionOutcome
7 Jul 2026 Annual Review of Complaints 2025/26That the committee noted: (a) the formal complaints received in 2025-26 and the councils’ performance in responding t... Noted Open
7 Jul 2026 Statement of accounts 2025/26 updateThat the committee (a) Noted progress on completing the 2025/26 Statement of Accounts and on the external audit build... Noted Open
7 Jul 2026 Internal audit annual report 2025/2026That the committee considered and noted the annual internal audit opinion and report. Noted Open
7 Jul 2026 Internal Audit Report Q1 2026/27RESOLVED : That the committee reviewed the results of recent internal audit work and monitored progress of management... Decided Open
7 Jul 2026 Internal audit plan 2026/27RESOLVED : That the committee approved the internal audit plan 2026/27. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies