Resolved
RESOLVED : to note the internal audit management report for the second quarter of 2016/17.
Joint Audit and Governance Committee noted this item on Monday 26 September 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED : to note the internal audit management report for the second quarter of 2016/17.
1. The purpose of this report is:
to report on management issues within internal audit;
to summarise the progress against the 2016/2017 audit plan up to 12 September 2016; and
to summarise the priorities for quarter three 2016/2017.
Page 324 Agenda Item 13
2. The contact officer for this report is Adrianna Partridge, Assurance Manager for South Oxfordshire District Council and Vale of White Horse District Council, telephone 01235 422485.
Strategic objectives
3. Managing our business effectively.
4. The CIPFA Code of Practice for Internal Audit in Local Government in the UK 2006 states that the head of internal audit should prepare a risk-based audit plan, which should outline the assignments to be carried out and the broad resources required to deliver the plan.
5. The CIPFA Code also states that the audit committee should approve the annual internal audit plan and monitor progress against the plan. The joint committee approved the 2016/2017 annual internal audit plan on 21 March 2016.
Management issues
6. Within the 2016/2017 South and Vale internal audit plan, a flexible allocation has been made for 5 councils partnership (5CP) assurance work. Through discussion with external audit, the following 5CP reviews have been proposed:
IA reviews Control process review of the 5CP procurement process – currently in progress. An assurance review of the IT general control environment –proposed for after the initial S&V target operating model (TOM) for IT (Feb – March 2017). An assurance review of the data migration process to Integra – pre-live checks Feb 2017 and post-live review June 2017. An assurance review of the 5CP corporate governance arrangements and how they link/integrate to the councils’ own corporate governance arrangements – proposed Jan 2017. Oversight (and insurance input) of the asset transfer process – currently in progress.
7. IA and EA involvement in other work Oversight (and input when relevant) of Capita and Vinci’s policy and process mapping programmes of work, and copies of all system flowcharts and maps to be shared with internal audit and external audit. Assurance manager now involved in Capita and Vinci’s working groups.
8. External audit reviews A review of the contract terms – currently in progress. A review of the implementation of the contract (how the councils are working with the providers and monitoring performance/resolving issues). – proposed Dec 2016 – Feb 2017. A review of whether the savings being designated are in accordance with the terms of the contract – proposed Nov 2016 – Jan 2017. Page 325 Agenda Item 13
Progress against the 2016/2017 audit plan
9. Progress against the approved audit plan has been calculated for the quarter and year to date and is summarised in appendix 1 attached.
Performance figures to date are as follows:
Target YTD Q1 Q2 Q3 Q4 15/16 15/16 15/16 15/16 Chargeable 74% 74.5% 71.5% 77% - - (identifiable client and/or specific IA deliverable) Non-Chargeable 8% 6% 7% 5% - - (corporate, not IA deliverable) Planned Lost 16% 18% 20% 16% - - (i.e. leave) Unplanned Lost 2% 1.5% 1.5% 2% - - (i.e. study, sickness)
10. As at 12 September 2016 the status of audit work against the 2016/2017 audit plan is as follows:
Planned
Strategic, operational and financial assurance work known and approved by the audit and governance committee.
In progress
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal audit management report quarter two 2016/2017Report | 177 KB | DownloadRead as text |
PDF |
Mgt report App 2 Audit Plan ScheduleAppendix | 101 KB | Download |
PDF |
Mgt report App1 follow up auditsReport | 67 KB | Download |
PDF |
Mgt report App1 planned auditReport | 79 KB | Download |
PDF |
Mgt report App1 unplanned auditsReport | 69 KB | Download |
Follow Joint Audit and Governance Committee at South Oxfordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Jul 2026 | Annual Review of Complaints 2025/26That the committee noted: (a) the formal complaints received in 2025-26 and the councils’ performance in responding t... | Noted | Open |
| 7 Jul 2026 | Statement of accounts 2025/26 updateThat the committee (a) Noted progress on completing the 2025/26 Statement of Accounts and on the external audit build... | Noted | Open |
| 7 Jul 2026 | Internal audit annual report 2025/2026That the committee considered and noted the annual internal audit opinion and report. | Noted | Open |
| 7 Jul 2026 | Internal Audit Report Q1 2026/27RESOLVED : That the committee reviewed the results of recent internal audit work and monitored progress of management... | Decided | Open |
| 7 Jul 2026 | Internal audit plan 2026/27RESOLVED : That the committee approved the internal audit plan 2026/27. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.