Internal audit activity report quarter one 2017/18

Agreed Finance 2 papers

Joint Audit and Governance Committee agreed this item on Monday 3 July 2017. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

It was agreed that the co-chairmen should send a letter to Capita’s local government services director expressing the committee’s disapproval at the failure of Capita to send representatives, seeking assurances that this would not happen again and requesting detailed information on actions taken or to be taken to implement the audit recommendations. HR Recruitment (Second Report) 2015/16 The Committee was concerned that, with regard to high risk recommendations relating to pre-employment checks and service area recruitment procedure, there appeared to be no improvements post 1 October 2016. Payroll 2016/17 In response to a member’s question about the recent overpayments of allowances to Vale of White Horse Councillors, the committee was informed by officers that Capita had stated that this had been caused by a data migration issue. Given the considerable sums involved, the committee was concerned at Capita’s apparent failure to carry out the appropriate checks. It was agreed that the co-chairmen’s letter should seek assurance from Capita that there was a robust control environment in place to ensure that such errors would not happen again. With regard to Recommendation 9, approval of monthly data, the Acting Chief Executive reported that a deputy S151 officer would be recruited as soon as possible. Training and Development (Second Report) 2016/17 Members reiterated previously expressed concerns about the lack of information about the implementation of recommendations. Performance Management 2016/17 In response to members’ questions, officers confirmed that this was a council function and provided additional information regarding the management response to Recommendation 2. Environmental Protection 2016/17 In response to a member’s question about the reasons for the differences between South and Vale’s processes for issuing fixed penalty notices, the committee was advised that both councils were happy with their current procedures. The Acting Chief Executive reported that the delay in implementing some of the report’s recommendations were due to capacity issues arising from the head of service post remaining vacant. He stated that his priority was to work with councillors to develop a long-term management structure that addressed current capacity gaps at head of service level and elsewhere. Overdue recommendations Appendix 2 to the report summarised all overdue recommendations within each service area. The committee was advised that, in future, this appendix would identify which of the recommendations related to service areas managed by contractors and details of original and revised implementation dates. At its previous meeting, the committee had requested that, in future, this appendix should identify the high risk overdue recommendations. As it had not been possible to include this information this time, ... view the full minutes text for item 6.
Word for word from the decision South Oxfordshire published for this meeting. Source: democratic.southoxon.gov.uk

Follow this further

Built from South Oxfordshire's papers

What the report saysPro

Report to Joint Audit and Governance Committee

Purpose of report

1. The purpose of this report is to summarise the outcomes of recent internal audit activity at both councils for the committee to consider. The committee is asked to review the report and the main issues arising, and seek assurance that action will be/has been taken where necessary.

2 The contact officer for this report is Adrianna Partridge, Assurance Manager for South Oxfordshire District Council (SODC) and Vale of White Horse District Council (VWHDC), telephone 01235 422485.

Strategic Objectives

3. Running an efficient council.

Page 25 Background

4. Internal audit is an independent assurance function that primarily provides an objective opinion on the degree to which the internal control environment supports and promotes the achievements of the council’s objectives. It assists the councils by evaluating the adequacy of governance, risk management, controls and use of resources through its planned audit work, and recommending improvements where necessary. After each audit assignment, internal audit has a duty to report to management its findings on the control environment and risk exposure, and recommend changes for improvements where applicable. Managers are responsible for considering audit reports and taking the appropriate action to address control weaknesses.

5. Assurance ratings given by internal audit indicate the following:

Full assurance: There is a good system of internal control designed to meet the system objectives and the controls are being consistently applied.

Substantial assurance: There is a sound system of internal control designed to meet the system objectives and the controls are being applied.

Satisfactory assurance: There is basically a sound system of internal control although there are some minor weaknesses and/or there is evidence that the level of non- compliance may put some minor system objectives at risk.

Limited assurance: There are some weaknesses in the adequacy of the internal control system which put the system objectives at risk and/or the level of non-compliance puts some of the system objectives at risk.

Nil assurance: Control is weak leaving the system open to significant error or abuse and/or there is significant non-compliance with basic controls.

6. Each recommendation is given one of the following risk ratings:

High Risk: Fundamental control weakness for senior management action

Medium Risk: Other control weakness for local management action

Low Risk: Recommended best practice to improve overall control

2017/2018 Audit Reports

7. Since the last audit and governance committee meeting, the following audits and follow up reviews have been completed:

Completed Audits

Full Assurance: 1 Substantial Assurance: 2 Satisfactory Assurance: 4 Limited Assurance: 6 Nil Assurance: 0

Page 26 High Risk Recs

Low Risk Recs Medium Risk No. of Recs

No. Agreed

No. Agreed

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal audit activity report quarter one 2017/18Report 492 KB DownloadRead as text
PDF
JAGCIA Q1 1718 Appendix 2 Overdue Recs ReportAppendix 189 KB Download

At this meeting

Whole meeting

Who was there

7 of 14 attended
AB
Andrew BrittainPublic, in attendance
DG
David GuestPublic, in attendance
CB
Charles BaileyCommittee Member, present
KB
Kevin BulmerCo-Chair, present
AD
Andrew DownOfficer, in attendance
DH
Cllr Dudley HoddinottCommittee Member, present
SH
Simon HowellCo-Chair, present
WJ
William JacobsOfficer, in attendance
TN
Toby NewmanCommittee Member, apologies
CP
Chris PalmerCommittee Member, present
AP
Adrianna PartridgeOfficer, in attendance
RS
Ron SchrieberOfficer, in attendance

All 14 on the meeting page

On this subject at South Oxfordshire

Search all
  1. Internal audit activity report quarter one 2017/18This decision
  2. Internal audit annual report 2025/2026Noted
  3. Internal Audit Report Q1 2026/27Decided
  4. Internal audit plan 2026/27Approved
  5. Internal audit update report Q3 2025/26Decided
  6. New Global Internal Audit Standards in the UK Public Sector & Updated Internal Audit CharterNoted

More from South Oxfordshire Joint Audit and Governance Committee

All decisions
MeetingDecisionOutcome
7 Jul 2026 Annual Review of Complaints 2025/26That the committee noted: (a) the formal complaints received in 2025-26 and the councils’ performance in responding t... Noted Open
7 Jul 2026 Statement of accounts 2025/26 updateThat the committee (a) Noted progress on completing the 2025/26 Statement of Accounts and on the external audit build... Noted Open
7 Jul 2026 Internal audit annual report 2025/2026That the committee considered and noted the annual internal audit opinion and report. Noted Open
7 Jul 2026 Internal Audit Report Q1 2026/27RESOLVED : That the committee reviewed the results of recent internal audit work and monitored progress of management... Decided Open
7 Jul 2026 Internal audit plan 2026/27RESOLVED : That the committee approved the internal audit plan 2026/27. Approved Open