Approved Finance 1 paper

Joint Audit and Governance Committee approved this item on Monday 29 January 2018. Below is the council's own wording, with the papers it was decided on.

Item35

Resolved

to adopt as a correct record the minutes of the committee meeting held on 25 September 2017 and agree that the chairman signs them as such.
Word for word from the decision South Oxfordshire published for this meeting. Source: democratic.southoxon.gov.uk

Follow this further

Built from South Oxfordshire's papers

What the report saysPro

Report to Joint Audit and Governance Committee

Public Document Pack Agenda Item 2

Minutes

OF A MEETING OF THE

Joint Audit and Governance Committee HELD ON MONDAY 25 SEPTEMBER 2017 AT 6.30 PM MEETING ROOM 1, 135 EASTERN AVENUE, MILTON PARK, OX14 4SB Present Members: South Oxfordshire District Councillors: Charles Bailey, Kevin Bulmer, Toby Newman, and John Walsh Vale of White Horse District Councillors: Dudley Hoddinott, Simon Howell (Chairman), and Chris Palmer

Officers: Sandy Bayley, Steve Culliford, Yvonne Cutler-Greaves, William Jacobs, Adrianna Partridge, and Mark Stone

Also present: Rhona Bellis and Simon Hewings (Capita Accountancy), Andrew Brittain and David Guest (EY)

15 Apologies for absence

Vale of White Horse District Councillor Henry Spencer had sent his apologies for absence.

16 Minutes

RESOLVED: to adopt as a correct record the minutes of the committee meeting held on 3 July 2017 and agree that the chairman signs them as such.

17 Declarations of interest

None

18 Urgent business and chairman's announcements

The chairman accepted two exempt items of urgent business in order that they could be resolved quickly.

19 Public participation

None Page 5 1 Agenda Item 2

20 Risk management strategy

The committee considered the report of the head of corporate services, which proposed a joint risk management strategy to 2019. The strategy extended to all operations of the two councils.

The committee supported the strategy and noted that risk management monitoring reports would be submitted to the committee every six months, starting with January 2018.

RESOLVED: to approve the risk management strategy.

21 Internal audit activity report - second quarter 2017/18

The committee considered the interim audit manager’s report on internal audit activity during the second quarter, 2017/18. Five audits and three follow-up audits had been completed during the quarter. None of the five audits had received a limited assurance rating.

The committee noted the summary of overdue audit recommendations and that several recommendations related to a vacant post. The interim audit manager agreed to investigate this and update the schedule accordingly. If any overdue recommendations were to be written-off, the committee would be advised of these.

Further to the minutes of the last meeting, it was noted that letters had been sent to Capita as requested (minute 6 refers).

RESOLVED: to

(a) note the internal audit activity report for the second quarter of 2017/18; and

(b) request the interim audit manager to update the schedule of outstanding audit recommendations and advise the committee of any recommendation that had been written-off.

22 Internal audit management report - second quarter 2017/18

The committee considered the interim audit manager’s report on internal audit management during the second quarter, 2017/18.

The committee noted that the audit plan 2017/18 was on target for completion during the year. Once the new management structure had been put in place, the audit plan and procedures would be reviewed.

RESOLVED: to

(a) note the internal audit management report for the second quarter of 2017/18; and

(b) request the interim audit manager to send the internal audit report on the five councils’ partnership to all committee members in advance of the report being considered at the next committee meeting.

Page 6 2 Agenda Item 2

23 External auditor's audit results report 2016/17

The committee considered the external auditor’s audit results for 2016/17. Andrew Brittain and David Guest of EY presented the main highlights from the report. They confirmed that the audit would be completed by 30 September.

For both councils, a number of audit differences were highlighted to the councils, the majority being below the reporting threshold but with one exception. For the Vale of White Horse an adjustment was needed relating to Enterprise Zone business rates, without any change to the bottom line.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
MinutesMinutes 163 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 14 attended
AB
Andrew BrittainPublic, in attendance
MH
Malcolm HainesPublic, in attendance
CB
Charles BaileyCommittee Member, absent
SB
Sandy BayleyCouncil Staff, in attendance
KB
Kevin BulmerCo-Chair, present
DH
Cllr Dudley HoddinottCommittee Member, present
SH
Simon HowellCo-Chair, present
WJ
William JacobsOfficer, in attendance
TN
Toby NewmanCommittee Member, apologies, sent representative
CP
Chris PalmerCommittee Member, in attendance
RP
Richard PullenSubstitute, present as substitute
RS
Ron SchrieberOfficer, in attendance

All 14 on the meeting page

On this subject at South Oxfordshire

Search all
  1. MinutesThis decision
  2. Minutes of the last meetingAgreed
  3. Minutes of the previous meetingApproved
  4. Minutes of the previous meetingApproved
  5. Minutes of the previous meetingApproved
  6. Confidential MinutesApproved

More from South Oxfordshire Joint Audit and Governance Committee

All decisions
MeetingDecisionOutcome
7 Jul 2026 Annual Review of Complaints 2025/26That the committee noted: (a) the formal complaints received in 2025-26 and the councils’ performance in responding t... Noted Open
7 Jul 2026 Statement of accounts 2025/26 updateThat the committee (a) Noted progress on completing the 2025/26 Statement of Accounts and on the external audit build... Noted Open
7 Jul 2026 Internal audit annual report 2025/2026That the committee considered and noted the annual internal audit opinion and report. Noted Open
7 Jul 2026 Internal Audit Report Q1 2026/27RESOLVED : That the committee reviewed the results of recent internal audit work and monitored progress of management... Decided Open
7 Jul 2026 Internal audit plan 2026/27RESOLVED : That the committee approved the internal audit plan 2026/27. Approved Open