Internal audit activity report quarter four 2017/2018

Noted Finance 1 paper

Joint Audit and Governance Committee noted this item on Monday 26 March 2018. Below is the council's own wording, with the papers it was decided on.

Item57

Resolved

to 1. note the internal audit activity report for the fourth quarter of 2017/18; and 2. request Capita and the 5 Councils’ Partnership client representative to circulate the payroll KPIs for the last six months, a progress report and the rectification plan to committee members as soon as possible, so that members can give notice of questions prior to Capita's report back to the next meeting .
Word for word from the decision South Oxfordshire published for this meeting. Source: democratic.southoxon.gov.uk

Follow this further

Built from South Oxfordshire's papers

What the report saysPro

Report to Joint Audit and Governance Committee

Purpose of report

1. The purpose of this report is to summarise the outcomes of recent internal audit activity at both councils for the committee to consider. The committee is asked to review the report and the main issues arising, and seek assurance that action will be/has been taken where necessary.

2 The contact officer for this report is Sandy Bayley, Interim Audit Manager for South Oxfordshire District Council (SODC) and Vale of White Horse District Council (VWHDC), telephone 01235 422496.

Strategic Objectives

3. Delivery of an effective internal audit function will support the councils in meeting their strategic objectives.

Page 21 Agenda Item 8 Background

4. Internal audit is an independent assurance function that primarily provides an objective opinion on the degree to which the internal control environment supports and promotes the achievements of the council’s objectives. It assists the councils by evaluating the adequacy of governance, risk management, controls and use of resources through its planned audit work, and recommending improvements where necessary. After each audit assignment, internal audit has a duty to report to management its findings on the control environment and risk exposure, and recommend changes for improvements where applicable. Managers are responsible for considering audit reports and taking the appropriate action to address control weaknesses.

5. Assurance ratings given by internal audit indicate the following:

Full assurance: There is a good system of internal control designed to meet the system objectives and the controls are being consistently applied.

Substantial assurance: There is a sound system of internal control designed to meet the system objectives and the controls are being applied.

Satisfactory assurance: There is basically a sound system of internal control although there are some minor weaknesses and/or there is evidence that the level of non- compliance may put some minor system objectives at risk.

Limited assurance: There are some weaknesses in the adequacy of the internal control system which put the system objectives at risk and/or the level of non-compliance puts some of the system objectives at risk.

Nil assurance: Control is weak leaving the system open to significant error or abuse and/or there is significant non-compliance with basic controls.

6. Each recommendation is given one of the following risk ratings:

High Risk: Fundamental control weakness for senior management action

Medium Risk: Other control weakness for local management action

Low Risk: Recommended best practice to improve overall control

2017/2018 Audit Reports

7. As at 13 March 2018, since the last audit and governance committee meeting, the following audits and follow up reviews have been completed:

Completed Audits

Full Assurance: 0 Substantial Assurance: 0 Satisfactory Assurance: 2 Limited Assurance: 2 Nil Assurance: 0

Page 22 Agenda Item 8

High Risk Recs

Low Risk Recs Medium Risk No. of Recs

No. Agreed

No. Agreed

No. Agreed Recs Assurance Rating Joint Treasury Management Satisfactory 2 0 0 1 1 1 1 17/18 Payroll 17/18 Limited 14 6 6 5 5 3 3 Capital Accounting & Limited 5 1 1 2 2 2 2 Management 17/18 Sundry Debtors 17/18 Satisfactory 5 0 0 2 2 3 3 SODC None VWHDC None

Follow Up Reviews Implemented

Implemented

Implemented No. of Recs

applicable No longer Ongoing Initial Partly

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal audit activity report quarter four 2017/2018Report 388 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 13 attended
CB
Charles BaileyCommittee Member, apologies, sent representative
SB
Sandy BayleyCouncil Staff, in attendance
KB
Kevin BulmerCo-Chair, present
SH
Simon HewingsOfficer, in attendance
DH
Dudley HoddinottCommittee Member, present
SH
Simon HowellCo-Chair, present
WJ
William JacobsOfficer, in attendance
TN
Toby NewmanCommittee Member, present
CP
Chris PalmerCommittee Member, present
RP
Richard PullenSubstitute, present as substitute
RS
Ron SchrieberOfficer, in attendance
HS
Henry SpencerCommittee Member, absent

All 13 on the meeting page

On this subject at South Oxfordshire

Search all
  1. Internal audit activity report quarter four 2017/2018This decision
  2. Internal audit annual report 2025/2026Noted
  3. Internal Audit Report Q1 2026/27Decided
  4. Internal audit plan 2026/27Approved
  5. Internal audit update report Q3 2025/26Decided
  6. New Global Internal Audit Standards in the UK Public Sector & Updated Internal Audit CharterNoted

More from South Oxfordshire Joint Audit and Governance Committee

All decisions
MeetingDecisionOutcome
7 Jul 2026 Annual Review of Complaints 2025/26That the committee noted: (a) the formal complaints received in 2025-26 and the councils’ performance in responding t... Noted Open
7 Jul 2026 Statement of accounts 2025/26 updateThat the committee (a) Noted progress on completing the 2025/26 Statement of Accounts and on the external audit build... Noted Open
7 Jul 2026 Internal audit annual report 2025/2026That the committee considered and noted the annual internal audit opinion and report. Noted Open
7 Jul 2026 Internal Audit Report Q1 2026/27RESOLVED : That the committee reviewed the results of recent internal audit work and monitored progress of management... Decided Open
7 Jul 2026 Internal audit plan 2026/27RESOLVED : That the committee approved the internal audit plan 2026/27. Approved Open